Published price information vs actual procurement price: issuing body, basis and timeliness, settlement effect (practice comparison)
The published price information is a regional statistical composite price periodically issued by cost management agencies (monthly/quarterly issues, lagging, excluding brand, batch, haul distance and payment terms); the actual procurement price is the enterprise's real current transaction price (including brand/model, batch, haul distance and freight, payment terms, VAT rate, bargaining power and other specifics) — either can be higher or lower: batch purchase plus cash payment is often below the published price information, while small-batch urgent purchase or long-distance haul is often above. The published price information is used for tender price ceilings, contract-agreed adjustment base prices and dispute fallback references; the procurement contract price and the invoice price only prove actual cost and must first be confirmed by the employer as an agreed material price (certified record of agreed material prices) before being upgraded to a basis for settlement.
Applicable Codes
- GB/T 50875-2013 工程造价术语标准
- T/ZBD 100.1-2022 建设工程造价数据建设通用标准
Topic Positioning
Clarifies the essential difference between "published price information" and "actual procurement price": the former is a regional guidance price issued by cost management agencies, the latter is the enterprise's real transaction price — and their differences in basis, timeliness and settlement effect.
Core Conclusions
- Different issuing bodies: the published price information is periodically issued by provincial/municipal cost management agencies as a statistical composite average for a region and issue period (month/quarter), lagging the previous period's market and excluding specific brand, batch, haul distance and payment terms; the actual procurement price comes from real transactions (procurement contract, invoice, payment voucher), specific to an individual transaction. 2) Different basis: the actual procurement price embeds immediate current conditions — brand/model, purchase batch, haul distance and freight, payment terms, VAT rate, supplier bargaining power — so it can be above or below the published price information: batch purchase plus cash payment is often below; small-batch urgent purchase or long-distance haul is often above. 3) Different effect: the published price information is used to prepare tender price ceilings, contract-agreed adjustment base prices and dispute fallback references; the procurement contract price and the invoice price only prove actual cost and become a basis for settlement only after the employer's confirmation of the price (certified record of agreed material prices); the priority of settlement bases is contract agreement > joint confirmation by both parties > published price information > market price enquiry. 4) When the gap is notable (deviation around ±5%-10% as the attention line), first check the basis — taxes and duties, delivery terms, specification, batch, issue period — before judging reasonableness.
Applicable Boundaries
Applies to material price management in construction works, preparation of tender price ceilings, contract price adjustment and settlement disputes; published price information, market prices and vendor quotations must be developed as classified data through the three channels and must never be mixed. Not applicable to single-point price lookups, nor a substitute for the pricing clauses agreed in the contract.
Further Reading
Terminology: GB/T 50875-2013 "Standard for construction cost terminology" clause 2.1.16 "construction cost information"; three-channel classification rules: T/ZBD 100.1-2022 "General standard for construction cost data development" clause 7.2.3; certified price records, adjustment base prices and the priority of settlement bases follow the contract and the pricing/settlement provisions of GB/T 50500-2024.