Rules for determining the construction-period price (measurement-period market price Ci) in material adjustment (GB/T 50500-2024 appendix A.2)

The construction-period price is the measurement-period market price Ci in the adjustment formula — the same three source options as the base price C0 (market price confirmed by both parties / the cost agency's current guidance price / same-period analogous winning-bid prices at the trading center) and must represent the current price level of the measurement period; multiple prices within a period take the arithmetic mean, the quantity-weighted average against completed quantities, or the price for the main-usage period, the order agreed by the parties; absent price information, adjust provisionally by the guidance price and true up later; the procurement-price method requires reporting to the employer for confirmation before purchase, non-response within the agreed time deemed acceptance; on schedule delay, take the higher of the planned and actual progress-date prices where the employer is at fault, the lower where the contractor is.

Applicable Codes

  • GB/T 50500-2024 App. A.2.1~A.2.5
  • GB/T 50500-2024 第8.7.2/8.7.4条
  • GB/T 50500-2024 App. A.1.5
  • GB/T 50500-2024 App. G.2

Topic Positioning

This card answers a high-frequency material-adjustment dispute: how the construction-period price — the "measurement-period market price Ci" — is determined, per GB/T 50500-2024 appendix A.2 and section 8.7.

Core Conclusions

(1) Ci source, one of three, same caliber as the base price and representing the current price level of the measurement period: market price confirmed by both parties; the cost agency's current guidance price; same-period analogous winning-bid prices at the trading center; the source is written by the employer into the tender documents, objections clarified before bidding. (2) Multiple prices in one period: arithmetic mean, quantity-weighted average against completed quantities, or the price for the main-usage period — method and order agreed by the parties. (3) No price information or major disputes: adjust provisionally by that period's guidance price and true up in later payments. (4) Procurement-price method: report quantities and unit prices for confirmation before purchase; batch purchases averaged by weights; no response within the agreed period deemed acceptance. (5) Schedule delay: employer-caused — take the higher of the planned and actual progress-date prices; contractor-caused — the lower; caused by neither, per clause 8.7.2 — the party at fault must not profit.

Applicable Boundaries

Applies to the price-information adjustment method (appendix A.2, table G.2.1-1); the index-method counterpart is A.1.5 (table G.2.1-2). Preconditions: the contract has defined the adjustable material scope (appendix G.2) and risk band (absent agreement, fluctuation beyond 5% is adjustable). The difference carries VAT only, no management fee or profit; the base price is locked 28 days before bid closing.

Further Reading

See GB/T 50500-2024 appendix A.2.1 (formula and Ci sources), A.2.2 (provisional adjustment), A.2.3 (multiple-price treatment), A.2.5 (procurement-price confirmation), A.1.5 (index method), clause 8.7.2 (5% trigger), clause 8.7.4 (delayed-schedule pricing).