Handling rules when the price-information issue and the construction month are misaligned (GB/T 50500-2024 Appendix A adjustment)
Price-information adjustment takes the issue corresponding to the measurement period (the month of completion), not the publication time; where the current issue is unpublished, provisionally use the nearest published issue and refund or supplement the difference later per actual prices (A.2.2); a measurement period spanning multiple issues uses the arithmetic mean / weighted mean / price of the main-consumption period (A.2.3); the base price C0 is locked 28 days before the bid submission deadline and does not drift with construction (A.2.1, A.2.4).
Applicable Codes
- GB/T 50500-2024 App. A.2.1~A.2.5
- GB/T 50875-2013 第2.1.16条
- T/ZBD 100.1-2022 第7.2.3条
Topic Positioning
How to take prices for adjustment when the publication time of price information misaligns with the construction month: take prices per the issue of the measurement period (the month of completion), not the publication time; where the current issue is unpublished, adjust provisionally and settle the difference later; where periods are crossed, average by segment. Basis: GB/T 50500-2024 Appendix A.
Core Conclusions
(1) Price-taking principle: the measurement-period market price Ci must represent the current market price level of the measurement period (A.2.1); therefore match the issue corresponding to the month of completion, regardless of publication order — price information has a collection/statistics lag, and the issue label is the criterion. (2) Current issue published: take that issue's price directly. (3) Current issue unpublished: provisionally compute the difference with the nearest published issue (A.2.2), and after that issue is published, refund or supplement the difference per actual prices in subsequent payments; where that issue simply does not exist (publication suspended or quarterly only), provisionally use the previous measurement period's price information. (4) One measurement period spanning multiple issues: choose one of three per the contract — arithmetic mean within the issues, weighted mean of quantity and price, or the price of the main-consumption construction period (A.2.3). (5) The base price C0 is locked 28 days before the bid submission deadline (for non-tendered works, 28 days before contract signing) and does not drift with construction; whether the quoted price is lower/higher/equal to the base price determines the overrun calculation basis (A.2.4). (6) First check the contract; where unclear, follow the above rules; measure completed works by segments corresponding to the adjustment periods, each segment matched to its issue's price information, and mark progress payments "provisionally adjusted" to prevent treating them as final.
Applicable Boundaries
Applies to price fluctuation adjustment under the price-information adjustment method for BOQ-priced contracts; the index method follows the same logic of using the previous period when no current index exists (A.1.2). Where the contract expressly agrees the price-taking issue, the contract prevails. Not applicable to provisional-price material substitution (Section 8.4 has different rules) or pure market purchases without contract constraints; price information serves only as the adjustment basis and dispute backstop, not as a single-point pricing basis.
Further Reading
GB/T 50500-2024 Code for BOQ pricing of construction works, Appendix A: A.2.1 (adjustment formula and Ci caliber), A.2.2 (provisional adjustment and later correction), A.2.3 (cross-period averaging), A.2.4 (relation between base price and quoted price), A.2.5 (pre-purchase submission; deemed acceptance upon overdue silence); segmented measurement see Clause 7.1.3; the term "project cost information" see GB/T 50875-2013 Clause 2.1.16; three-channel classification of price information/market prices/manufacturer quotations see T/ZBD 100.1-2022 Clause 7.2.3.