Highway works quota norms (prescribed resource consumption standards) for the average haul distance of materials by truck: no addition of on-site haul or secondary transfer distance (JTG 3830-2018 Clause 3.1.2 / JTG/T 3832-2018 material-transport chapter notes)

Highway works system (JTG 3830-2018 Clause 3.1.2; identical provision in JTG 3820-2018): no adjustment coefficient may be applied to the average truck haul distance, and no on-site haul or secondary-transfer distance may be added beyond the site warehouse or stockpile; JTG/T 3832-2018 lower-volume Chapter 9 notes: the truck/tipper/water-tanker transport quota norms (prescribed resource consumption standards) apply only to average haul distances within 15 km; beyond 15 km, transport costs are computed at market rates.

Applicable Codes

  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.2条
  • JTG 3820-2018 · Measure for Compilation of Investment Estimates of Highway Construction Projects 第3.1.2条
  • JTG/T 3832-2018 · Budget Quota of Highway Engineering 下册Ch. 9 材料运输 章说明
  • JTG/T 3821 · Estimate Indicators of Highway Engineering

Topic Positioning

The computation caliber of the 'average haul distance' for material transport by truck in highway works feasibility-stage cost estimate/preliminary estimate/budget compilation — whether on-site haul or secondary-transfer distance may be added to the average. Conclusion: no; the average distance ends at the site warehouse (stockpile).

Core Conclusions

  1. Statutory caliber of the average haul distance (Clause 3.1.2 of JTG 3830-2018, notes on freight and handling charges within the composition of the norm-based material price for estimating, key sentence verbatim): 'Freight and handling charges' means the costs of moving materials from the supply point to the site warehouse (where materials are stored at the works), including loading/unloading and freight... where one material has two or more supply points, the freight shall be computed by weighted averaging of the distances, volumes, and rates. As the preliminary estimate and budget quota norms (prescribed resource consumption standards) already account for site access roads and already include 'site short-distance hauling' costs, no adjustment coefficient may be applied to the average truck haul distance, nor may on-site haul or secondary-transfer distance be added beyond the site warehouse or stockpile.
  • The 'Administrative compilation rules for feasibility-stage cost estimates of highway works construction projects' JTG 3820-2018 carries the identical provision (same caliber at the feasibility-stage cost estimate stage, per the 'Highway works estimation indicators' JTG/T 3821).
  1. Scope and tail rules of the truck transport quota norms (Chapter 9 'Material transport' notes, JTG/T 3832-2018 lower volume, highway works budget quota manual):
  • The truck, tipper, and water-tanker items apply only to average haul distances within 15 km;
  • Beyond the first distance unit (1 km), a tail under half an incremental quota norm unit is dropped, at or over half counts as one incremental quota norm unit;
  • Beyond 15 km average distance, transport costs follow market rates — the quota norms (prescribed resource consumption standards) no longer apply;
  • The quota norms already allow for rough subgrade, soft soil, mud, sharp curves, and steep grades (no further coefficients).
  1. Practical conclusion: in preliminary estimates and budgets the material average haul ends at the site warehouse (stockpile); multiple supply points are weighted by distance, volume, and rate; the quota norms already include 'site short-distance hauling' — on-site transfers must not be charged again. On-site transfers genuinely required by the project execution plan (construction methodology and site organization) (e.g. large access-road limits, secondary transfer of bulky materials) belong at the project execution plan (construction methodology and site organization)/preliminaries level and must be justified and booked there, never folded into the material average haul — a common review reduction point in preliminary estimate/budget compliance checks.

Applicable Boundaries

  • Applies to highway works feasibility-stage cost estimate/preliminary estimate/budget compilation (JTG 3820-2018, JTG 3830-2018, JTG/T 3832-2018 system).
  • The 15 km limit and tail rules apply only to the truck, tipper, and water-tanker items; beyond 15 km switch to market rates.
  • Not for the railway system: railway TB 10801/10811/10821 handles secondary transfer differently (site haul within 50 m already in quota norm labour; beyond 50 m via the TB/T 10821 short-haul quota norms) — the two systems must not be mixed.
  • Manual carrying and barrow transport have their own chapter-note rules (e.g. extra distance on slopes) — outside this card.

Further Reading

  • JTG 3830-2018 Clause 3.1.2 with Table 3.1.2-1 (gross-mass coefficients) and Table 3.1.2-2 (off-site transport wastage rates; note: bagged cement +0.5 percentage points when trucked over 500 km).
  • JTG 3820-2018 Clause 3.1.2 (same caliber).
  • JTG/T 3832-2018, lower volume, Chapter 9 notes and items 9-1-1 (manual carrying), 9-1-2 (barrow), etc.
  • Railway comparison (see referenced cards): TB 10801-2024 material prices; TB/T 10821 short-haul quota norms.