Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Price-taking rules when one material has multiple published prices / original prices: weighted average by supply quantity at compilation, three agreed methods at adjustment, unified caliber

When one material has multiple prices, take prices by scenario: at compilation, original prices from multiple origins/supply channels are determined by weighted average per supply proportions (TB 10811-2024 Clause 2.2.1 — neither the high nor the low); at adjustment, multiple market prices within the same measurement period use one of the three contractually agreed methods and its priority — arithmetic mean, weighted mean with completed quantities, or the price of the main-consumption construction period (GB/T 50500-2024 Appendix A.2.3); for multi-agency publications with no agreement, follow the caliber of the agency at the project location; before taking prices, unify the tax-inclusive/exclusive, delivered/ex-factory, and specification-grade calibers; market prices, published prices, and manufacturer quotations are used by classified channels and strictly never mixed.

Applicable Codes

  • TB 10811-2024 铁路基本建设工程设计概(预)算费用定额
  • GB/T 50500-2024 建设工程工程量清单计价标准
  • T/ZBD 100.1-2022 建设工程造价数据建设通用标准
  • GB/T 50875-2013 工程造价术语标准
  • TB/T 10813-2024 铁路工程材料基期价格

Topic Positioning

General price-taking rules when one material has multiple prices (multiple origins/channels, multiple issues within one period, multiple agencies, multiple specifications), covering estimate/budget compilation and settlement adjustment.

Core Conclusions

Take prices by scenario; there is no simple "take low / take high":

  1. Multiple sources at compilation: where several original prices arise from different origins or supply channels, determine by weighted average per supply proportions (TB 10811-2024 Clause 2.2.1).
  2. Multiple prices at adjustment: where multiple market prices form within the same measurement period, use one of the three methods per the contract and its priority — arithmetic mean of market prices, weighted mean with completed quantities, or the market price of the main-consumption construction period (GB/T 50500-2024 Appendix A.2.3), which must be agreed in advance.
  3. Multi-agency publications: with no agreement, follow the current caliber of the agency at the project location; where no corresponding published price exists, provisionally use the published price and adjust later per actuals (Appendix A.2.2).
  4. Three classified channels: market prices, published price information, and manufacturer quotations are used by classification, with transaction prices as the main channel, strictly never mixed (T/ZBD 100.1-2022 Clause 7.2.3).

Applicable Boundaries

Where the contract has agreed priorities, its provisions prevail; not applicable to employer-supplied material deduction or provisional-price confirmation procedures. Price-taking must unify the tax-inclusive/exclusive, delivered/ex-factory, and specification-grade calibers.

Further Reading

TB 10811-2024 Clauses 2.2.1-2.2.3; GB/T 50500-2024 Appendices A.2.2, A.2.3; T/ZBD 100.1-2022 Clause 7.2.3; GB/T 50875-2013 Clause 2.1.16; TB/T 10813-2024 general principles 1.0.4 (composition of base-period price Classes A/B/C).