Rules for determining the quantity (Q) of materials subject to price adjustment: contractual agreement takes precedence, and key points on matching the quantity basis and the period (GB/T 50500-2024)
There is no unified statutory formula for the adjustable-factor quantity Q; it is determined by the calculation method agreed by the employer and contractor in the contract (Appendix A.2.1 + Note 2 of Table G.2.1-1), and must be detailed and clarified in the tender documents / contract special clauses. In practice, the most common basis is "quantities measured for the current period x material consumption under quota norms (prescribed resource consumption standards)/mix ratio (including wastage)", or the purchase quantities confirmed by the employer (A.2.5). Q must correspond to the basis of the price adjustment period and to the price Ci for the measurement period; where the contract is silent, the standard provides no fallback determination and disputes easily arise.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1/A.2.3/A.2.5
- GB/T 50500-2024 App. G.2 Table G.2.1-1/Table G.2.1-2
- GB/T 50500-2024 第8.7.1~8.7.4条
Topic Positioning
This card answers "how to determine the adjustable-factor quantity (Q)" in adjustment for changes in costs: the determination rules, common quantity bases and period-matching points for Q under GB/T 50500-2024, complementing the "price dimension" cards on base prices and risk bands (no-adjustment tolerance, e.g. ±5%).
Core Conclusions
Q has no unified statutory formula; the rule is "contractual agreement takes precedence": A.2.1 defines Q as the quantity subject to price adjustment, and any other calculation method must be detailed and clarified in the tender documents and the contract special clauses; Note 2 of Table G.2.1-1 states that "quantity" is determined according to the calculation method agreed by the employer and contractor in the contract. Division of form-filling duties: the tender-inviting party fills in the serial number, name, specification, model, unit, base price (reference price for adjustment) and risk band; the bidder fills in the quoted price — the unit and basis must be locked in the table. Three bases are common in practice: (1) completed-quantity method: quantities measured for the current period x material consumption under quota norms/mix ratio (including wastage) — the most common, synchronized with measurement and payment; (2) purchase-quantity method: calculated according to the quantities actually purchased by the contractor and checked and confirmed by the employer in advance (A.2.5), with batch purchases averaged by weight — close to actual but dependent on the employer's approval of material prices; (3) BOQ consumption method: BOQ consumption x completion ratio for the current period — simple but may deviate from actual. Q must correspond to the price adjustment period (8.7.1 provides that price differences are calculated by price adjustment period); where a measurement period has multiple prices (A.2.3 arithmetic mean / weighted mean / price during the construction period of the main consumption), Q and Ci must take the same measurement-period basis and must not be mixed.
Applicable Boundaries
Applies to price adjustment for changes in costs under construction contracts priced on a bill of quantities (BOQ) basis (both adjustment based on published price information and index-based (formula) adjustment apply; the index method likewise requires clarity on weights/amounts by the same logic); where the contract provides otherwise, its provisions prevail — this card sets out rules rather than mandatory values. Not applicable to fixed lump-sum contracts or contracts agreeing to no adjustment; the 5% fallback addresses the extent of price fluctuation, not quantity. Whether wastage rates are included, and whether quantities follow the BOQ or actual consumption, must be stated in the contract, otherwise disputes arise where negotiation fails.
Further Reading
GB/T 50500-2024 China national pricing standard for BOQ, Appendix A.2.1 (formula and definition of Q), A.2.3 (taking prices where a measurement period has multiple prices), A.2.5 (submission and checking of purchase quantities; deemed approval upon lapse of the response period), Appendix G.2 Tables G.2.1-1/G.2.1-2 (schedule of price-adjustable key materials, Note 2), Clauses 8.7.1-8.7.4 (price adjustment periods, risk-band fallback, price determination where the works are delayed).
Keywords
- quantities subject to price adjustment
- 可调因子数量
- material price adjustment
- 已完工程量法
- 采购量法
- 物价变化调整
- schedule of price-adjustable key materials
- GB/T 50500-2024