Maximum bid price (former tender price ceiling) compilation framework and cost composition under GB/T 50500-2024
State-funded projects must set a maximum bid price (the former tender price ceiling), compiled and reviewed by the tenderer or a commissioned cost consultant, published in detail with the tender documents, and not to be raised or discounted; compilation basis: the seven items of GB/T 50500-2024, Clause 5.2.1. Cost composition: divisional and elemental work costs (pre-tax fully loaded all-in unit rate, including risk costs and auxiliary work costs) plus preliminaries (statutory safety provisions, non-competitive) plus other-item costs (provisional sums, provisional prices, dayworks, general contractor's service fee, etc.) plus taxes (VAT listed separately). Note the 2024 edition abolishes the separate line item for statutory fees, absorbing them into the all-in unit rate - different from the 2013 edition and some local documents; confirm the applicable edition before compiling.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB 50500-2013 建设工程工程量清单计价规范
- 招标投标法实施条例 第27条
- DB22/T 5036-2020
- DB37/T 5161-2020
Topic Positioning
This card maps Chapter 5 'Maximum bid price' (the former tender price ceiling) of GB/T 50500-2024, Standard for Valuation of Construction Works with Bills of Quantities: compiling entity, compilation basis, cost composition and easily missed items, for quick checking during ceiling-price compilation, review and bid clarification.
Core Conclusions
(i) State-funded projects must set a maximum bid price, and the tenderer may not set a minimum bid price; the ceiling is compiled and reviewed by a capable tenderer or a commissioned cost consultant, one per project only, published in detail with the tender documents, and shall not be raised or discounted. (ii) Compilation basis (Clause 5.2.1): the valuation standard and the quantity calculation standard; the tender documents with addenda, clarifications and modifications; national and provincial-sector pricing regulations; relevant technical standards and codes; item description, ground and hydrological conditions and site circumstances; reasonable duration and conventional process sequence; engineering price information and cost data indices. (iii) Cost composition: divisional and elemental work costs (all-in unit rate = labor cost + material cost + construction plant usage cost + management fee + profit + risk cost within the agreed range + auxiliary work costs, a pre-tax all-in price excluding VAT) + preliminaries (technical measures + organizational measures; the statutory safety provisions accrue per national and provincial regulations and is non-competitive) + other-item costs (provisional sums, provisional prices for specialist works, dayworks, general contractor's service fee, employer-supplied materials, etc.; provisional prices already containing VAT must not be double-counted) + taxes (VAT listed separately). (iv) Easily missed in practice: risk costs, auxiliary work costs, material price differentials, provisional sums, dayworks, general contractor's service fee.
Applicable Boundaries
Confirm the applicable edition first: GB/T 50500-2024 has abolished the separate statutory-fee line item (social insurance and housing fund absorbed into labor unit prices and management fee rates), whereas the GB 50500-2013 system and some local pricing documents still treat statutory fees and taxes as separate non-competitive items whose rates must match the tender documents. The two regimes must not be mixed, and the old five-part composition must not be applied to the 2024 edition. This card does not cover minimum bid prices, evaluation benchmark prices or other ceiling-price forms.
Further Reading
See GB/T 50500-2024, Chapter 5 (5.2.1 compilation basis, 5.2.5 preliminaries, 5.2.6 other-item costs, 5.2.8 price references from similar works), Term 2.0.9 and Clauses 3.1.6/3.1.7 on the all-in unit rate; Implementation Regulations of the Tendering and Bidding Law, Article 27; for local supplements see Jilin DB22/T 5036-2020, Shandong DB37/T 5161-2020 and other pricing administration rules.
Keywords
Cited By
- ←
Where statutory levies went after the 2024 BOQ pricing system dropped them as a separate line: social insurance and housing fund for production workers into labour cost; social insurance and housing fund for management staff and the works pollution charge (environmental protection tax) into overheads; urban maintenance and construction tax and surcharges likewise into overheads
The levies were not abolished but 'unbundled and no longer separately listed': GB/T 50500-2024 clause 3.1.2 makes the BOQ four parts - the works bill, the bill of preliminaries, the bill of provisional sums and other charges, and value added tax - leaving no slot for statutory levies at BOQ level; clause 3.1.6 requires the all-in unit rate and the item price to be 'fully inclusive pre-tax prices excluding VAT', which semantically absorbs the former levies into labour cost and overheads. The concrete destinations are fixed by the provincial expense norms: social insurance and housing fund for production workers (construction workers) go into labour cost; social insurance and housing fund for management staff and the works pollution charge (adjusted to the environmental protection tax under state provisions) go into overheads; urban maintenance and construction tax, education surcharge and local education surcharge also go into overheads.
- ←
Full workflow for preparing the tender bill of quantities: preparing entity and object, the seven bases of preparation, itemisation with the five elements and item description, the four-part BOQ composition, deliverables and appendix forms, error liability, and the interface with the tender price ceiling
Chapter 4 of GB/T 50500-2024 provides: the bill of quantities is prepared by a tenderer with preparation capability or by a construction cost consultant commissioned by it (4.1.1); it is itemised with the contract object or a single project or individual structure as the object and forms part of the tender documents (4.1.2); the deliverables comprise the cover, signature page, explanatory notes of the estimate, notes on measurement rules, and the BOQ and pricing forms (4.1.3), in forms B.1.1, C.1.1, D.4.1, E.1.1/E.2.1/E.2.3/E.3.1/E.4.1 to E.4.5/E.5.1 and G.1.1. The BOQ is prepared and priced in four parts -- the work-item BOQ, the preliminaries BOQ, the other items BOQ and VAT (3.1.2) -- and the current edition no longer carries a statutory levies and taxes section; the all-in unit rate and the sum are fully inclusive pre-tax prices excluding VAT, tax is entered under VAT, and the provisional sum for nominated specialist subcontract works already includes VAT and must not be taxed again (3.1.6).
- ←
Re-examination of compilation errors in the tender price ceiling (renamed the maximum acceptable tender price in GB/T 50500-2024), bidder objections and complaint handling: the GB 50500-2013 route of '5-day complaint + order to rectify when the error exceeds +/-3%' versus the GB/T 50500-2024 Clauses 5.3.3 and 5.3.4 route of objection - referral - re-publication
GB 50500-2013: a bidder which, on re-check, considers that the tender price ceiling was not compiled in accordance with the code shall complain to the tendering and bidding supervision authority and the construction cost administration institution within 5 days after publication (Clause 5.3.1); where the re-examination result differs from the published price by more than +/-3%, the tenderer shall be ordered to rectify (Clause 5.3.8). GB/T 50500-2024 removes the fixed percentage and the fixed day count: where the re-examination conclusion deviates significantly from the published maximum acceptable tender price, the tenderer shall explain and revise (Clause 5.3.3); a bidder may object in writing to the tenderer within the prescribed time, and where the tenderer fails to correct it reasonably, the bidder may refer the matter to the administrative supervision and administration department, and the price must be re-published under that department's procedures (Clause 5.3.4).
- ←
Cost items expressly excluded from the all-in unit rate in BOQ-based pricing (VAT, statutory levies and fees, main contractor's attendance and coordination provisions, provisional sums, employer-borne costs, statutory safety provisions), the correct billing position of each, and audit identification of mixed allocation
Under GB/T 50500-2024 Clause 2.0.9 the all-in unit rate 'includes labour cost, material cost, plant and small tools cost, management cost, profit and risk costs within a defined range, and excludes VAT', and Clause 3.1.6 makes it a 'fully inclusive price excluding VAT'. Hence VAT (charged at the summary level under Clause 3.2.11), main contractor's attendance and coordination provisions (Clauses 2.0.17, 3.2.9 and 4.2.6, listed separately in the bill of provisional sums and other charges by item or by percentage rate), provisional sums (Clauses 2.0.13 and 8.3.1, at the employer's disposal and not owned by the contractor), the price of employer-supplied materials with their delivery and unloading charges and the material cost of the employer-borne permitted wastage (Clauses 3.2.4 and 6.2.4), and statutory safety provisions (Clause 3.2.5, non-competitive and separately listed in the bill of preliminaries) must not enter the all-in unit rate of work items; the 2024 edition cost composition no longer has a 'statutory levies and fees' heading (the five insurances and one housing fund for production workers now go into labour cost, and those for management staff plus the construction effluent fee go into overheads), so adding a separate statutory levies heading and charging it again is an error.
- ←
Labour cost pricing basis within the all-in unit rate: norm-based labour cost (base-period workday rate) versus current-period published labour price information and labour market prices, the applicable rules at the tender price ceiling and tender stages, and the test that the labour cost differential and the labour cost inside the all-in unit rate are not adjusted twice
Labour cost in the all-in unit rate = norm (budget) labour consumption x the current-period labour rate (published price information or a market price confirmed by the parties): consumption is locked to the quota manual while the rate is opened to the current-period market (GB/T 51095-2015, clause 5.3.9). The base-period workday rate published with the quota manuals is not itself the pricing input for BOQ rate build-up; it is a component of norm-based labour cost and the comparison base of the labour cost differential. At the tender price ceiling stage the published labour rates / published price information take precedence (GB/T 50500-2024, clauses 5.2.1 and 5.2.8); the tender is priced freely by the tenderer on its in-house norms and the market, but not below cost and not above the tender price ceiling (clauses 6.1.1, 6.1.3, 6.2.1). Differentials caused by changes in costs carry VAT only, not overheads or profit (clause 3.3.5); the same labour differential may be taken once only, in either the current-period-price pricing system or the base-period-price-plus-differential system, and must not be stacked on the labour cost already inside the all-in unit rate.
- ←
Reading the all-in unit rate pricing schedule of the fee quota norms line by line: charging bases (labour cost / labour cost plus plant and small tools cost), the order of charging (overheads, profit, risk cost -> all-in unit rate; pre-tax project cost -> VAT -> unit works cost), and a comparison of provincial bases (Shaanxi 2025 tables 5-1/5-2/5-3; Hubei 2024) with sector bases (highway form 08; railway table 2.6.2)
The main line of the all-in unit rate pricing program: labour, materials and plant (including dynamic adjustment / price differentials) -> direct cost subtotal -> overheads and profit (base: 'labour cost plus plant and small tools cost'; some provinces use 'labour cost') x rate -> (the Hubei basis adds a separate risk-factor line) -> all-in unit rate = the sum of all items; unit works cost = element works + preliminaries + other items = pre-tax (net-of-tax) project cost, then x VAT rate and added. In the Shaanxi 2025 'Shaanxi construction works fee rules', table 5-2 (base = labour cost plus plant and small tools cost) and table 5-3 (base = labour cost) list the social security costs of construction workers separately into the all-in unit rate as labour cost x rate, and table 5-1 places VAT after 'pre-tax project cost'; in the Hubei 2024 fee quota norms, overheads / profit = (labour cost + plant and small tools cost) x rate with the risk factor alone on line 6, while Annex 4 (tender price ceiling program) still keeps an independent 'statutory levies and fees' line (a trace of the 2013 BOQ basis). Highway JTG 3830-2018 form 08: preliminaries / overheads take quota labour cost + quota plant cost (or quota direct cost) as base, statutory levies take labour cost as base, profit takes (quota direct cost + preliminaries + overheads) as base, and taxes and duties take (direct cost + preliminaries + overheads + statutory levies + profit) as base.
- ←
Judging the synonymy of the tender price ceiling and the maximum tender price ceiling, the rejection rule for tender offers above the ceiling, and the item-by-item comparison of the compilation bases of the three and the division of their roles in tender evaluation and contract price formation
The tender price ceiling (GB 50500-2013 Clause 2.0.45) and the maximum tender price ceiling (GB/T 50500-2024 Clause 2.0.19) are one and the same thing renamed: the 2013 definition itself uses 'maximum tender price ceiling' as the genus, and the 2024 definition matches item by item in compiling entity, compilation basis elements and the function of capping tender offers. The tender offer (2013 Clause 2.0.46: the lump total stated after summing the priced BOQ) is the bidder's autonomous responsive price and must fall between the cost line and the ceiling line: under Article 51 item (5) of the Implementation Regulations for the Tendering and Bidding Law (State Council Decree No. 709, 2019 revision), where a tender offer is below cost or above the maximum tender price ceiling set in the tender documents, the tender evaluation committee shall reject the bid; the corresponding pricing-standard clauses are GB 50500-2013 Clause 6.1.5 and GB/T 50500-2024 Clause 6.1.3.
- ←
Composition of the tender bill of quantities: the five parts of GB 50500-2013 (bill of divisional and elemental work items, bill of preliminaries, bill of provisional sums and other charges, bill of statutory levies, bill of taxes and duties) with the itemisation rules of each, and the composition contrast under GB/T 50500-2024
GB 50500-2013 Clause 4.1.4: the tender bill of quantities shall be compiled with the individual work (or project) as the unit and shall consist of the bill of divisional and elemental work items, the bill of preliminaries, the bill of provisional sums and other charges, and the bills of statutory levies and of taxes and duties. Under Clause 4.4.1 the bill of other charges contains provisional sums, provisional prices (provisional unit prices for materials, provisional unit prices for permanent plant, provisional prices for nominated specialist works), dayworks, and the main contractor's attendance and coordination provisions; under Clause 4.5.1 statutory levies cover social insurance contributions (old-age, unemployment, medical, work-injury and maternity), the housing provident fund, and the works pollution discharge fee; under Clause 4.6.1 taxes and duties cover business tax, city maintenance and construction tax, the education surcharge and the local education surcharge. GB/T 50500-2024 Clause 3.1.2 instead compiles and prices the bill of divisional and elemental work items, the bill of preliminaries and the bill of other charges together with value added tax (the statutory levies and tax bills are no longer set up; the tax becomes value added tax, computed per Clause 3.2.11 by multiplying the total of the three bills, after deducting the provisional prices of nominated specialist works, by the VAT rate).
- ←
Layered build-up of the fully loaded all-in rate: the base chain from labour, materials and plant through overheads, profit, statutory levies and taxes; the three charging-base regimes; why percentage rates cannot be added directly; and the cost boundary and conversion against the BOQ all-in unit rate (which excludes statutory levies as a separate line and VAT)
The fully loaded all-in rate must be built up layer by layer: overheads and profit are usually charged on labour cost plus plant and small tools cost, or on labour cost alone; statutory levies mostly on labour cost; VAT on the fully inclusive price excluding VAT. Each layer has a different, progressively larger base, so multiplying one base by (1 + the sum of the rates) overstates the result (a worked example overstates by about 33%). The correct chain is D = A + B + C -> overheads E and profit F charged on their own bases -> fully inclusive price excluding VAT P = D + E + F -> VAT T = P x t -> Q = P + T. The BOQ all-in unit rate under GB/T 50500-2024 cl. 2.0.9 and 3.1.6 is a pre-tax price excluding VAT (cl. 3.1.2's four BOQ categories no longer list statutory levies separately); the conversion is fully loaded all-in rate Q = (BOQ all-in unit rate Qc + statutory levies R) x (1 + VAT rate t).
- ←
The VAT charging base of the bill of quantities and the non-duplication of tax on provisional sums for specialist works (GB/T 50500-2024 clauses 3.2.11 and 3.1.6)
VAT = [work-item list + preliminaries list + other-items list (less the provisional sums for specialist works)] total x the VAT rate set by the authorities; the specialist provisional sums are VAT-inclusive, and no further tax may be charged on them (clauses 3.2.11 and 3.1.6). Under general taxation the construction rate is 9% (price and tax separated); under the simplified scheme the levy rate is 3% (factor prices carry input tax, the base being the tax-exclusive works cost that already includes input tax).
- ←
Whether the all-in unit rate includes statutory levies and taxes: comparison and determination between BOQ-based pricing (non-fully-loaded) and the fully loaded all-in rate
Whether the all-in unit rate includes statutory levies and taxes depends on the pricing basis: under GB/T 50500-2024 BOQ-based pricing it excludes value added tax (VAT) (a price-exclusive tax listed separately) and no longer lists statutory levies and fees as a separate item (social insurance and housing fund contributions are amortized into labour cost and the overheads percentage rate); under the fully loaded all-in rate basis (GB/T 51095-2015 Clause 6.2.3, DB42/T 823-2021, DB14/T 1319-2021 highway) it includes statutory levies and fees and taxes. Confirm the applicable basis before pricing and review; the two sets must never be mixed.
- ←
Reviewing tender bills of quantities: methods and criteria for detecting omissions, errors, and duplications
Check the BOQ against four baselines—tender documents, construction drawings, measurement standards, and the pricing standard: omissions via drawing cross-check + standard appendix tick-off + item description derivation + preliminaries check; errors via codes (twelve digits, no duplicate codes within one project), item descriptions (standard, concise, accurate, complete), units and quantities, and work-content attribution (operations must not be split); duplications via duplicate codes, substantively identical items, split-out operations, and overlaps between work items and preliminaries. Per GB/T 50500-2024 Article 4.1.4: BOQ defects are borne by the employer under unit-rate contracts (adjusted per Section 8.2) and by the contractor under lump-sum contracts (not adjusted per Article 6.1.7).
- ←
GB/T 50500-2024 VAT pricing basis: all-in unit rates are fully inclusive prices excluding VAT, with VAT listed and assessed separately
BOQ item all-in unit rates and their totals are fully inclusive prices excluding VAT (labour cost + material cost + plant and small tools cost + management fee + profit + agreed risk costs + indispensable auxiliary work costs), with taxes and duties listed separately under VAT; the VAT base = the combined amounts of the bill of quantities for divisional and sub-divisional works + the bill of preliminaries + the bill of provisional sums and other charges (less provisional sums for nominated specialist subcontract works) x the prescribed rate; provisional sums for nominated specialist subcontract works are tax-inclusive provisional amounts, on which VAT is no longer assessed.
- ←
Definitions, cost composition and applicable conventions of the direct-cost rate, the all-in unit rate and the fully loaded all-in rate compared (Order No. 107 of the Ministry of Construction, GB/T 50500-2024, GB/T 51095-2015, etc.)
The three rate conventions widen in scope in turn: the direct-cost rate (labour plus materials plus plant only, with on-costs, profit and taxes computed separately) is contained in the all-in unit rate (labour plus materials plus plant and small tools plus overheads plus profit plus risk fees within the agreed band; GB/T 50500-2024 clause 2.0.9 expressly excludes VAT, which is carried separately), which is contained in the fully loaded all-in rate (further including statutory levies and taxes, tax-inclusive; GB/T 51095-2015 clause 6.2.3 requires its use for the tender price ceiling and tenders). Note that the "all-in rate method" defined in Order No. 107 of the Ministry of Construction is a fully loaded unit rate - the same name as, but different content from, the "all-in unit rate" of current BOQ pricing; the "all-in rate" of highway works is likewise a wide convention including statutory levies and taxes (and additionally equipment procurement cost and preliminaries).
- ←
Checking tender prices for omitted taxes and duties, statutory levies and fees, and preliminaries (edition basis → tax back-calculation → levy rates → preliminaries comparison)
Four-step check for omitted taxes and duties / statutory levies and fees / preliminaries: ① confirm the pricing edition basis first (2013: five costs listed separately vs 2024: statutory levies and fees embedded in all-in unit rates, only VAT listed separately); ② taxes and duties — check the rate and the base (work items + preliminaries + bill of provisional sums and other charges, net of provisional sums for nominated specialist subcontract works), and verify by back-calculation: total price ÷ 1.09; ③ statutory levies and fees — check completeness of the listed items and consistency of percentage rates (non-competitive; must exactly match the tender documents / provincial rates); ④ preliminaries — compare item by item against the project execution plan (construction methodology and site organization), with a dedicated check on the non-competitive mandatory health, safety and environmental (HSE) provisions; under the 2024 edition a cost-breakdown table must be submitted with the tender.
- ←
Should the construction-installation cost in a design estimate carry provisional sums? — the stage division of provisional sums (BOQ/contract level) vs reserve funds (estimate level)
No. The construction-installation cost (works cost) in a design estimate must not carry provisional sums. Provisional sums are a contract-price account of BOQ pricing (construction tendering and implementation) (defined in GB/T 50500-2024, 2.0.13; scope limited by 1.0.2; employer-controlled, unused portions revert, 8.3.1); the estimate's uncertain/unforeseeable costs are carried by the reserve funds (basic + price-difference) in the total estimate, whose composition — works costs + other construction costs + reserves + construction-period loan interest + VAT (T/ZBD 100.3-2022, 4.1.1 and Annex A) — has no "provisional sum" account.
- ←
Linked measurement of the VAT burden rate and contract gross margin (weighted composite input deduction rate + sensitivity analysis)
For construction projects under the general VAT method: VAT burden rate = 9% − (1 − gross margin) × composite input deduction rate r, with r weighted by cost structure (materials 13% special invoices, machinery rental 9%, labor subcontracting 3% simplified, self-performed labor with no input). The sensitivity of the burden rate to the gross margin = r (derivative with respect to the margin; e.g., with r = 8%, each 1-point rise in margin raises the burden rate ≈0.08 points). Adding VAT surcharges (12%) and enterprise income tax (25%), the composite tax burden sensitivity ≈ 25% + 1.09r ≈ 0.34 (at r = 8%) — each extra point of gross margin has about one third eaten by incremental taxes.
- ←
Pricing rules for prime-sum estimates (provisional sums) of specialist works: GB/T 50500-2024 VAT-inclusive, lump-sum per item, deduction from the VAT base, and substitution on adjustment (compared with GB 50500-2013)
GB/T 50500-2024 defines the prime-sum estimate of specialist works as "specialist-work costs estimated VAT-inclusive where requirements and price cannot be fixed at tendering" (2.0.15, excluding works directly awarded by the employer), listed under the other-items list, priced by lump-sum per item (3.2.7); the VAT base is the total of work-item, preliminaries, and other-items lists (excluding the specialist prime sum), so VAT is not charged on it again (3.1.6, 3.2.11); on adjustment, mandatory-tender items are wholly replaced by the winning VAT-inclusive subcontract price (8.4.1), others may be priced VAT-inclusive per Section 8.10 or jointly tendered by both parties (8.4.7). Compared with GB 50500-2013's vague "comprehensive prime sum including management fee and profit other than fees and taxes" (Section 4.4), the rules are refined in price basis, pricing-mode classification, VAT treatment, and substitution.
- ←
Preparing the subcontract control price and the subcontract target price: concept distinction, preparation bases, inversion check, and linking the two prices
The subcontract control price is the enterprise's internal maximum bid limit for subcontract tendering (referring to GB/T 50500-2024 Clause 5.2.1, prepared by the market or cost method, and must pass the inversion check of not exceeding the corresponding main contract revenue item); the subcontract target price is the internal expected cost (integrated into the target cost system per GB/T 50326-2017 Clause 11.2.4: bid-cost separation + estimation on the basis of the contractor's in-house norms, decomposed by contract section/responsible department, effective upon approval by the authorized person). Relationship of the two: control price <= corresponding main contract revenue item, target price <= control price; the transaction price falling between the two is optimal, with dynamic correction by three-cost comparison.
- ←
Method for formulating bid pricing strategy: project features -> total price level -> unit-rate structure -> compliance floor
Bid pricing strategy = total price level (how much to bid) x unit-rate structure (how to allocate), determined by project features x competitive situation x own conditions; standards only set the floor framework. Four steps: (1) translate project features into pricing signals across evaluation method, works type/scale, BOQ accuracy, contract risk allocation, payment terms, schedule, and competition; (2) set the total price in three tiers (high/competitive/low, floor = not below corporate cost); (3) design the unit-rate structure (unbalanced bidding, premised on the tender documents allowing it and confident direction of quantity differences); (4) check substantive clauses item by item, pass unit-rate reasonableness, analyze contracting risks per the standard.
- ←
Correspondence between the subcontract BOQ and the main contract BOQ: four-layer mapping of scope, BOQ elements, price, and fees
The subcontract BOQ is not built from scratch but the implementation-level refinement (projection) of the specialist-works portion of the main contract BOQ, and the two must be reconcilable item by item: (1) scope without overlap or omission; (2) the five elements (code/name/features/unit/calculation rules) consistent item by item, with codes reusable from the main contract; (3) on price, the specialist works provisional sum is wholly replaced by the tax-inclusive awarded price of the subcontract tender (material provisional sums are pre-tax prices — do not mix calibers); (4) measure costs are included in the subcontract total without double counting, the general contractor's service fee is listed separately on the main contractor side, and progress payments flow along the employer → main contractor → subcontractor chain.
- ←
"Tender control price" and "tender price ceiling" are one and the same thing: term unification in GB/T 50500-2024 and the 2013→2024 changes in preparation requirements (basis of preparation, price sources, publication requirements, reasonable construction duration)
"Tender control price" and "tender price ceiling" are one and the same thing: GB/T 50500-2024 China national pricing standard for BOQ (effective 1 September 2025) uniformly renames the "tender control price" of the GB 50500 system as the "tender price ceiling" (ceiling price, Clause 2.0.19) and deletes the former term; Clause 3.3.1 of GB/T 50875-2013 had already defined the "tender control price" as "the tender price ceiling of the tendered works". Changes in preparation requirements: (1) the basis of preparation (Clause 5.2.1, eight items) no longer centres on "pricing quota norms + published construction cost information" but on "provisions on measurement of the works and pricing + project price information, construction cost data and indices", so that preparation may be based on market price information and construction cost data; (2) price sources (Clause 5.2.8) are opened up to six categories of market-based information (tender price ceilings, construction-drawing based budgets (pre-tender estimates), design estimates (approved cost ceilings) and cost estimates of similar works, competitive tender unit rates, settlement unit rates, contract prices, market price enquiry, price indices); (3) the publication requirement (Clause 5.1.1) makes it clear that the total price and the basis and method of preparation are to be published when the tender documents are issued; (4) a reasonable construction duration dimension is added (Clause 5.2.1 item 6 and the final paragraph).
- ←
Scope of GB/T 50500-2024: state-funded works shall use BOQ pricing (compulsion now carried by MOHURD Order No. 16), others should/may choose freely, compared with GB 50500-2013
Per GB/T 50500-2024 Clause 3.1.1: works invested with fiscal or state-owned funds "shall" prepare BOQs per national and industry measurement standards and use BOQ pricing; non-state-funded works "should", and may choose other methods (3.1.5 allows percentage-fee and other pricing where unit-price/lump-sum pricing is unsuitable, provided the pricing requirements and adjustment rules are stated in tender and contract documents). The 2024 edition changed from a mandatory GB (50500-2013) to recommended GB/T - "must" became "shall", mandatory provisions repealed - but the practical rule "state-funded works must use BOQ pricing" is not relaxed: compulsion is carried by Article 6 of the "Measures for pricing of construction contracting" (MOHURD Order No. 16): such works "shall adopt BOQ pricing".
- ←
Distinguishing the basis of the all-in unit rate from that of the fully loaded all-in rate (incl. taxes and specified on-costs): composition differences, applicable scenarios, and risks of mixed use
Narrow-sense all-in unit rate = labour cost + material cost (including engineering equipment) + plant and small tools cost + overheads (company and site) + profit + risk cost within the agreed scope and risk band (no-adjustment tolerance, e.g. ±5%), excluding statutory levies and fees and value added tax (VAT) (GB/T 50500-2024 Clause 2.0.9, VAT being a price-exclusive tax listed separately); the fully loaded all-in rate (incl. taxes and specified on-costs) = the above + statutory levies and fees + taxes and duties (VAT under the current standard), tax-inclusive (GB/T 51095-2015 and other consultancy/local bases). Note that the 2024 edition's "fully inclusive price excluding VAT" means all costs are included but VAT is still excluded — different from the industry-conventional fully loaded all-in rate (incl. taxes and specified on-costs). A single project must adopt a consistent basis; mixing the two leads to total-price miscalculation.
- ←
Three bases for the composition of the construction price: cost elements, BOQ-based pricing, and final-account listing
The construction price (cost of works (construction and installation)) has three composition bases: (1) by cost elements (GB/T 50875-2013 Clause 2.2.10) = labour cost + material cost + construction machinery usage cost + management fee + profit + statutory levies and fees + taxes and duties (VAT under the current standard); (2) by BOQ-based pricing (GB/T 50500-2024) = divisional/sub-divisional works cost + preliminaries + other-item cost + VAT — the 2024 edition abolishes the separate statutory-levies item, the all-in unit rate being a fully inclusive price excluding VAT, and the VAT base deducting provisional sums for nominated specialist subcontract works; (3) by final-account listing (Clause 10.3.2) — 13 items. Mind the differences between the 2013 and 2024 bases when comparing.
- ←
GB/T 50500-2024 vs GB 50500-2013 edition change: all-in unit rate composition changes and the repositioning of statutory levies and fees and taxes and duties in the BOQ-based pricing system
The 2024 edition removes "statutory levies and fees" entirely from the BOQ system (no longer listed; the mandatory "shall not be competitive" clause canceled); taxes and duties become value added tax (VAT) listed separately at the summary level (= total of summarized list prices x VAT rate); the all-in unit rate is explicitly a fully inclusive price excluding VAT (labour cost + materials + plant and small tools cost + management fee + profit + agreed-scope risk + indispensable auxiliary work costs); "overheads (company and site)" is renamed "management fee". The 2013 edition excluded statutory levies and fees and taxes and duties indirectly via mandatory provisions of codes; 2024 declares "excluding VAT" directly in the term definition. The standard changed from mandatory GB to recommended GB/T, effective 2025-09-01 with the 2013 edition abolished.
- ←
GB/T 50500-2024 replacing GB 50500-2013: what GB becoming GB/T means, expiry of the 2013 mandatory provisions, and the 2025-09-01 effective date
MOHURD Announcement (No. 212 of 2024, issued 2024-11-26) approved the "Standard for measure and valuation of construction work with bills of quantities" as national standard GB/T 50500-2024, effective 1 September 2025, repealing GB 50500-2013 simultaneously. GB = mandatory national standard, GB/T = recommended (Standardization Law, 2017 revision, Article 2: mandatory standards must be executed; adoption of recommended standards is encouraged); all 2013 mandatory provisions expire with the standard, and the 2024 edition sets no mandatory provisions. Typical contrast: 2013 Clause 3.1.1 (mandatory) "works contracted with state-owned funds must use BOQ pricing" becomes 2024 3.1.1 with fiscal/state-funded works "shall" and others "should" use BOQ pricing. The binding force of a recommended standard is realized through incorporation in tender documents and contracts.
- ←
Price-taking time point for the tender price ceiling: the latest issue of price information published as at the date of completion of preparation; "28 days before the tender deadline" is the adjustment base price time point, not the price-taking time point
The tender price ceiling (employer's maximum acceptable price) takes prices at the price level of the preparation period: use the latest issue (month/quarter) of construction cost price information published as at the date of completion of preparation, noting the issue in the deliverable; where a difference from actual construction-period conditions exists, adjust reasonably (GB/T 50500-2024 Clause 5.2.9). "28 days before the tender deadline" (for works not subject to tendering, 28 days before the date of contract signing) is the lock-in time point for the contractual adjustment base price C₀ in Appendix A.2.1, used for adjustment for cost fluctuation after award, and is unrelated to price-taking for the tender price ceiling.
- ←
Main contractor's attendance and coordination fee: bases to which percentage rates are applied and rates — calculation bases for the three service targets, the C = A × B pricing formula, construction payment settlement adjustment, and tender price ceiling estimation (GB/T 50500-2024)
Main contractor's attendance and coordination fee = calculation base A × rate B (or a lump sum entered directly under a total-price package). Bases for the three targets: (1) materials/works equipment provided by the employer (free-issue) -> supply contract price; (2) specialized subcontracted works (within the contract, not executed by the contractor) -> the subcontract's contract price; (3) directly awarded specialized works (outside the contract) -> that specialized works' contract price. The national standard sets only rules, not rates; where the fee is priced per item the risk is lumped and no adjustment is made in the construction payment settlement, while where it is priced by rate and no base is agreed, it may be adjusted in the construction payment settlement on the contract price. Local rate references (Hubei 2024 norms for on-costs and expenses): pure management and coordination 1.5%, with attendance services 3%–5%, employer-supplied (free-issue) materials 1% of value.
- ←
GB/T 50500-2024 Appendix E pricing cost summary: Table E.1.1 summary hierarchy (project → single project → unit work) and aggregation rules for billed items, preliminary items, other charges and VAT
GB/T 50500-2024 Appendix E contains a single general summary table — Table E.1.1 "Project summary table" — using three-level numbering (1 → 1.1 → 1.1.1) to express the project → single project → unit work hierarchy; Note 2: "This table is preferably used for the summary calculation of works where the contract subject is the object of preparation of the bill of quantities; works where a single project or unit work is the object of preparation of the bill of quantities may also be summarised using this table." Aggregation rules: billed (BOQ) item costs (the only level expanded down to unit-work detail) roll up level by level; preliminary items (with 2.1 safety-production preliminary items listed separately) and other charges (broken out into provisional sums / provisional sum for nominated specialist subcontract works / dayworks / main contractor's attendance and coordination provisions / other items agreed in the contract) are summarised at whole-project level; VAT is listed separately and its calculation base excludes the provisional sum for nominated specialist subcontract works (Note 1); total = 1+2+3+4. All-in unit rates are fully inclusive prices excluding VAT (Clause 3.1.6, term 2.0.9); statutory levies and fees are no longer listed separately in the 2024 edition, having been merged into management fee; settlement follows Table E.6.1, with amounts adjusting for errors and omissions in the BOQ entered respectively under "contract price adjustment amount" of billed items and preliminary items.
- ←
Quantifying advance-funding pressure when contract payment proportions are too low, and standard floors (GB/T 50500-2024: 80% progress payments, 10%-30% advance payment)
Every 10-point drop in the payment proportion adds roughly 10% of the contract amount in advance funding: peak advance = (1 - payment proportion) x contract amount; average advance ~= peak/2; annual financing cost ~= average advance x annual rate. GB/T 50500-2024: progress payments should not be below 80% of cumulative completed work value (9.1.7); in-process settlement not below 80% (10.2.4); advance payment not below 10% and not above 30% of contract price (9.2.2). Advance funding stacks migrant-wage, supply-chain, and tax-prepayment chain risks; the Regulation on Payment to SMEs (30/60-day terms and overdue interest) can be invoked for relief.
- ←
Price bases and setting procedure for the material procurement maximum price limit (internal control price / tender price ceiling)
The material maximum price limit = base price × (1 ± adjustment coefficient). Price basis priority: contract-agreed/confirmed price > published price information (government guidance prices) (a base reference only, not to be selected directly) > market inquiry (≥3 quotes from different suppliers, countersigned by multiple parties with records) > recent transaction prices of similar projects (adjusted for differences in construction period, scale and delivery standard). Five setting steps: approved inquiry-pricing implementation plan → organized market inquiry with countersigning → supplier prequalification and quote review → correction of differences → finalization with records and an inquiry ledger. The basis is unified as the tax-inclusive delivered all-in price, with the capital cost of the payment credit period converted in. State-funded projects must set a maximum tender price ceiling, publish it with the tender documents, must not raise or lower it after preparation, and must not set a minimum tender price.
- ←
A six-dimension framework for unifying cost-data calibers across projects (cost composition / quantities / tax / time / allocation / tagging)
Caliber unification = fixing one set of "comparable benchmarks" across six dimensions: (1) cost composition unified to the fully loaded all-in rate basis (covering labour, materials, plant, overheads, profit, statutory levies and fees and taxes); provincial quota systems often state only that it "should" be adopted, so a conversion comparison table must be built and kept on file as an audit trail; (2) quantities unified to BOQ quantities or quota quantities and labelled; (3) prices stored uniformly tax-exclusive with the taxation method recorded; (4) time basis: the feasibility-stage estimate, the preliminary estimate and the tender price ceiling take the date the deliverable was completed, the contract price takes the commencement date, and the settlement price takes the completion date, with cross-period conversion via construction cost indices (base date 2017-01-01, index 1000); (5) allocation rules unified by project-type templates; (6) labelling across four dimensions: region – project type – cost type – time. Basis: GB/T 51095-2015, GB/T 50500-2024, GB/T 51290-2018, etc.
- ←
Four-step back-calculation of the minimum acceptable profit rate for bid pricing, and the statutory floor
The minimum acceptable profit rate is back-calculated from corporate individual cost: minimum bid P_min = corporate individual cost C + minimum acceptable profit pi_min, rate r_min = pi_min / P_min. pi_min comprises financing cost (interest on advances/deposits), risk premium (changes, material inflation, lump-sum risks), allocated fixed costs (head-office overhead), and the strategic floor. Statutory floors: the bid must not be below cost nor above the maximum bid price (GB/T 50500-2024 Article 6.1.3); below-cost bids shall be rejected at evaluation, obviously lower bids require written cost justification. The cost basis is corporate individual cost (measured via corporate quotas); calculation worksheets must be retained.
- ←
Appendix D “Pricing Statements” of GB/T 50500-2024: required contents of the four statement tables and dispute risks of omissions (tender price ceiling / tender (priced offer) / final account statement + method of measurement statement for the bill of quantities (BOQ))
GB/T 50500-2024 Appendix D has four statement tables: D.1.1 tender price ceiling preparation (review) statement must include project overview, scope, basis of preparation (review), special requirements (if any), and other issues to be explained; D.2.1 tender (priced offer) statement must include scope, item description (work item specification), planned duration, site conditions, project execution plan (construction methodology and site organization) features, and other issues to be explained; D.3.1 final account (interim) preparation (review) statement must include project overview, scope, basis of preparation (review), and other issues; D.4.1 statement of method of measurement for the BOQ must specify the names and numbers of the national/industry measurement standards adopted and list supplementary rules of measurement (with 4.1.3). Omitting basis details, scope delimitation, supplementary rules of measurement, and explanations of price and percentage rate determination (GB/T 51095-2015 8.2.3) are high-frequency final account dispute triggers.
- ←
Definition and cost composition of the all-in unit rate (GB/T 50500-2024 Clause 2.0.9, GB/T 50875-2013 Clause 2.2.58)
All-in unit rate = labour cost + material cost (including engineering equipment) + plant and small tools cost + overheads (company and site) + profit + risk cost within the agreed scope and range, required to complete one specified unit of measurement of a billed (BOQ) item; VAT is excluded (a price-exclusive tax). Basis: GB/T 50500-2024 Clause 2.0.9 and GB/T 50875-2013 Clause 2.2.58; building works BOQ-based pricing uses the "incomplete-cost" caliber excluding statutory levies and fees and taxes, while highways and other industries may use the fully loaded caliber including statutory levies and fees and taxes — confirm the applicable industry standard before citing.
- ←
GB/T 50500-2024, China's BOQ pricing standard: positioning, 2024-vs-2013 changes, chapter map and card-group navigation
GB/T 50500-2024, the China national pricing standard for BOQ-based pricing (MOHURD Announcement No. 212 of 2024, approved 26 November 2024), came into force on 1 September 2025 and repealed GB 50500-2013. Its status shifted from a partly mandatory code to a recommended national standard (GB to GB/T), aiming to regularise pricing rules and let the market form construction costs. It governs pricing activity in tendering, contracting and execution for construction works; EPC and other general-contracting models apply it by reference, and the requirement that state-funded projects use BOQ pricing is carried by a MOHURD ministerial order. Nine headline revisions (per the foreword): risk scope and allocation rules by contract form; a new bid clarification mechanism; revised pricing of preliminaries; the 'contract price agreement' chapter replaced by contract selection and requirements; revised measurement and adjustment rules; site visas abolished and additional-works pricing introduced; interim settlement by construction stage added; dispute resolution revised; the cost-expert-assessment chapter deleted. The structure was rebuilt from 16 chapters into 12 chapters plus annexes: 'tender control price' renamed tender price ceiling; completion settlement and contract-termination settlement merged into 'works settlement and payment' (absorbing stage settlement); dispute resolution and expert assessment merged; pricing tables moved to annexes (with a new Annex G, schedule of price-adjustable key materials).