Rules for determining the construction-period price (measurement-period market price Ci) in material adjustment (GB/T 50500-2024 appendix A.2)
The construction-period price is the measurement-period market price Ci in the adjustment formula — the same three source options as the base price C0 (market price confirmed by both parties / the cost agency's current guidance price / same-period analogous winning-bid prices at the trading center) and must represent the current price level of the measurement period; multiple prices within a period take the arithmetic mean, the quantity-weighted average against completed quantities, or the price for the main-usage period, the order agreed by the parties; absent price information, adjust provisionally by the guidance price and true up later; the procurement-price method requires reporting to the employer for confirmation before purchase, non-response within the agreed time deemed acceptance; on schedule delay, take the higher of the planned and actual progress-date prices where the employer is at fault, the lower where the contractor is.
Applicable Codes
- GB/T 50500-2024 App. A.2.1~A.2.5
- GB/T 50500-2024 第8.7.2/8.7.4条
- GB/T 50500-2024 App. A.1.5
- GB/T 50500-2024 App. G.2
Topic Positioning
This card answers a high-frequency material-adjustment dispute: how the construction-period price — the "measurement-period market price Ci" — is determined, per GB/T 50500-2024 appendix A.2 and section 8.7.
Core Conclusions
(1) Ci source, one of three, same caliber as the base price and representing the current price level of the measurement period: market price confirmed by both parties; the cost agency's current guidance price; same-period analogous winning-bid prices at the trading center; the source is written by the employer into the tender documents, objections clarified before bidding. (2) Multiple prices in one period: arithmetic mean, quantity-weighted average against completed quantities, or the price for the main-usage period — method and order agreed by the parties. (3) No price information or major disputes: adjust provisionally by that period's guidance price and true up in later payments. (4) Procurement-price method: report quantities and unit prices for confirmation before purchase; batch purchases averaged by weights; no response within the agreed period deemed acceptance. (5) Schedule delay: employer-caused — take the higher of the planned and actual progress-date prices; contractor-caused — the lower; caused by neither, per clause 8.7.2 — the party at fault must not profit.
Applicable Boundaries
Applies to the price-information adjustment method (appendix A.2, table G.2.1-1); the index-method counterpart is A.1.5 (table G.2.1-2). Preconditions: the contract has defined the adjustable material scope (appendix G.2) and risk band (absent agreement, fluctuation beyond 5% is adjustable). The difference carries VAT only, no management fee or profit; the base price is locked 28 days before bid closing.
Further Reading
See GB/T 50500-2024 appendix A.2.1 (formula and Ci sources), A.2.2 (provisional adjustment), A.2.3 (multiple-price treatment), A.2.5 (procurement-price confirmation), A.1.5 (index method), clause 8.7.2 (5% trigger), clause 8.7.4 (delayed-schedule pricing).
Keywords
Related Cards
- →
Priority of price bases for construction payment settlement: contract agreement > price confirmed by both parties > published price information > market price enquiry (purchase contract / invoice prices require the employer's approval of material prices)
Bases for settlement by priority: ① contract-agreed price (fundamental basis); ② price confirmed by the employer and contractor (certified record of agreed material prices — report quantity and unit price to the employer for verification before purchase; deemed approval upon lapse of the response period); ③ published price information (base price for adjustment / dispute fallback); ④ market price enquiry (for provisional sums and materials without published prices). Purchase contract prices and invoice prices only prove actual cost and become a basis for settlement only after the employer's approval of material prices.
- →
Steel price adjustment calculation: price-information adjustment formula, per-specification per-period threshold checks with adjustment on actual basis, and tax treatment (GB/T 50500-2024 Appendix A.2)
Steel price adjustment uses the price-information adjustment method (GB/T 50500-2024 Appendix A.2): △P = Σ[(Ci − C0·(1±r)) × Q] × (1 + VAT rate), adjusting only the portion beyond the risk band on an actual basis; the agreed risk band prevails, with the beyond-5% fallback where not agreed or unclear (8.7.2). Each specification must be checked independently each period for exceeding the risk band (base prices, published price information, and increase rates differ; specifications within the risk band are not adjusted for the period); the price difference carries VAT only, no management fee or profit (3.3.5); when checking adjustment tables, first look at whether the bid price is above or below the base price (A.2.4 determines the excess-calculation base).
- →
Guidance price vs market price: definition sources, essential difference and role positioning (official term definitions + three-channel classification rule)
The guidance price (construction cost information) is the labor/material/plant-shift price information plus cost indices and indicators periodically published by cost management agencies — a reference, guidance price (GB/T 50875-2013 clause 2.1.16); the market price is the actually transacted price, acquired mainly through transactions. The two differ essentially; per T/ZBD 100.1-2022 clause 7.2.3 they must be developed as data under the three channels market/guidance/vendor-quotation prices, strictly never mixed. Guidance prices serve maximum bid prices, adjustment base prices and dispute fallbacks; market prices serve actual procurement cost verification, filling gaps of materials without guidance prices, and — after joint confirmation — as settlement bases.
- →
Framework for distinguishing quantity risk from price risk in contracts: risk objects, responsible parties, and quantified trigger lines (GB/T 50500-2024)
Quantity risk governs "how much is built" (BOQ defects, quantity changes and item additions/deletions from changes); price risk governs "how much per unit" (input prices and all-in unit-rate levels). On allocation, Article 3.3.2 lists owner risks (unit-rate BOQ defects, erroneous source data, approved changes, legislative changes, beyond-band fluctuations); Article 3.3.3 lists contractor risks (preliminaries lists, total-price BOQ defects, own technical/management risks, within-band fluctuations). Quantified triggers: quantity change 15% (8.9.1/8.9.2); price fluctuation 5% or the contract-agreed band (8.7.2/8.7.6).
- →
The mechanism for determining the scope of price-adjustable materials and typical categories (GB/T 50500-2024 appendix G.2)
GB/T 50500-2024 sets no statutory "list of price-adjustable materials": the employer and contractor define the scope of adjustable main materials and lock it in as a contract annex by completing table G.2.1-1 (price-information adjustment method) or G.2.1-2 (price-index adjustment method) of appendix G.2; the statutory adjustable factors are only three classes — labor cost, main material cost, and fuel/power cost of construction plant; price differences carry VAT only, with no management fee or profit.
- →
Published price information vs actual procurement price: issuing body, basis and timeliness, settlement effect (practice comparison)
The published price information is a regional statistical composite price periodically issued by cost management agencies (monthly/quarterly issues, lagging, excluding brand, batch, haul distance and payment terms); the actual procurement price is the enterprise's real current transaction price (including brand/model, batch, haul distance and freight, payment terms, VAT rate, bargaining power and other specifics) — either can be higher or lower: batch purchase plus cash payment is often below the published price information, while small-batch urgent purchase or long-distance haul is often above. The published price information is used for tender price ceilings, contract-agreed adjustment base prices and dispute fallback references; the procurement contract price and the invoice price only prove actual cost and must first be confirmed by the employer as an agreed material price (certified record of agreed material prices) before being upgraded to a basis for settlement.
Cited By
- ←
Valuation rules for the four variables of material price adjustment (adjustment based on published price information) and the step-by-step calculation flow: base price C0, risk band r, measurement-period market price Ci and adjustable quantity Q (GB/T 50500-2024 Annex A.2)
The published-price-information method takes its values in five steps. (1) C0 = the market price level 28 days before the tender submission deadline (for non-tendered works, 28 days before the contract signing date), one source chosen from three (the market price used in setting the tender price ceiling / the quarterly (monthly) published price information of the cost administration body / award prices of comparable projects published for the same period by the trading centre); the tender documents must state the source, the issuing body and the specific quarter (month). (2) r: the contractual agreement prevails; where none exists or it is unclear, adjustment is allowed once the movement exceeds 5% (clause 8.7.2), the sign of r following the sign of dC (positive on increase, negative on decrease). (3) Ci takes the current price of the measurement period; with multiple prices, use the arithmetic mean / the weighted mean against executed quantities / the price over the main-consumption construction period; where a price is missing or disputed, published price information may be used provisionally and trued up later; purchase prices must be submitted to the employer for verification before purchase, silence within the time limit being deemed approval. (4) Q is calculated under the contractual quantity calculation rules. (5) Adjustment only where |Ci - C0| / C0 > r; on increase the excess unit differential = Ci - C0(1+r), on decrease = C0(1-r) - Ci; multiplied by Q it bears VAT only, with no overheads or profit.
- ←
Selecting between the two methods of contract price adjustment for changes in costs: comparison of applicable conditions, clause-by-clause contrast and same-contract mixing boundaries of the Appendix A.1 index-based adjustment and the Appendix A.2 adjustment based on published price information under GB/T 50500-2024
The two methods share an identical adjustable scope, base time point and trigger threshold (only labour cost, key material cost and the fuel and power cost of construction plant are adjustable; the base time point is 28 days before the tender deadline; where the contract sets no band or sets it unclearly, fluctuations beyond 5% are adjustable; the differential carries VAT only, never overheads or profit). The difference lies only in the price variable. A.1, index-based (formula) adjustment, takes the VAT-exclusive contract price P0 as the base and weights the fixed weight A and the variable weights B1...Bn of each adjustable factor by the ratio 'current index / base index' - the index source is agreed in the contract, the agreed fluctuation band is folded into the base price index, and where an index is missing the previous measurement period's index may be used provisionally. A.2, adjustment based on published price information, takes the adjustable factor quantity Q as the base and computes the money price differential between the base price C0 and the measurement-period market price Ci less the risk band coefficient r; the base price and the market price are each chosen from three sources (market price used in setting the tender price ceiling / published price information of the cost management agency / tender-winning prices published by the trading centre), whether the band is exceeded is determined by scenarios of the tender price against the base price, and under the purchase-price route the contractor must submit quantity and unit price to the employer for checking before purchase (no reply in time is deemed approval). The standard itself has no dedicated 'applicable conditions' clause, only 'one of the methods of Appendix A'; the choice is first a matter for the contract; where one contract assigns different methods to different adjustable factors, they must be entered separately in Table G.2.1-1 (published price information method) / Table G.2.1-2 (index method), without double counting the same differential.
- ←
Can published price information directly serve as the basis for material price adjustment: legality + three preconditions (listing / beyond band / tax) (GB/T 50500-2024)
Published price information (government guidance prices) is a price source expressly recognized for price adjustment (for fluctuation) (Appendix A.2.1: both the base price C0 and the measurement-period price Ci may adopt the current published price information issued by the cost management agency; A.2.4: where published price information serves as both base price and current price, adjust within the agreed risk band), but adjustment is not unconditional and full-scope: (1) the material must be listed in the contract annex "schedule of price-adjustable key materials" (Table G.2.1-1; not listed, not adjusted); (2) only the portion beyond the contract-agreed risk band is adjusted to actual, the band being contractor-borne; (3) where the contract sets no band, fluctuation beyond 5% is the fallback trigger (8.7.2). The price difference carries value added tax (VAT) only, not management fee or profit (3.3.5).
- ←
Composition of multi-month construction material published price information (government guidance prices): three methods for determining multiple market prices within a measurement period (GB/T 50500-2024 Appendix A.2.3 — arithmetic mean / quantity-weighted / price for the main consumption period)
Multi-month construction does not automatically mean weighting: when measuring monthly (or per agreed measurement period), each period takes its own market price Ci, differences computed and accumulated period by period — no prior weighting needed; only when one measurement period spans multiple price issues (e.g., quarterly measurement, monthly published price information (government guidance prices)) is Ci composed per A.2.3's three methods: (1) arithmetic mean, (2) weighted average with completed quantities, (3) price during the main-consumption construction period — method and priority order must be contractually agreed. Method choice directly flips threshold triggering — the same data can show +8.75% (arithmetic, exceeds the 5% risk band, adjustable) vs +4.13% (weighted, within the risk band, no adjustment); the composed Ci enters dP = sum[(Ci - C0(1 +/- r)) x Q] x (1 + VAT rate), with price differences subject to value added tax (VAT) only, not management fee or profit (3.3.5).
- ←
Price adjustment (for fluctuation) calculation for ready-mixed (commercial) concrete: whole-factor adjustment per m³, adjustment to actual beyond the risk band, and tax treatment (GB/T 50500-2024 Appendix A.2 adjustment based on published price information)
Ready-mixed concrete is adjusted as one whole adjustable factor per m³ (the published price information (government guidance prices) already includes raw-material cost; cement, sand/gravel, and admixtures must not be adjusted separately again, to avoid double counting), using the GB/T 50500-2024 Appendix A.2 adjustment based on published price information: beyond-band unit price difference = Ci - C0×(1+r) on a rise, or C0×(1-r) - Ci on a fall; adjustment amount = unit price difference × Q; the agreed risk band (no-adjustment tolerance, e.g. ±5%) prevails; where not agreed or unclear, fluctuation beyond 5% is the fallback trigger (8.7.2); the price differential attracts value added tax (VAT) only, not management fee or profit (3.3.5); where the tender price differs from the base price (reference price for adjustment), apply the A.2.4 cross-base rule against arbitrage. Worked example: C0=480 CNY/m³, Ci=530 CNY/m³, r=5%, Q=1000 m³; fluctuation 10.4% triggers; beyond-band unit difference 26 CNY/m³; adjustment 26,000 CNY; including 9% VAT the tax-inclusive amount is 28,340 CNY.
- ←
Appendix G main materials (adjustment) list of GB/T 50500-2024: locking stage and adjustment-quantity caliber (contract annex / completed quantities per measurement cycle)
Tables G.2.1-1/2 are filled during tendering and locked as a whole as a contract annex at signing: the tenderer fills scope/base price (market price level 28 days before the bid deadline)/risk band; bidders fill tender prices and agree price data in the tender-letter appendix (3.3.5 item 2, A.2.1). Adjustment quantities are neither tender quantities nor actual purchase quantities but follow "the quantity calculation method the parties specify in the contract" (table note 2, A.2.1); the default framework is quantities corresponding to completed qualifying work in the measurement cycle, measured in segments per adjustment cycle and accumulated (7.1.3).
- ←
Adjustment of the contract price (GB/T 50500-2024 Chapter 8): eleven triggering events, mechanism by section, and FIDIC mapping
Adjustment of the contract price is the mechanism for changing the contract price during performance. GB/T 50500-2024 Cl. 8.1.1 lists eleven triggering events: BOQ errors, provisional sums, PC sums (provisional estimates), contractor's services, dayworks, changes in costs, changes in laws and policies, variations, additional works, claims, and other events agreed by the parties; the procedure runs submit, check, re-check, review and confirm (8.1.2). Key mechanics: BOQ errors and variations share one re-rating ladder (identical items at contract rates; analogous items converted; different items negotiated), with a 15% quantity boundary for re-rating (8.2/8.9); provisional sums are controlled by the employer and any unused balance reverts at final account (8.3); PC-sum items are replaced by tender prices — materials pre-VAT, specialist works VAT-inclusive (8.4); dayworks are measured under 7.5 (certified dayworks records) and priced at the BOQ daywork rates (8.6, with deemed approval if verification is overdue, 7.5.5); changes in costs are adjusted beyond the agreed band — 5% by default — by index-based (formula) adjustment or adjustment based on published price information (8.7 + Annex A), the differential carrying VAT only; changes in laws pivot on the base date, adjusting price and/or time for enactments, amendments, repeals or new interpretations after it, with no upward adjustment during contractor-caused delay (8.8); additional works may follow contract rates or freshly negotiated rules under a supplementary agreement (8.10); claims cover events outside 8.2-8.10 — compensatory, not punitive, and mutual, with profit added for eight categories of employer-risk events (8.11). FIDIC counterparts sit scattered across Clause 13 (variation valuation 13.3, provisional sums 13.4, changes in laws 13.6, changes in cost 13.7 — 2017 numbering) and Clause 20 claims (28-day hard time bar): adjacent institutions, not chapter-for-chapter equivalents.
- ←
Pricing rules for cross-region material procurement: purchase-origin price + freight compose the delivered price; adjustment per contract and the price-confirmation procedure
Budget compilation does not force a binary "project location vs purchase location": material budget price = (material original price + freight within price) x (1 + procurement-and-keeping rate), the purchase-origin price serving as the original price and freight reflecting the inter-region difference; multi-source procurement is weighted by supply share. Settlement adjustment follows the contract first; absent agreement, the base price is the published price information (government guidance prices) for the project location or the mutually confirmed price 28 days before the bid deadline, the benefit of regional price differences accrues to the contractor, and prices must be submitted to the employer for confirmation before purchase — silence is deemed acceptance.
- ←
Price adjustment for wires and cables: itemized by full specification, copper-linkage agreements, and handling missing published price information (government guidance prices) (GB/T 50500-2024 Appendix A.2)
Cable price adjustment shares the same mechanism as steel (GB/T 50500-2024 Appendix A.2 adjustment based on published price information (government guidance prices)): difference = SUM[(Ci - C0 x (1 +/- r)) x Q], only the portion exceeding the risk band is adjusted on an actual basis; r as agreed takes precedence, and if not agreed, fluctuation beyond 5% is adjustable (8.7.2); C0 = market price 28 days before the tender deadline (= FIDIC Base Date) (for non-tendered projects: 28 days before contract signing); the difference carries value added tax (VAT) only, no management fee or profit. Cables must be listed item by item in Table G.2.1-1 by full specification (voltage class x cores x cross-section x armor x flame-retardance) and adjusted separately — merging and averaging is strictly prohibited; the copper-linkage method must fix in the contract the copper content/conversion coefficient and the copper-price source; for missing published price information, the paths are employer's approval of material prices / market price enquiry, with symmetric unit bases.
- ←
Building a material published-price-information vs actual purchase-price comparison table: four-segment table structure, deviation analysis, and the four-party certification and sign-off process
The comparison table = base segment (name/specification precise to the grade, unit, work location and period) + price segment (published price information stating the issuing agency, period, and tax-inclusive/delivered basis; purchase price on the same basis, side by side) + analysis segment (deviation rate = (purchase price − published price information)/published price information × 100%, each deviation explained and checked against the contract risk band) + signature segment (applicant/supervision/employer signatures and seals). Based on the GB/T 51095-2015 Appendix E.0.4 enquiry (price verification) form, extended with "published price information (agency + period)" and "deviation rate" columns; process: ≥ 3 enquiries → comparison → supervision price verification → employer confirmation before purchase (failure to reply within the time limit deemed acceptance) → contract at the approved price → archive into the price library. The signed and sealed comparison table is the certified record of agreed material prices — a basis for preparing the settlement.
- ←
Steel price adjustment calculation: price-information adjustment formula, per-specification per-period threshold checks with adjustment on actual basis, and tax treatment (GB/T 50500-2024 Appendix A.2)
Steel price adjustment uses the price-information adjustment method (GB/T 50500-2024 Appendix A.2): △P = Σ[(Ci − C0·(1±r)) × Q] × (1 + VAT rate), adjusting only the portion beyond the risk band on an actual basis; the agreed risk band prevails, with the beyond-5% fallback where not agreed or unclear (8.7.2). Each specification must be checked independently each period for exceeding the risk band (base prices, published price information, and increase rates differ; specifications within the risk band are not adjusted for the period); the price difference carries VAT only, no management fee or profit (3.3.5); when checking adjustment tables, first look at whether the bid price is above or below the base price (A.2.4 determines the excess-calculation base).
- ←
Which period's published price applies to settlement material prices: the two-date system — base price locked at the contract base date (28 days before bid closing) plus period-by-period pricing per measurement cycle (GB/T 50500-2024 Annex A.2 price-information method)
Settlement material prices are not taken from a single period (completion date or submission date) but from the "base price locked at the contract base date + current prices per measurement cycle" two-date system: base C0 at 28 days before bid closing (non-tendered: 28 days before contract signing); current Ci per measurement cycle from the cost authority's published price information (or jointly confirmed market prices, or same-period trading-center award prices); differences beyond the contractual risk band are computed per cycle and totalled into the final account; with no band agreed, a 5% fluctuation triggers adjustment; express contracts govern.
- ←
Cement price adjustment calculation: determining the adjustment object by usage path (site-mixed / ready-mixed concrete / direct purchase) + price-information adjustment method formulas and caliber points (GB/T 50500-2024 Appendix A.2)
Cement adjustment first fixes the object by usage path: site-mixed concrete/mortar and direct purchase adjust cement (CNY/t, quantity per mix-ratio cement usage or the employer-confirmed purchase quantity), ready-mixed concrete adjusts concrete (CNY/m3) with cement not separately adjusted (the published price information already includes raw-material costs, preventing double-counting). Formulas (Appendix A.2): rising overrun unit price difference = Ci − C0×(1+r), falling = C0×(1−r) − Ci, amount = unit price difference × Q; absent an agreed risk band, fluctuation beyond 5% triggers (8.7.2); the price difference carries VAT only, without management fee or profit (3.3.5); bagged/bulk calibers consistent, listed by type and strength grade, rising and falling adjusted symmetrically in both directions.
- ←
GB/T 50500-2024 rules for determining the base date: agreement first; tendered works = 28 days before the tender deadline, non-tendered works = 28 days before contract signing (term 2.0.21)
The base date (GB/T 50500-2024 term 2.0.21) is the date on which the contractor, during the tender period, determined the tender total price, the BOQ all-in unit rates and their sums, and it serves as the price datum for adjustment for changes in costs and for adjustment arising from changes in laws, regulations and policies. Determination order: agreement first, statutory fallback — where the tender documents (inquiry documents for non-tendered works) and the contract are silent, tendered works take 28 days before the tender deadline (= FIDIC Base Date) and non-tendered works 28 days before contract signing. That point is at once the base period of index-based (formula) adjustment (A.1.6), the base price C₀ of adjustment based on published price information (A.2.1), and the common starting point for adjustment for changes in laws, regulations and policies (8.8.1).
- ←
Material price adjustment channels under fixed lump-sum contracts: no adjustment within the agreed risk band, adjustment beyond the risk band, mandatory adjustment for statutory causes
Under a fixed lump-sum contract, cost fluctuations within the agreed risk band are not adjusted, but "fixed" ≠ an uncapped lump sum: ① contract-agreed price adjustment clauses are applied as agreed; ② where no risk band is agreed or the agreement is unclear, the portion of labour cost, principal material cost and construction machinery fuel and power cost fluctuating beyond 5% may be adjusted per Appendix A (8.7.2 fallback); the standard prohibits uncapped risk allocation to one party / "all risks" lump-sum wording (3.3.1), and cost movements beyond the agreed risk band are borne by the employer (3.3.2); ③ materials under government pricing/guidance pricing follow the new prices; ④ policy-driven adjustments to labour cost; ⑤ abnormal large fluctuations may be negotiated under the change of circumstances doctrine (8.7.3). Price adjustment claims under lump-sum contracts are procedurally handled as claims (T/ZBD 100.5-2023 3.1.7); price differences carry value added tax (VAT) only, no management fee or profit (3.3.5).
- ←
Cross-month material price adjustment: adjustment-period division and three methods for synthesizing multiple prices within a period (arithmetic mean / weighted mean with completed quantities / price of the main-consumption construction period)
Cross-month construction is not computed in a lump: adjust independently per the contractually agreed adjustment period (usually the measurement period, e.g., monthly) (8.7.1); where multiple market prices occur within one period, choose one of three per the symmetric provisions of Appendix A.2.3 (information method) / A.1.5 (index method) — arithmetic mean, weighted mean with completed quantities, or the price of the main-consumption construction period, with the weighted mean closest to actual cost; the three methods differ significantly, and the method and priority order must be agreed in the contract. Supporting: provisionally adjust per the published price information and correct later per actuals (A.2.2); the synthesized price and the base price C0 are compared symmetrically in the same caliber (A.2.1); price-taking under delays follows the responsible direction (8.7.4); the price difference carries VAT only, without management fee or profit (3.3.5).
- ←
Price reference time point for final account: adjust period by period per each measurement period's published price information (government guidance prices) during construction and aggregate; interim settlements by construction stage (China's 2020 milestone-based interim settlement system; no exact international equivalent) are incorporated without recomputation (not a single issue at the month of completion)
A final account has no 'single settlement-period price information': contractual agreement takes precedence; where adjustment is agreed, base price C0 locks the price for the period 28 days before the tender deadline (= FIDIC Base Date) (for non-tendered works, 28 days before contract signing), while measurement-period price Ci is taken period by period using the published price information (government guidance prices) issued for the corresponding construction completion period (month/quarter), adjusted and accumulated period by period; confirmed interim settlements by construction stage are incorporated directly into the final account without re-measurement or re-pricing; where the published price information for a given period has not been issued, that period's published prices may be used provisionally, with subsequent payments adjusted on an actual basis.
- ←
Handling paths when published price information clearly deviates from actual market prices: unify the bases of comparison first to exclude illusions, then correct by scenario (temporary adjustment with later true-up / price certification / expert assessment as fallback)
Published price information is only a reference guide price issued by the cost management agency (GB/T 50875-2013 Clause 2.1.16), not a mandatory price. On deviation, first unify the bases of comparison — VAT-inclusive/exclusive, delivered/ex-works, specification and unit — to exclude illusions; where an adjustment dispute is significant, temporarily use the current published price information and true up later against actual market prices, refunding the excess or paying the shortfall (GB/T 50500-2024 Appendix A.2.2); absent agreement or where the agreement is unclear, substitute the price confirmed by mutual market price enquiry and certify the price before purchase (deemed approval upon lapse of the response period, A.2.5); construction cost expert assessment ranks the certified-and-approved price > contract-agreed price > mutually agreed price (GB/T 51262-2017 Clause 5.6.4). Enquiries from >= 3 suppliers with records in a register; adjust only beyond the agreed risk band (5% if not agreed).
- ←
Overview of the full-chain use rules for construction cost published price information: nature, price calibers, stage-by-stage pricing, and frequent misconceptions
Published price information means reference guide prices issued by cost management agencies, running through the whole chain "price-limit compilation - bid verification - adjustment base - settlement fallback". Five iron rules: contract agreement first; caliber unification (tax-inclusive/exclusive, delivered/ex-factory, procurement-keeping fee); period alignment (base price locked 28 days before the bid deadline, measurement price matched to the measurement period); adjust only beyond band (±5% if not agreed); confirmation with records (submit to the employer before purchase, silence deemed acceptance).