Maximum bid price (former tender price ceiling) compilation framework and cost composition under GB/T 50500-2024

State-funded projects must set a maximum bid price (the former tender price ceiling), compiled and reviewed by the tenderer or a commissioned cost consultant, published in detail with the tender documents, and not to be raised or discounted; compilation basis: the seven items of GB/T 50500-2024, Clause 5.2.1. Cost composition: divisional and elemental work costs (pre-tax fully loaded all-in unit rate, including risk costs and auxiliary work costs) plus preliminaries (statutory safety provisions, non-competitive) plus other-item costs (provisional sums, provisional prices, dayworks, general contractor's service fee, etc.) plus taxes (VAT listed separately). Note the 2024 edition abolishes the separate line item for statutory fees, absorbing them into the all-in unit rate - different from the 2013 edition and some local documents; confirm the applicable edition before compiling.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB 50500-2013 建设工程工程量清单计价规范
  • 招标投标法实施条例 第27条
  • DB22/T 5036-2020
  • DB37/T 5161-2020

Topic Positioning

This card maps Chapter 5 'Maximum bid price' (the former tender price ceiling) of GB/T 50500-2024, Standard for Valuation of Construction Works with Bills of Quantities: compiling entity, compilation basis, cost composition and easily missed items, for quick checking during ceiling-price compilation, review and bid clarification.

Core Conclusions

(i) State-funded projects must set a maximum bid price, and the tenderer may not set a minimum bid price; the ceiling is compiled and reviewed by a capable tenderer or a commissioned cost consultant, one per project only, published in detail with the tender documents, and shall not be raised or discounted. (ii) Compilation basis (Clause 5.2.1): the valuation standard and the quantity calculation standard; the tender documents with addenda, clarifications and modifications; national and provincial-sector pricing regulations; relevant technical standards and codes; item description, ground and hydrological conditions and site circumstances; reasonable duration and conventional process sequence; engineering price information and cost data indices. (iii) Cost composition: divisional and elemental work costs (all-in unit rate = labor cost + material cost + construction plant usage cost + management fee + profit + risk cost within the agreed range + auxiliary work costs, a pre-tax all-in price excluding VAT) + preliminaries (technical measures + organizational measures; the statutory safety provisions accrue per national and provincial regulations and is non-competitive) + other-item costs (provisional sums, provisional prices for specialist works, dayworks, general contractor's service fee, employer-supplied materials, etc.; provisional prices already containing VAT must not be double-counted) + taxes (VAT listed separately). (iv) Easily missed in practice: risk costs, auxiliary work costs, material price differentials, provisional sums, dayworks, general contractor's service fee.

Applicable Boundaries

Confirm the applicable edition first: GB/T 50500-2024 has abolished the separate statutory-fee line item (social insurance and housing fund absorbed into labor unit prices and management fee rates), whereas the GB 50500-2013 system and some local pricing documents still treat statutory fees and taxes as separate non-competitive items whose rates must match the tender documents. The two regimes must not be mixed, and the old five-part composition must not be applied to the 2024 edition. This card does not cover minimum bid prices, evaluation benchmark prices or other ceiling-price forms.

Further Reading

See GB/T 50500-2024, Chapter 5 (5.2.1 compilation basis, 5.2.5 preliminaries, 5.2.6 other-item costs, 5.2.8 price references from similar works), Term 2.0.9 and Clauses 3.1.6/3.1.7 on the all-in unit rate; Implementation Regulations of the Tendering and Bidding Law, Article 27; for local supplements see Jilin DB22/T 5036-2020, Shandong DB37/T 5161-2020 and other pricing administration rules.