Cross-month material price adjustment: adjustment-period division and three methods for synthesizing multiple prices within a period (arithmetic mean / weighted mean with completed quantities / price of the main-consumption construction period)

Cross-month construction is not computed in a lump: adjust independently per the contractually agreed adjustment period (usually the measurement period, e.g., monthly) (8.7.1); where multiple market prices occur within one period, choose one of three per the symmetric provisions of Appendix A.2.3 (information method) / A.1.5 (index method) — arithmetic mean, weighted mean with completed quantities, or the price of the main-consumption construction period, with the weighted mean closest to actual cost; the three methods differ significantly, and the method and priority order must be agreed in the contract. Supporting: provisionally adjust per the published price information and correct later per actuals (A.2.2); the synthesized price and the base price C0 are compared symmetrically in the same caliber (A.2.1); price-taking under delays follows the responsible direction (8.7.4); the price difference carries VAT only, without management fee or profit (3.3.5).

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准

Topic Positioning

The calculation framework for material price differences when construction spans months and multiple adjustment periods: period division, the three methods for synthesizing multiple prices within a period, and their differences.

Core Conclusions

  1. No lump-summing across months: compute separately per the contractually agreed adjustment period (usually monthly); each period compares that period's market price with the base price and independently adjusts the portion beyond the risk band (8.7.1).
  2. Where multiple market prices (or price indices) occur within one period, the price-information adjustment method (Appendix A.2.3) and the price-index adjustment method (Appendix A.1.5) symmetrically provide a choice of three: (1) arithmetic mean; (2) weighted mean with completed quantities; (3) the price of the main-consumption construction period. The three differ significantly; the method and priority order must be agreed in the contract, otherwise settlement disputes are certain.
  3. Supporting: where published price information is unavailable or disputes are significant, provisionally compute per the current published price information and correct later per actuals (A.2.2); the synthesized price is still compared with the base price C0 (28 days before the bid submission deadline; for non-tendered works, 28 days before contract signing) in the same caliber (A.2.1); under delays, price-taking follows responsibility — the higher price for employer-caused delays, the lower for contractor-caused (8.7.4); the price difference carries VAT only, without management fee or profit (3.3.5).

Applicable Boundaries

Applies to works using the price-information or price-index adjustment method; where the contract provides otherwise, its provisions prevail; "independent judgment per monthly period" and "one judgment after synthesis within the period" are two calibers — which one applies should be stated in the tender documents and contract special clauses; adjustable materials are limited to the contractually agreed scope (Appendix G.2).

Further Reading

GB/T 50500-2024 Appendix A.1.5, A.2.1-A.2.3, A.2.5, Clauses 8.7.1-8.7.4, 3.3.5, 2.0.21; Appendix G.2 Tables G.2.1-1/2 are contract attachment formats.