base price (reference price for adjustment)

14 knowledge cards · sorted by most recently updated

Concept Guide

Concept

In Chinese construction pricing, the base price (reference price for adjustment) is the locked unit rate for labour, materials or machinery entered in the tender or contract. It is drawn from the GB 50500 system and from published price information issued by local cost authorities. The contractor compares this base price with the market price at an agreed reference point, often shortly before tender submission; movement within a stated risk band is borne by the contractor, and movement beyond it is adjusted. Adjustment is normally initiated by the contractor's claim, reviewed by the employer or cost consultant, and paid as a price difference in interim or final payments. The risk band, adjustable elements and source of the base price should be stated in the particular conditions.

FIDIC Mapping

Chinese term FIDIC term Relation Note
base price (reference price for adjustment) Base Date (Sub-Clause 1.1.4) adjacent FIDIC fixes a date, not a unit rate; no adjustment threshold
risk band Adjustments for Changes in Cost (Sub-Clause 13.7) absent No self-borne band; index movement from Base Date adjusts directly
cost index base Schedule(s) of cost indexation (Sub-Clause 13.7) adjacent Both use indexation; FIDIC uses coefficients a, b, c… and indices Ln, En, Mn
published price information / quota norms published price information / quota norms distinct China often uses government-published prices; FIDIC relies on the contract schedule

Key differences lie in trigger, data source, risk allocation and procedural rigidity. Under Sub-Clause 1.1.4 the Base Date is 28 days before the latest date for tender submission. Under Sub-Clause 13.7, if a schedule of cost indexation is included, amounts are adjusted for rises or falls in cost. The fixed coefficient a represents the non-adjustable portion, while b, c, d… represent estimated proportions of cost elements. If no schedule is included, Sub-Clause 13.7 does not apply.

Caution: do not equate the Chinese base price with FIDIC Base Date. One is a unit rate with a risk band; the other is a date. Without a contract index schedule, 13.7 gives no adjustment route.

Chinese TermEnglish TermFIDIC TermRelationNotes
基准价base price (reference price for adjustment)Base Date (Sub-Clause 1.1.4)adjacentFIDIC 用基准日锁定投标截止前 28 天的状态,不设要素基期单价;中国基准价是具体人工/材料单价并与风险幅度联动,超出幅度才调,FIDIC 指数自基准日变动即调。
风险幅度risk bandAdjustments for Changes in Cost (Sub-Clause 13.7)absentFIDIC 13.7 无自担阈值带,合同含指数表时按公式直接加扣;中国风险幅度是承包人自担波动区间,制度逻辑不同。
指数基期/造价指数cost index base period / cost indexSchedule(s) of cost indexation (Sub-Clause 13.7)adjacent均以指数调差,但 FIDIC 用固定系数 a 与 b、c、d… 及 Ln、En、Mn 指数,总系数不超过 unity;中国常用地方造价信息价,数据源与刚性不同。
基准日Base DateBase Date (Sub-Clause 1.1.4)distinctBase Date 是日期锚点,用于判断法律与物价变化;中国基准价是价格锚点。两者名称相近但语义不同,不可互换。