Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Pricing rules for cross-region material procurement: purchase-origin price + freight compose the delivered price; adjustment per contract and the price-confirmation procedure

Budget compilation does not force a binary "project location vs purchase location": material budget price = (material original price + freight within price) x (1 + procurement-and-keeping rate), the purchase-origin price serving as the original price and freight reflecting the inter-region difference; multi-source procurement is weighted by supply share. Settlement adjustment follows the contract first; absent agreement, the base price is the published price information (government guidance prices) for the project location or the mutually confirmed price 28 days before the bid deadline, the benefit of regional price differences accrues to the contractor, and prices must be submitted to the employer for confirmation before purchase — silence is deemed acceptance.

Applicable Codes

  • GB/T 50875-2013 工程造价术语标准
  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
  • TB 10811-2024 铁路基本建设工程设计概(预)算费用定额
  • JTG 3830-2018 公路工程建设项目概算预算编制办法
  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 51262-2017 建设工程造价鉴定规范

Topic Positioning

The rule for taking "project-location or purchase-location price" for cross-region material procurement: budgets build the delivered price from the purchase-origin price + freight; adjustment follows the contract and the price-confirmation procedure.

Core Conclusions

The rules do not force a binary choice:

  1. Budget compilation: material budget price = (material original price + freight-and-miscellaneous within price) x (1 + procurement-and-keeping rate) (TB 10801-2024 Clause 3.2.5). The original price is the ex-factory price or the price at the designated delivery point; freight within price covers transport and loading/unloading to the site — the purchase-location price is the original price, freight reflects the inter-region difference, and their sum is the delivered cost. Multiple origins and supply channels are weighted by supply share (TB 10811-2024 Clause 2.2.1).
  2. Settlement adjustment: contract agreement first; absent agreement, the base price is the published price information (government guidance prices) for the project location or the mutually confirmed price 28 days before the bid deadline (non-tendered works: 28 days before contract signing) (GB/T 50500-2024 Appendix A.2.1); the benefit of regional price differences accrues to the contractor; adjusting by the confirmed purchase price requires submission for verification before purchase, silence being deemed acceptance (Appendix A.2.5); appraisal prioritizes the approved-confirmed price > contract-agreed price > mutually agreed price (GB/T 51262-2017 Clause 5.6.4).

Applicable Boundaries

Applies to compilation-period pricing and adjustment absent special contract terms; where the contract specifies the pricing method, it prevails; provisionally priced materials are replaced by the tax-exclusive price confirmed by the employer (GB/T 50500-2024 Clause 8.4.5). Before comparing prices, check the caliber of the published price information (government guidance prices): whether freight/procurement-keeping fees are included; railway base prices in classes A/B/C — mismatched calibers distort the comparison.

Further Reading

TB 10801-2024 Clause 3.2.5; TB 10811-2024 Clauses 2.2.1-2.2.3; GB/T 50500-2024 Appendices A.2.1/A.2.5; GB/T 51262-2017 Clause 5.6.4.