Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Price fallback paths when the project location lacks published price information for a material: contractual agreement → alternative channels → market price enquiry → employer's approval of material prices → expert assessment backstop

Missing published price information is backfilled in steps: ① contractual agreement takes precedence; ② alternative channels (price information issued by cost-administration departments or industry bodies, and the detailed price composition of analogous billed (BOQ) items; railway compilation-period prices are determined by the design unit through investigation and analysis); ③ market price enquiry (three classified channels — market price / published price information / vendor quotations — dominated by real transaction prices, strictly not mixed, with a documented audit trail); ④ report to the employer for approval of material prices before procurement; failure to reply within the time limit is deemed approval (GB/T 50500-2024, Appendix A.2.5); for materials covered by a provisional sum, once confirmed by the employer the pre-tax price is substituted (8.4.5); ⑤ in dispute, construction cost expert assessment (judicial appraisal) follows signed-and-approved price > contract-agreed price > mutually agreed price (GB/T 51262-2017, Clause 5.6.4). Completing the price approval procedure before procurement is the key to success at settlement.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 51262-2017 建设工程造价鉴定规范
  • T/ZBD 100.1-2022 建设工程造价数据建设通用标准
  • TB 10811-2024 铁路基本建设工程设计概(预)算费用定额

Topic Positioning

How a price is determined when the project location has not published price information for a material (missing item) — the stepwise fallback path of contractual agreement, alternative channels, market price enquiry, the employer's approval of material prices, and construction cost expert assessment.

Core Conclusions

① Where the contract already stipulates a pricing method for materials without published price information, the contract governs; ② alternative channels — price information issued by cost-administration departments or industry bodies, together with the detailed analysis schedules of analogous billed (BOQ) items (GB/T 50500-2024, Clause 8.6.3); railway compilation-period prices are determined by the design unit through investigation and analysis (TB 10811-2024, Clause 2.2.3); ③ market price enquiry — market price, published price information and vendor quotations as three classified channels, dominated by real transaction prices, strictly not mixed (T/ZBD 100.1-2022, Clause 7.2.3), with a documented audit trail; ④ the employer's approval of material prices (key) — report to the employer for verification and confirmation before procurement; failure to reply within the time limit is deemed approval (Appendix A.2.5); for materials covered by a provisional sum, once confirmed the pre-tax price is substituted (Clause 8.4.5); ⑤ dispute backstop — construction cost expert assessment (judicial appraisal) follows signed-and-approved price > contract-agreed price > mutually agreed price (GB/T 51262-2017, Clause 5.6.4).

Applicable Boundaries

Applies to backfilling missing material prices at the compilation, price adjustment (for fluctuation) and settlement stages under BOQ-based pricing, premised on there being no contrary contractual agreement; not directly applicable to labour or machine-shifts. Where published price information is normally issued, it remains the preferred baseline for price adjustment and the dispute backstop.

Further Reading

GB/T 50500-2024, Clauses 8.4.5 and 8.6.3 and Appendix A.2.5; GB/T 51262-2017, Clause 5.6.4; T/ZBD 100.1-2022, Clause 7.2.3; TB 10811-2024, Clause 2.2.3.

Keywords

Cited By