Engineering Knowledge Cards.

material price adjustment

22 knowledge cards · sorted by most recently updated

Concept Guide

Concept

Material price adjustment is a standard price-adjustment mechanism in Chinese construction contracts, rooted in the GB 50500 bill-of-quantities valuation code and in local cost-management rules. For major materials such as steel, cement and concrete, the contract names a base price taken from published price information issued by the local cost authority before the tender deadline. The price published or actually paid during construction is compared with that base, and only the part exceeding an agreed risk band (commonly ±5%, always subject to the contract) is adjusted; movement inside the threshold is borne by the contractor. The adjustment equals the excess amount multiplied by the actual quantity consumed. It is normally initiated by the contractor with the interim payment application or at settlement, supported by invoices and published price documents, reviewed by the employer or engineer, and settled through interim payments or the final account rather than through a variation or claim procedure.

FIDIC Mapping

Chinese term FIDIC term Relation Note
material price adjustment Adjustments for Changes in Cost (13.7) adjacent Same purpose, different trigger and data source
risk band fixed coefficient 'a' (13.7) adjacent China uses a band; FIDIC uses a non-adjustable coefficient
cost indexation adjustment Schedule(s) of cost indexation (13.7) adjacent No schedule means the sub-clause does not apply

Key differences:

  • Trigger: China relies on a contractual risk band; FIDIC 13.7 requires a Schedule of cost indexation, with coefficient a covering the non-adjustable portion, and works for both rises and falls.
  • Data source: China uses local published price information for individual materials; FIDIC uses cost indices for labour, Goods and other inputs to the Works.
  • Risk allocation: in China the band is borne by the contractor; under 13.7 each Party bears the risk of any rise or fall in Costs not fully compensated.
  • Rigidity: FIDIC applies the schedule mechanically, so it must be included in the Contract; Chinese practice often runs through adjustment documents, site instructions or settlement review.

Warning: copying material price adjustment into an international contract usually fails because the materials are listed but no indexation schedule or coefficients are attached — FIDIC 13.7 expressly does not apply in that case. Published price information is not a FIDIC cost data source, so indices or evidence must be agreed separately, with the risk band converted into coefficients.

Chinese TermEnglish TermFIDIC TermRelationNotes
材料调差material price adjustmentAdjustments for Changes in Cost (Sub-Clause 13.7)adjacent中国机制只针对主要材料,以信息价基准差额法单向调价,门槛内自担;FIDIC 13.7 覆盖 labour、Goods 及其他投入,按指数表双向调整,并以系数 a 界定不可调部分,两者触发条件与费用口径不同。
风险幅度risk bandfixed coefficient 'a' (Sub-Clause 13.7)adjacent中国以百分比幅度划定承包人自担区间,属单项材料口径;FIDIC 的 a 是合同付款中不可调整的比例系数,属整体付款口径,且须与各项成本要素系数合计不超过 1。
指数公式调差cost indexation adjustmentSchedule(s) of cost indexation (Sub-Clause 13.7)adjacent中国常用地方造价机构发布的调价文件与信息价,无需合同附表;FIDIC 明文规定合同未附指数表时该条不适用,故调价权完全取决于投标时是否已把 Schedule 纳入合同。

Updated 2026-09-13