Cross-month material price adjustment: adjustment-period division and three methods for synthesizing multiple prices within a period (arithmetic mean / weighted mean with completed quantities / price of the main-consumption construction period)
Cross-month construction is not computed in a lump: adjust independently per the contractually agreed adjustment period (usually the measurement period, e.g., monthly) (8.7.1); where multiple market prices occur within one period, choose one of three per the symmetric provisions of Appendix A.2.3 (information method) / A.1.5 (index method) — arithmetic mean, weighted mean with completed quantities, or the price of the main-consumption construction period, with the weighted mean closest to actual cost; the three methods differ significantly, and the method and priority order must be agreed in the contract. Supporting: provisionally adjust per the published price information and correct later per actuals (A.2.2); the synthesized price and the base price C0 are compared symmetrically in the same caliber (A.2.1); price-taking under delays follows the responsible direction (8.7.4); the price difference carries VAT only, without management fee or profit (3.3.5).
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
Topic Positioning
The calculation framework for material price differences when construction spans months and multiple adjustment periods: period division, the three methods for synthesizing multiple prices within a period, and their differences.
Core Conclusions
- No lump-summing across months: compute separately per the contractually agreed adjustment period (usually monthly); each period compares that period's market price with the base price and independently adjusts the portion beyond the risk band (8.7.1).
- Where multiple market prices (or price indices) occur within one period, the price-information adjustment method (Appendix A.2.3) and the price-index adjustment method (Appendix A.1.5) symmetrically provide a choice of three: (1) arithmetic mean; (2) weighted mean with completed quantities; (3) the price of the main-consumption construction period. The three differ significantly; the method and priority order must be agreed in the contract, otherwise settlement disputes are certain.
- Supporting: where published price information is unavailable or disputes are significant, provisionally compute per the current published price information and correct later per actuals (A.2.2); the synthesized price is still compared with the base price C0 (28 days before the bid submission deadline; for non-tendered works, 28 days before contract signing) in the same caliber (A.2.1); under delays, price-taking follows responsibility — the higher price for employer-caused delays, the lower for contractor-caused (8.7.4); the price difference carries VAT only, without management fee or profit (3.3.5).
Applicable Boundaries
Applies to works using the price-information or price-index adjustment method; where the contract provides otherwise, its provisions prevail; "independent judgment per monthly period" and "one judgment after synthesis within the period" are two calibers — which one applies should be stated in the tender documents and contract special clauses; adjustable materials are limited to the contractually agreed scope (Appendix G.2).
Further Reading
GB/T 50500-2024 Appendix A.1.5, A.2.1-A.2.3, A.2.5, Clauses 8.7.1-8.7.4, 3.3.5, 2.0.21; Appendix G.2 Tables G.2.1-1/2 are contract attachment formats.
Keywords
- 跨月调差
- 调价期段
- 多价格合成
- 算术平均
- weighted average
- 主要用量施工期价格
- adjustment based on published price information
- index-based (formula) adjustment
- material price adjustment
- GB/T 50500-2024