Determining material cost within the all-in unit rate: the two-step norm resource consumption × material unit price method, special situations, and the tax-exclusive boundary
Material cost = norm material consumption × norm-based material price for estimating: consumption is taken from the factor quantities of the budget quota norms (prescribed resource consumption standards) line item; the material unit price is the composite average price from the place of origin to the site warehouse up to issuance from the warehouse, with industry-specific formulas (railway: (original price + freight and handling included in the material price) × (1 + purchasing and custody percentage rate); highway: (original price + freight and handling charges) × (1 + off-site transport wastage rate) × (1 + purchasing and custody percentage rate)). Prime cost (PC) sums for materials are included at the tax-exclusive unit price stated in the BOQ; cost fluctuations beyond the agreed risk band (no-adjustment tolerance, e.g. ±5%; if not agreed, 5%) are adjusted per Appendix A, the price difference carrying value added tax (VAT) only, with no management fee or profit; material cost never includes VAT.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 50875-2013 工程造价术语标准
- GB/T 51095-2015 建设工程造价咨询规范
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
- TB 10811-2024 铁路基本建设工程设计概(预)算费用定额
- JTG 3830-2018 公路工程建设项目概算预算编制办法
Topic Positioning
How material cost within the all-in unit rate is determined: rate build-up by the two-step norm resource consumption × material unit price method, covering special situations such as prime cost (PC) sums for materials and price adjustment (for fluctuation), and the tax-exclusive boundary, applicable to the multi-industry conventions of building / railway / highway works.
Core Conclusions
Material cost = norm material consumption × norm-based material price for estimating. Consumption is taken from budget quota norms (prescribed resource consumption standards) line items (net quantity + construction wastage); the material unit price is the composite average price of the material from its origin to the site warehouse up to issuance from the warehouse. Industry formulas differ: railway norm-based material price = (original price + freight and handling included in the material price) × (1 + purchasing and custody percentage rate), the rate taken at 1.10%-4.98% per TB 10811 Table 2.2.2; highway = (original price + freight and handling charges) × (1 + off-site transport wastage rate) × (1 + purchasing and custody percentage rate). Prime cost (PC) sums for materials are included at the tax-exclusive unit price stated in the BOQ; after the actual price is confirmed, only the material cost is adjusted and value added tax (VAT) is calculated separately (GB/T 50500-2024 Clauses 6.2.5, 8.4); cost fluctuations beyond the agreed risk band (no-adjustment tolerance, e.g. ±5%; if not agreed, 5%) are adjusted per Appendix A, the price difference carrying VAT only, with no management fee or profit (Clauses 3.3.5, 8.7.2). The all-in unit rate excludes VAT (Clause 2.0.9).
Applicable Boundaries
Applies to material-cost rate build-up and verification in budget compilation, tender (priced offer), and settlement; price sources vary by industry (railway uses TB/T 10813 base-period prices plus design-surveyed compilation-period prices). Not applicable to: employer-supplied-material stripping pricing, dayworks (separately per Clause 8.6.3), or scenarios where no applicable quota norms apply and market price enquiry is required for rate build-up.
Further Reading
GB/T 50500-2024 Clauses 2.0.9, 3.3.5, 6.2.5, 8.6.3, 8.7.2; GB/T 50875-2013 Clauses 2.2.14, 2.2.58; GB/T 51095-2015 Clause 5.3.9; railway TB 10801-2024 Section 3.2, TB 10811-2024 Section 2.2; highway JTG 3830-2018.
Keywords
Related Cards
- →
Three-dimensional cost analysis method for billed (BOQ) items: quantity, price, and fee (quantity recheck → price reasonableness → fee composition)
Split the cost of a single billed (BOQ) item into three independent dimensions for review — quantity (recheck of quantities), price (three-layer review of the all-in unit rate), and fee (verification of costs outside the unit rate): the quantity dimension re-quantifies from drawings and compares with the BOQ quantities, checking missing items and duplicate listings; the price dimension reviews consumption, prices, and rates under the all-in unit rate = labour cost + material cost + plant and small tools cost + management fee + profit + risk cost within the agreed range (excluding VAT, GB/T 50500-2024 Clauses 2.0.9, 3.1.6) and identifies unbalanced rates / rate loading; the fee dimension verifies the completeness of preliminaries, non-competitive costs, provisional sums and specified-material/nominated-works provisional sums, and arithmetic checks. Based on the nine items of tender review and normalization in GB/T 51095-2015 Clause 6.3.2.
- →
GB/T 50500-2024 rules for adjusting price differences, management fee, and tax after the actual price of provisionally priced materials/equipment is determined (Section 8.4)
Per GB/T 50500-2024 Section 8.4, once the actual price of provisionally priced materials (including engineering equipment) is determined, only the material provisional-price item in the all-in unit rate is adjusted (pre-tax difference = confirmed actual pre-tax unit price − provisional pre-tax unit price, times quantity); labor, machinery, management fee, profit and other costs are not adjusted; VAT is charged additionally on the difference and the contract price is adjusted. Replacement price: for items subject to mandatory tendering by law, the pre-tax winning purchase price replaces it; otherwise, the pre-tax inquiry/own-quote price confirmed by the employer. Specialist-work provisional prices are VAT-inclusive, replaced wholesale by the winning VAT-inclusive subcontract price — a different rule.
- →
Market-inquiry pricing when no applicable quota exists: the two-step method (multi-source inquiry → labor/material/machinery pricing) and traceability/audit requirements
A missing quota does not mean missing pricing rules: the all-in unit rate structure (labor/materials/machinery + management fee + profit + statutory fees + taxes) stays unchanged, with labor/material/machinery prices obtained instead from multi-channel market inquiries (online platforms / telephone / site visits / similar-project benchmarks), and consumption referenced from similar quotas with correction, manufacturer technical parameters, or field measurement. Inquiries must be multi-source and benchmarked, consistent with design parameters, and must not directly pick published prices; records are countersigned and a ledger kept; fees still accrue per the fee standards. The priority of price bases is contract agreement > price confirmed by both parties > published price > market inquiry — inquiry-based pricing is the last resort and requires employer / auditor acceptance with traceability (inquiry-verification report, preparation notes, all-in unit rate analysis sheets).
- →
Deduction of employer-supplied (free-issue) materials from payments and allocation of costs: deduction mechanism, procurement/custody fee and wastage responsibility (GB/T 50500-2024, T/ZBD 100.4-2023)
Where employer-supplied (free-issue) material prices are not included in the all-in unit rate (stripped pricing), settlement naturally requires no deduction; where the contract stipulates prior inclusion, deduct from the settlement amount at actual consumption (issued quantity − stock) × the supply contract unit price. Procurement and custody costs follow the material and belong to the procuring party (the employer); the cost of the contractor's custody and assistance services is borne by the employer and charged under the main contractor's attendance and coordination provisions; wastage within the valid wastage rate is borne by the employer, over-drawing attributable to the contractor is borne by the contractor, and employer-caused causes (non-conforming specifications, untimely supply) are borne by the employer.
Cited By
- ←
Dividing price and quantity gaps of employer-supplied (free-issue) materials: price gaps to the employer and outside the contractor's adjustment scope, quantity gaps bounded by the effective wastage rate, custody and freight splitting at the delivery point with unloading (GB/T 50500-2024 clauses 3.6.1, 3.2.4, 3.6.3, 6.2.4, 8.7.5; against GB 50500-2013 clause 3.2.1)
Price gaps are the employer's and never enter the contractor's adjustment: 3.6.1 - 'at bidding, the prices of employer-supplied materials do not enter the all-in unit rates'; 3.2.4 - 'the material cost of employer-supplied materials does not enter the work-item list'; 8.7.5 - 'the material adjustments of 8.7.2~8.7.4 are not suited to employer-supplied items... adjustable by the employer on actual changes but not listed in the contract total' - the gap between actual purchase and contracted prices is the employer's own, forming no contractor adjustment income and no downward contract revision. Quantity gaps split at the effective wastage rate: contractor-caused over-draws are borne by the contractor per 3.6.3, clawed back at supply-contract prices from interim or final payments; within the rate, and employer-caused excesses (specification mismatch pushing wastage beyond the rate; employer-caused over-draws), fall on the employer. Custody and freight split at 'delivered to the delivery point and unloaded': before, the employer's (6.2.4 - bid rates exclude those costs); after, site custody, double handling and own installation wastage are the contractor's, coordination and custody services charged to the employer in attendance provisions (3.6.4).
- ←
Reading published price information as tax-inclusive or net, and the de-taxing conversion: de-tax by element (goods 13%, transport 9%, levy rate 3%), then custody, then into the all-in unit rate - with the order-bias test and double-tax prevention
Published prices are often tax-inclusive or freight-inclusive: read the release notes first. Tax-inclusive prices de-tax by each element's own rate (goods 13%, transport services 9%, simplified levy 3%) before purchasing and custody; a tax-inclusive delivered price divided once by 1.13 never adds freight or custody again. 'Add freight then divide the whole by 13%' differs algebraically from 'divide first, add later' only in form - both de-tax freight at 13%; the bias test is delta = F x (1/1.09 - 1/1.13) x (1+k). Net prices enter the all-in unit rate with VAT listed separately - one VAT only, throughout (GB/T 50500-2024 clauses 2.0.9, 3.1.6, 3.2.11).
- ←
Fee boundary for material price adjustment: the price difference carries VAT only, with no management fee or profit; the eight cost categories under Clause 8.7.6 are not adjusted (GB/T 50500-2024)
Per GB/T 50500-2024 Clause 3.3.5 item 4, price differences of labor, materials, and machinery fuel/power carry VAT only — no management fee or profit; Clause 8.7.6 lists eight categories not adjusted for price changes (construction consumables, small tool usage, preliminaries, other machinery usage beyond fuel/power, materials outside agreed adjustable items, changes beyond the agreed scope and band, management fee and profit, contractor's own-cause costs); Clause 8.7.3 opens a negotiation exception for abnormal, unforeseeable fluctuations.
- ←
Where material wastage is booked, and the double counting and omission tests: off-site transport and storage losses into the material unit price (price factor) versus site haulage and operation losses into the quota consumption (quantity factor), with the site warehouse / designated stockpile point as the boundary, plus a comparison of booking positions for typical work items and settlement audit checkpoints
Material wastage may enter only one of the material unit price (price factor) or the quota consumption (quantity factor); the dividing line is the site warehouse / designated stockpile point. Losses before the line (source to site warehouse) - transport loss and store-keeping loss - go into the material unit price (highway lists an off-site transport wastage rate separately; railway folds it into purchasing and custody charges; building works list a transport loss charge plus a storage loss); losses after the line (warehouse / stockpile point to the point of working or installation) - transport, processing, working and on-site stockpiling losses - go into the quota consumption. Since material cost = quota material consumption x norm-based material price, each factor carries only its own segment of wastage and nothing repeats: multiplying the same segment into both factors (overstating by roughly that wastage rate) is double counting; missing from both is omission. When applying quotas to compile a budget, the wastage rate must not be applied once more on top of the quota consumption (consumption = net quantity x (1 + wastage rate) is an algorithm at the level of quota compilation and measurement only).
- ←
Attribution of quantity gaps between BOQ quantities and quota quantities, and the rate conversion: all-in unit rate P = Sum(Tn) / Q, four destinations of quantity gaps (into the BOQ quantity / into the rate / into quota consumption / into the risk allowance), and conversion points for typical work items
BOQ quantities and quota quantities must be kept on two separate tracks and never swapped: first attribute each quantity gap to one of four classes - content already built into the measurement rules (working space for earthworks) goes into the BOQ quantity; content listed under 'work content' but given no quantity (battering, shoring boards, base trimming and clearing) goes only into the ancillary-works cost or risk allowance inside the all-in unit rate; content carried by the quota through wastage rates or contents (material wastage, rebar wastage plus construction bars at 5%, permissible overbreak in rock works, 0.50m over-concreting of bored piles) goes into the numerator, the quota line-item totals; whatever neither the BOQ nor the quota provides can only go into the rate risk allowance. The conversion formula is P = Sum(Tn) / Q (P rounded to 2 decimal places, Tn kept at full precision without rounding, Q rounded to 3 decimal places). Quoting with quota quantities passed off as BOQ quantities is an explicit error: the dimensional bases differ, the all-in unit rate is understated (omission ratio = 1 - quota rate / all-in rate), and it blurs the parties' respective responsibilities for BOQ accuracy.
- ←
Deduction of employer-supplied (free-issue) materials from payments and allocation of costs: deduction mechanism, procurement/custody fee and wastage responsibility (GB/T 50500-2024, T/ZBD 100.4-2023)
Where employer-supplied (free-issue) material prices are not included in the all-in unit rate (stripped pricing), settlement naturally requires no deduction; where the contract stipulates prior inclusion, deduct from the settlement amount at actual consumption (issued quantity − stock) × the supply contract unit price. Procurement and custody costs follow the material and belong to the procuring party (the employer); the cost of the contractor's custody and assistance services is borne by the employer and charged under the main contractor's attendance and coordination provisions; wastage within the valid wastage rate is borne by the employer, over-drawing attributable to the contractor is borne by the contractor, and employer-caused causes (non-conforming specifications, untimely supply) are borne by the employer.
- ←
The rate build-up path from quota line items to the all-in unit rate of a BOQ item and the cost calculation procedure: divisional work item cost as BOQ quantity x all-in rate, sum of quota line item amounts / BOQ item quantity (3 decimal places for quantities, 2 for rates), the three pricing methods, the analysis sheet identical to the BOQ rate, and the taxed versus tax-exclusive cost structures
The all-in unit rate of a BOQ item is converted as 'sum of quota line item amounts / BOQ item quantity' (item amounts at full precision with no rounding, BOQ quantities to 3 decimals, all-in rates to 2), and divisional work item cost = sum of (item quantity x all-in rate); the rates and prices in the all-in unit rate analysis sheet must exactly match those in the BOQ (GB/T 50500-2024 clause 3.1.7); pricing methods are unit-rate, lump-sum and percentage-rate, with divisional items and dayworks best priced at unit rates and preliminary items by lump sum or percentage; the taxed cost follows 'tax-exclusive cost of works = (divisional items + unit-rate preliminaries) + lump-sum preliminaries + other charges, and VAT = tax-exclusive cost x rate'; the scope of the all-in rate must be confirmed first - GB/T 50500-2024 clause 2.0.9 excludes VAT, while GB/T 51095-2015 clause 5.3.8 and article 5 of Ministry of Construction Order No. 107 are full-cost scopes including statutory levies and taxes.
- ←
Four cost components of the material price (norm-based material price for estimating) and the step-by-step computation: the formula, the charging base of purchasing and custody, the double pass of transport wastage and the placement of inspection and testing costs
Material price (norm-based material price for estimating) = (material price at source + freight and handling) x (1 + transport wastage rate) x (1 + purchasing and custody rate); purchasing and custody charges take price at source + freight and handling + transport wastage, i.e. the wastage-inclusive source price and freight, as their base (wastage passes through both the wastage and custody stages - the sanctioned basis, not double counting), and the two rates must not simply be added; at 2% wastage and 3% custody the combined factor is 1.02 x 1.03 = 1.0506 (simple addition gives 1.05, about 0.06% short). The material price contains only four items - source price, freight and handling, transport wastage, purchasing and custody; inspection and testing costs of the contractor's ordinary verification sit in overheads, not in the material price. The railway basis differs: transport wastage merges into purchasing and custody, the formula being (source price + freight included in price) x (1 + custody rate), with no separate wastage multiplier.
- ←
Determining overheads (company and site) and profit within the all-in unit rate: the dual track of the percentage-rate method and independent market-level measurement (including railway on-costs percentage rates)
Overheads (company and site) and profit are determined on the dual track of fee standards/percentage-rate method + market-level correction: estimates/budgets and tender price ceilings (employer's maximum acceptable price) are computed per the percentage rates in the norms for on-costs and expenses (railway merges the two into on-costs (indirect costs) = (base-period labour cost + base-period plant and small tools cost) × on-costs percentage rate, TB 10811-2024 Table 2.9.1, 16 categories, 14.3%–58.6%); tenders (priced offers) are independently measured by the enterprise; profit is a competitive cost but bidding below enterprise cost is prohibited. Price adjustment for cost fluctuation carries value added tax (VAT) only, with no overheads or profit.
- ←
Definitions, cost composition and applicable conventions of the direct-cost rate, the all-in unit rate and the fully loaded all-in rate compared (Order No. 107 of the Ministry of Construction, GB/T 50500-2024, GB/T 51095-2015, etc.)
The three rate conventions widen in scope in turn: the direct-cost rate (labour plus materials plus plant only, with on-costs, profit and taxes computed separately) is contained in the all-in unit rate (labour plus materials plus plant and small tools plus overheads plus profit plus risk fees within the agreed band; GB/T 50500-2024 clause 2.0.9 expressly excludes VAT, which is carried separately), which is contained in the fully loaded all-in rate (further including statutory levies and taxes, tax-inclusive; GB/T 51095-2015 clause 6.2.3 requires its use for the tender price ceiling and tenders). Note that the "all-in rate method" defined in Order No. 107 of the Ministry of Construction is a fully loaded unit rate - the same name as, but different content from, the "all-in unit rate" of current BOQ pricing; the "all-in rate" of highway works is likewise a wide convention including statutory levies and taxes (and additionally equipment procurement cost and preliminaries).
- ←
Scope of the "delivered price" basis of published material price information: the mainstream basis includes the material price at source, freight and handling charges, transport wastage and purchasing and custody charges, but exceptions exist by region and category; read the notes of the current issue before use, and never count twice charges already included
The mainstream basis of published price information is the "delivered price" - it includes the material price at source, freight and handling charges, transport wastage and purchasing and custody charges (GB/T 50875-2013 defines the material unit price as the comprehensive average price formed from the source of the building material to the site warehouse up to issue from stock). But the basis is not uniform nationwide: Beijing Construction Cost Information states that steel members exclude freight and handling charges, which may be increased on the facts where transport conditions are constrained. The notes of the current issue must be read before use, and freight and handling charges or purchasing and custody charges already included must not be counted again in the rates.
- ←
Highway works JTG 3830-2018 material off-site transport wastage rate table: the rule that the wastage rate for bagged cement hauled by motor beyond 500 km increases by 0.5 percentage points, and the Table 3.1.2-2 values
Per the note to Table 3.1.2-2 "Material off-site transport wastage rate table" of the "Administrative compilation rules for estimates and budgets of highway construction projects" (JTG 3830-2018): "For cement carried by motor transport, when the haul distance exceeds 500 km, the wastage rate of bagged cement increases by 0.5 percentage points." The base off-site transport wastage rate for cement (bagged and bulk, including one handling) is 1.0%, plus 0.4% for each additional handling; beyond 500 km bagged cement takes 1.5% (1.0%+0.5%) — bagged only, with no cumulative stepping. The wastage enters the norm-based material price for estimating = (material price at source + freight and handling charges) × (1 + off-site transport wastage rate) × (1 + purchasing and custody charges rate) − recoverable packaging value. The same note appears in Table 3.1.2-2 of the "Administrative compilation rules for feasibility-stage cost estimates of highway construction projects" (JTG/T 3820-2018), on an identical basis.
- ←
GB/T 50500-2024 comparison of specialist-work provisional amounts (VAT-inclusive) and material provisional prices (VAT-exclusive): listing, taxation, and adjustment rules
Under GB/T 50500-2024 "Standard for BOQ pricing of construction works": the specialist-work provisional amount is a VAT-inclusive price (listed in other items, deducted from the VAT computation base to avoid double taxation, replaced wholesale by the successful VAT-inclusive subcontract price at adjustment); the material provisional price is a VAT-exclusive pre-tax unit price (entered into the comprehensive rate of a work-section item, VAT charged normally on the VAT line, adjustment limited to the pre-tax material difference within the comprehensive rate). The two have opposite tax calibers and differ in listing, taxation, and adjustment — mixing them double-counts or omits VAT.
- ←
Triage rules when quota materials differ from actually used materials: variety/species per express quota rules or via design change; same material — adjustment for price differentials only
First triage the type of "different material": for a variety/species change, non-load-bearing materials follow express quota conversion rules for consumption conversion (mix-proportion tables, stabilized-soil mix formulas, dry/wet mortar equivalent interchange, admixture/ready-mixed concrete adjustments), while load-bearing structural materials (rebar/sections/timber) must go through design change and equal-strength/equal-section substitution procedures — not quota conversion; changing only the price of the same material is purely an adjustment for price differentials (consumption fixed; price difference = quota consumption x (compilation-period price - base-period price)). Red lines: cement variety, actual construction mix proportion, and machinery type/species differences are never converted; site losses are already included and not counted again.
- ←
Railway 2024 quotas: budgeting self-built aggregate yards producing machine-made sand with combined plants (TB/T 10821-2024 Chapter 6 YY-70) and the unit-price composition of self-quarried aggregate
Machine-made sand uses Chapter 6 YY-70 of TB/T 10821-2024 (unit 100 m3 of finished aggregate; 2020 base 3,386.81 yuan/100 m3 — labor 270.66, plant 3,116.15, materials 0, raw feed separate). Chapter 6 is not a direct BOQ item: per the compilation measures 3.2.2 "material cost = sum of (quota consumption x material budget price)", it analyzes the self-quarried yard price (material original price) entering the material cost of concrete and other items. Self-quarried unit price: material budget price = (original price + freight-within-price) x (1 + procurement and custody rate) (TB 10801-2024 Clause 3.2.5); sand 4.47%, crushed stone (including ballast and medium/small cobbles) 3.45% (TB 10811-2024 Table 2.2.2); aggregate is Class A — base prices exclude freight, booked separately.
- ←
Railway 2024 quota: distinguishing surveyed-price materials from base-period-price materials — the Appendix A computer-code test and the main-material list (TB 10811/10801/10813-2024)
The sole test for surveyed-price vs base-period-price materials: check whether the material's computer code falls within Table A.0.1 of Appendix A of TB 10811-2024 "Railway capital construction design estimate (budget) fee quota". Within = main material: compilation-period price is exclusive of deductible input VAT and determined by the design organization's investigation, with price difference = quota-tabulated consumption x (compilation-period price − base-period price) listed as material price difference (TB 10801-2024 clause 4.1.2 item 2 sub-item 2)); outside = auxiliary material: base-period price used directly (TB/T 10813-2024, 2020 price level, exclusive of deductible input VAT), no survey, no compilation-period difference. Special cases: petrol/diesel compilation-period differences go into the construction-plant-use price difference; water and electricity are not on the surveyed list — their difference is computed separately as consumption x (compilation-period price − base-period price) (base prices: water 0.55 yuan/t, electricity 0.0.47 yuan/kWh).
- ←
Highway works quota norms (prescribed resource consumption standards) for the average haul distance of materials by truck: no addition of on-site haul or secondary transfer distance (JTG 3830-2018 Clause 3.1.2 / JTG/T 3832-2018 material-transport chapter notes)
Highway works system (JTG 3830-2018 Clause 3.1.2; identical provision in JTG 3820-2018): no adjustment coefficient may be applied to the average truck haul distance, and no on-site haul or secondary-transfer distance may be added beyond the site warehouse or stockpile; JTG/T 3832-2018 lower-volume Chapter 9 notes: the truck/tipper/water-tanker transport quota norms (prescribed resource consumption standards) apply only to average haul distances within 15 km; beyond 15 km, transport costs are computed at market rates.
- ←
Highway JTG 3830-2018 purchasing and custody charge rates for materials: steel 0.75%, fuel and explosives 3.26%, other materials 2.06%, purchased components 0.42%, commercial mixes exempt — and the basis for the norm-based material price for estimating
Per clause 3.1.2 of JTG 3830-2018 "Administrative compilation rules for estimates and budgets of highway construction projects", the purchasing and custody charge is calculated on the combined base "material price at source + freight and handling charges + off-site transport wastage" multiplied by the rate: steel 0.75%; fuel and explosive materials 3.26%; other materials 2.06%; purchased components, products and semi-products 0.42%; commercial cement concrete, asphalt mixes and all types of stabilized-soil mixes carry no purchasing and custody charge. Material price for estimating = (material price at source + freight and handling charges) x (1 + off-site transport wastage rate) x (1 + purchasing and custody charge rate).
- ←
Whether published price information / base-period prices include freight and miscellaneous charges: price-caliber determination (ex-factory caliber excludes, delivered-to-site caliber includes) and the A/B/C classification of railway base-period prices
Whether price information includes transport charges depends on the publication caliber: the ex-factory/market-price caliber excludes freight and miscellaneous charges (to be listed separately when compiling budgets), while the delivered-to-site caliber includes them (usable directly for price assembly). Railway base-period prices per TB 10813-2024 fall into three classes: Class A = original price x (1 + procurement-and-keeping rate) and Class B = comprehensive ex-factory price x (1 + procurement-and-keeping rate) both exclude freight and miscellaneous charges; only Class C = (original price + freight-and-miscellaneous charges within the price) x (1 + procurement-and-keeping rate) includes them. Always read the current issue's publication notes to confirm the caliber before use.
- ←
Whether published price information / base-period prices include the procurement and keeping fee: caliber determination (railway base-period prices fully include, most provincial price information excludes, highway adds separately)
The procurement and keeping fee is added by rate and not merged into the material original price. Railway base-period prices (TB/T 10813-2024), Classes A/B/C, all include the procurement and keeping fee (rates per TB 10811-2024 Table 2.2.2); the price information published by most provinces and cities uses the market-price caliber and excludes the fee, so it must be added separately when compiling budgets; a few publish "comprehensive prices including the fee", which must not be double-counted. Highway JTG 3830-2018 adds the fee separately on the basis of (original price + freight and miscellaneous charges + off-site transport loss). Always read the current issue's publication notes before use.
- ←
Railway 2024 quota subgrade purchased-fill material fee: when chargeable, how the fill price is built up, and the caliber distinction from material costs (TB 10801-2024 clause 3.5 / TB 10811-2024 clause 2.5.1)
The fill-material fee is charged only for filling materials obtained by **purchase** (soil, rock, permeable material, mineral material etc. not treated as materials), built up as "fill fee = sum(fill consumptions x fill price)" (TB 10801-2024 clause 3.5.2); the fill price is exclusive of deductible input VAT and is determined by investigation and analysis by the design organization (TB 10811-2024 clause 2.5.1) — it does not enter the material library, carries no purchasing and custody charges, and is not subject to price adjustment (for fluctuation). Self-excavated reuse (cut-to-fill) carries no fill fee; land-related costs of borrowing from temporarily occupied land go under Chapter 1 temporary land-use fees. This differs sharply from the clause-3.2 works material cost (norm-based material price for estimating = (material price at source + freight and handling included in the material price) x (1 + purchasing and custody rate)); in practice the test is "whether it appears in the quota consumption table".