material price adjustment
Concept Guide
Concept
Material price adjustment is a standard price-adjustment mechanism in Chinese construction contracts, rooted in the GB 50500 bill-of-quantities valuation code and in local cost-management rules. For major materials such as steel, cement and concrete, the contract names a base price taken from published price information issued by the local cost authority before the tender deadline. The price published or actually paid during construction is compared with that base, and only the part exceeding an agreed risk band (commonly ±5%, always subject to the contract) is adjusted; movement inside the threshold is borne by the contractor. The adjustment equals the excess amount multiplied by the actual quantity consumed. It is normally initiated by the contractor with the interim payment application or at settlement, supported by invoices and published price documents, reviewed by the employer or engineer, and settled through interim payments or the final account rather than through a variation or claim procedure.
FIDIC Mapping
| Chinese term | FIDIC term | Relation | Note |
|---|---|---|---|
| material price adjustment | Adjustments for Changes in Cost (13.7) | adjacent | Same purpose, different trigger and data source |
| risk band | fixed coefficient 'a' (13.7) | adjacent | China uses a band; FIDIC uses a non-adjustable coefficient |
| cost indexation adjustment | Schedule(s) of cost indexation (13.7) | adjacent | No schedule means the sub-clause does not apply |
Key differences:
- Trigger: China relies on a contractual risk band; FIDIC 13.7 requires a Schedule of cost indexation, with coefficient a covering the non-adjustable portion, and works for both rises and falls.
- Data source: China uses local published price information for individual materials; FIDIC uses cost indices for labour, Goods and other inputs to the Works.
- Risk allocation: in China the band is borne by the contractor; under 13.7 each Party bears the risk of any rise or fall in Costs not fully compensated.
- Rigidity: FIDIC applies the schedule mechanically, so it must be included in the Contract; Chinese practice often runs through adjustment documents, site instructions or settlement review.
Warning: copying material price adjustment into an international contract usually fails because the materials are listed but no indexation schedule or coefficients are attached — FIDIC 13.7 expressly does not apply in that case. Published price information is not a FIDIC cost data source, so indices or evidence must be agreed separately, with the risk band converted into coefficients.
| Chinese Term | English Term | FIDIC Term | Relation | Notes |
|---|---|---|---|---|
| 材料调差 | material price adjustment | Adjustments for Changes in Cost (Sub-Clause 13.7) | adjacent | 中国机制只针对主要材料,以信息价基准差额法单向调价,门槛内自担;FIDIC 13.7 覆盖 labour、Goods 及其他投入,按指数表双向调整,并以系数 a 界定不可调部分,两者触发条件与费用口径不同。 |
| 风险幅度 | risk band | fixed coefficient 'a' (Sub-Clause 13.7) | adjacent | 中国以百分比幅度划定承包人自担区间,属单项材料口径;FIDIC 的 a 是合同付款中不可调整的比例系数,属整体付款口径,且须与各项成本要素系数合计不超过 1。 |
| 指数公式调差 | cost indexation adjustment | Schedule(s) of cost indexation (Sub-Clause 13.7) | adjacent | 中国常用地方造价机构发布的调价文件与信息价,无需合同附表;FIDIC 明文规定合同未附指数表时该条不适用,故调价权完全取决于投标时是否已把 Schedule 纳入合同。 |
Updated 2026-09-13
- 01
Valuation rules for the four variables of material price adjustment (adjustment based on published price information) and the step-by-step calculation flow: base price C0, risk band r, measurement-period market price Ci and adjustable quantity Q (GB/T 50500-2024 Annex A.2)
The published-price-information method takes its values in five steps. (…
GB/T 50500-2024 App. A.2.1GB/T 50500-2024 App. A.2.2GB/T 50500-2024 App. A.2.32026-11-08 - 02
Hierarchy of effect and order of interpretation when tender documents, bid documents and the awarded contract conflict over material price adjustment (adjustment of the works price): substantive content follows the tendering and bidding documents; conflicts that are not substantive follow the priority order of contract documents (particular conditions first; later signing of the same class first) and the limits of those rules
A price-adjustment clause is part of the pricing and adjustment method o…
中华人民共和国招标投标法(主席令第21号,2017修正)第45条、第46条中华人民共和国招标投标法实施条例(国务院令第676号,2017修订)第57条最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)(法释〔2020〕25号)第2条、第22条2026-10-31 - 03
Whether a supplier may seek a price adjustment when building material prices rise sharply during a fixed-price procurement (sales) contract: routing by contract type (procurement contracts via sales contract rules plus change of circumstances; construction contracts via Interpretation II Article 9; government pricing via Civil Code Article 513), a comparison of three adjustable exceptions and five unsupported scenarios, a legal basis list, and points on evidence, time limits and jurisdiction
As a rule, no. A supplier who has signed a fixed-price procurement contr…
中华人民共和国民法典第五百三十三条中华人民共和国民法典第五百一十三条中华人民共和国民法典第五百四十三条2026-10-29 - 04
Dividing price and quantity gaps of employer-supplied (free-issue) materials: price gaps to the employer and outside the contractor's adjustment scope, quantity gaps bounded by the effective wastage rate, custody and freight splitting at the delivery point with unloading (GB/T 50500-2024 clauses 3.6.1, 3.2.4, 3.6.3, 6.2.4, 8.7.5; against GB 50500-2013 clause 3.2.1)
Price gaps are the employer's and never enter the contractor's adjustmen…
GB/T 50500-2024 建设工程工程量清单计价标准 第3.6.1条GB/T 50500-2024 第3.6.2条GB/T 50500-2024 第3.6.3条2026-10-25 - 05
Rules for determining the material adjustment base price (C0): base date, one-of-three sources and the adjustment computation base (GB/T 50500-2024)
The base price C0 = the market price level 28 days before the bid closin…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1GB/T 50500-2024 术语2.0.21GB/T 50500-2024 App. A.2.42026-09-25 - 06
Can published price information directly serve as the basis for material price adjustment: legality + three preconditions (listing / beyond band / tax) (GB/T 50500-2024)
Published price information (government guidance prices) is a price sour…
GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25 - 07
Taking and weighting published price information for materials across multiple months: default per-period adjustment; weight only when one measurement period spans price issues (GB/T 50500-2024 Appendix A.2)
Per GB/T 50500-2024: for construction spanning measurement periods (e.g…
GB/T 50500-2024 建设工程工程量清单计价标准(第7.1.3条、App. A.2.1~A.2.5、App. GTable G.2.1-1、第8.7.2条、第3.3.5条)2026-09-25 - 08
Three-layer playbook for locking in the prices of bulk materials: contract-side price-adjustment mechanism + procurement-side price-locking methods + material-differentiated strategy (GB/T 50500-2024)
Locking the price of bulk materials = on the contract side, first fix th…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50358-2017 建设项目工程总承包管理规范DB37/T 5096-2017 建设工程项目管理咨询规范2026-09-25 - 09
Overview of material price adjustment in construction works: applicable conditions, base price (reference price for adjustment), risk band, and calculation methods (GB/T 50500-2024 Sections 3.3/8.7 and Appendices A, G)
Four indispensable elements of material price adjustment: ① adjustable s…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.5-2023 建设工程结算审核作业指引建设部令第107号 建筑工程施工发包与承包计价管理办法2026-09-25 - 10
Price adjustment for wires and cables: itemized by full specification, copper-linkage agreements, and handling missing published price information (government guidance prices) (GB/T 50500-2024 Appendix A.2)
Cable price adjustment shares the same mechanism as steel (GB/T 50500-20…
GB/T 50500-2024 App. A.2GB/T 50500-2024 第3.3.5条GB/T 50500-2024 第8.7节2026-09-25 - 11
Steel price adjustment calculation: price-information adjustment formula, per-specification per-period threshold checks with adjustment on actual basis, and tax treatment (GB/T 50500-2024 Appendix A.2)
Steel price adjustment uses the price-information adjustment method (GB/…
GB/T 50500-2024 App. A.2GB/T 50500-2024 第3.3.5条GB/T 50500-2024 第8.7.2条2026-09-25 - 12
Appendix A price adjustment (for fluctuation) methods for changes in costs, GB 50500-2013 vs GB/T 50500-2024: weighting coefficient basis and adjustment threshold differences
The two editions share the same formula skeleton in Appendix A (index-ba…
GB/T 50500-2024 建设工程工程量清单计价标准(App. A、第8.7节、App. G)GB 50500-2013 建设工程工程量清单计价规范(App. A、第9.8节)2026-09-25 - 13
Price-difference calculation method after material prices exceed the risk band (price-information adjustment method, GB/T 50500-2024 Appendix A.2)
The excess beyond the risk band is adjusted per actuals: when prices ris…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1~A.2.5GB/T 50500-2024 第8.7.1~8.7.4条GB/T 50500-2024 第3.3.5条2026-09-25 - 14
Which period's published price applies to settlement material prices: the two-date system — base price locked at the contract base date (28 days before bid closing) plus period-by-period pricing per measurement cycle (GB/T 50500-2024 Annex A.2 price-information method)
Settlement material prices are not taken from a single period (completio…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.21条、第3.3.5条、第8.7.1~8.7.4条、第10.2.3条、第10.2.7条、第10.3.2条、App. A.2.1~A.2.4、App. G.2T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第3.1.7条2026-09-25 - 15
Alternative adjustment paths when price information lacks the specification: mutually confirmed price / purchase price / awarded-bid price fallbacks + the same-caliber red line for C0 and Ci (GB/T 50500-2024 Appendix A.2)
Price information is only one of the Ci sources listed in A.2.1; lacking…
GB/T 50500-2024 App. A.2.1GB/T 50500-2024 App. A.2.2GB/T 50500-2024 App. A.2.52026-09-25 - 16
Mechanism for material price changes under fixed unit-price contracts: unit price locked + quantities at actuals + beyond-band adjustment (GB/T 50500-2024)
Under unit-price contracts the all-in unit rate is fixed within the cont…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.5-2023 建设工程结算审核作业指引T/ZBD 100.4-2023 建设工程造价鉴定作业指引2026-09-25 - 17
Selecting the contract pricing form when material prices fluctuate sharply: the hybrid mode of fixed unit rate + price adjustment clauses
With sharp fluctuations, neither a pure fixed price (quotes carry risk p…
建设部令第107号 建筑工程施工发包与承包计价管理办法 第十二条GB/T 50500-2024 建设工程工程量清单计价标准 第3.3.1/3.3.5/8.7.2~8.7.6条及App. A、App. GGB/T 50875-2013 工程造价术语标准 第3.3.6~3.3.8条2026-09-25 - 18
Whether actual purchase quantities can directly serve as the material adjustment quantity: triple filtering of contract agreement + employer confirmation + not exceeding rational consumption (GB/T 50500-2024)
The purchase quantity cannot directly serve as the adjustment quantity Q…
GB/T 50500-2024 App. A.2.1、A.2.5、App. GTable G.2.1-1、第3.6.3条、第8.7.2条T/ZBD 100.4-2023 第4.5.7条2026-09-25 - 19
Material price adjustment channels under fixed lump-sum contracts: no adjustment within the agreed risk band, adjustment beyond the risk band, mandatory adjustment for statutory causes
Under a fixed lump-sum contract, cost fluctuations within the agreed ris…
GB/T 50500-2024 第3.3.1~3.3.3、3.3.5、8.7.1~8.7.6条GB/T 50500-2024 App. A、App. G.2建设部令第107号 第12条2026-09-25 - 20
Cross-month material price adjustment: adjustment-period division and three methods for synthesizing multiple prices within a period (arithmetic mean / weighted mean with completed quantities / price of the main-consumption construction period)
Cross-month construction is not computed in a lump: adjust independently…
GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25 - 21
Rules for determining the quantity (Q) of materials subject to price adjustment: contractual agreement takes precedence, and key points on matching the quantity basis and the period (GB/T 50500-2024)
There is no unified statutory formula for the adjustable-factor quantity…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1/A.2.3/A.2.5GB/T 50500-2024 App. G.2 Table G.2.1-1/Table G.2.1-2GB/T 50500-2024 第8.7.1~8.7.4条2026-09-25 - 22
Rules for determining the construction-period price (measurement-period market price Ci) in material adjustment (GB/T 50500-2024 appendix A.2)
The construction-period price is the measurement-period market price Ci…
GB/T 50500-2024 App. A.2.1~A.2.5GB/T 50500-2024 第8.7.2/8.7.4条GB/T 50500-2024 App. A.1.52026-09-25