Price bases and setting procedure for the material procurement maximum price limit (internal control price / tender price ceiling)
The material maximum price limit = base price × (1 ± adjustment coefficient). Price basis priority: contract-agreed/confirmed price > published price information (government guidance prices) (a base reference only, not to be selected directly) > market inquiry (≥3 quotes from different suppliers, countersigned by multiple parties with records) > recent transaction prices of similar projects (adjusted for differences in construction period, scale and delivery standard). Five setting steps: approved inquiry-pricing implementation plan → organized market inquiry with countersigning → supplier prequalification and quote review → correction of differences → finalization with records and an inquiry ledger. The basis is unified as the tax-inclusive delivered all-in price, with the capital cost of the payment credit period converted in. State-funded projects must set a maximum tender price ceiling, publish it with the tender documents, must not raise or lower it after preparation, and must not set a minimum tender price.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第5.2.1/5.2.8/5.2.9条
- DB37/T 5096-2017 建设工程项目管理咨询规范 第6.5.1/6.5.2条
- DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范 第7.6.4条
- GB/T 50358-2017 建设项目工程总承包管理规范 第6.2.1/6.3.3条
- GB/T 50430-2017 工程建设施工企业质量管理规范 第8.2.2条
Topic Positioning
This card covers how to set material/equipment procurement maximum price limits (two scenarios: the enterprise's internal procurement control price and the tender maximum price ceiling): the priority of price bases, the five-step setting procedure, and the compliance red lines — reusable by construction enterprise procurement posts and tenderers/agents.
Core Conclusions
The limit is in essence "base price × (1 ± adjustment coefficient)"; price basis priority: ① contractually agreed/confirmed prices rank highest; ② the cost authority's published price information (government guidance prices) serves as a base reference, but it must not be selected directly — it must match the design parameters and project positioning and be consistent with market price levels; ③ market inquiry — for the same material, no fewer than 3 quotes, taking a reasonable range; ④ recent transaction prices of similar projects (settlement unit prices, contract prices, cost estimates) as the fallback, reasonably adjusted for differences in construction period, construction standard, project scale, delivery requirements, material source and other factors (GB/T 50500-2024, Clauses 5.2.8, 5.2.9). Five setting steps: prepare the inquiry-pricing implementation plan (background and purpose, specifications/quantities/expected prices, supplier scope, organization and responsibilities, methods and procedures, timing) approved by the employer → organize the market inquiry, forming records countersigned by multiple parties → supplier prequalification → qualified supplier list → quote review → clarification if necessary → correction of differences → finalize and archive the inquiry materials, build the inquiry ledger, and enter the data into the price information database (DB37/T 5096-2017, Clauses 6.5.1, 6.5.2; GB/T 50358-2017, Clause 6.2.1; DBJ/T 15-153-2019, Clause 7.6.4). The limit basis must be unified as the "tax-inclusive delivered all-in price", and the capital cost of the payment credit period must be converted into the comparison.
Applicable Boundaries
Applies to setting material/equipment procurement limits for construction enterprises; in tender scenarios, state-funded projects must set a maximum tender price ceiling that must not be raised or lowered after preparation, and no minimum tender price may be set (a floor is illegal). Not applicable to labour/specialist subcontract pricing. Limits on sharply fluctuating principal materials should be updated dynamically (e.g., 15–30 day validity); where published price information is unavailable, rely on market inquiry. Local standards (DB37/T, DBJ/T 15-153) are process references only — the current rules in force at the project location prevail.
Further Reading
GB/T 50500-2024, Standard for Valuation of Construction Works with Bills of Quantities, Clauses 5.2.1, 5.2.8, 5.2.9 (preparation bases and use of price information); DB37/T 5096-2017 Clauses 6.5.1, 6.5.2 (inquiry-pricing implementation plan and market inquiry countersigning); DBJ/T 15-153-2019 Clause 7.6.4 (inquiry ledger and price information database); GB/T 50358-2017 Clauses 6.2.1, 6.3.3 (procurement procedure and inquiry comparison); GB/T 50430-2017 Clause 8.2.2 (five elements of supplier evaluation).
Keywords
- 材料采购限价
- 最高限价
- tender price ceiling
- 询价定价实施方案
- market price enquiry
- 含税到场综合价
- 采购控制价
- enquiry register (log)