prime cost (PC) sum for materials
- 01
Provisional prices (materials / specialist works): the settlement adjustment procedure of replacing the provisional price with the actual confirmed price - legal position, the submission-checking-review-re-examination-confirmation chain and deemed approval on expiry, the two confirmation routes (compulsory tendering and otherwise), adjusting only the pre-tax material price, the deduction direction when the confirmed price is lower, the boundary against material price adjustment, and the clause mapping of GB/T 50500-2024 against GB 50500-2013
The final account replaces the provisional price with the 'confirmed pri…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.14、3.2.3、3.3.5、6.2.5、8.1.2~8.1.6、8.4.1~8.4.8、8.5.3、8.7.2~8.7.5、8.10、9.4.6、10.3.2条及App. A、App. G.2GB 50500-2013 建设工程工程量清单计价规范 第5.2.5、6.2.5、9.9.1~9.9.4条中华人民共和国招标投标法实施条例(2018修订)第二十九条2026-10-25 - 02
Settlement pricing when the confirmed price of a provisionally priced material differs from published price information: the procedurally formed confirmed price (net award price, or employer-confirmed enquiry price) replaces the provisional sum, published prices serving only as the contractually agreed base or a provisional fallback in disputes
Settlement follows the confirmed price formed under the contractual proc…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.14、3.3.5、8.4.1~8.4.6、10.3.2条及App. A 第A.2.2、A.2.5条GB/T 50875-2013 · Standard glossary of project costs 第2.2.60、2.1.16条T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第3.1.7条2026-10-18 - 03
The non-adjustment boundary of material price adjustment: the eight cost classes never adjusted for price moves, the BOQ items outside routine adjustment, and the negotiated handling of abnormal fluctuation (GB/T 50500-2024 clauses 8.7.3 / 8.7.5 / 8.7.6)
GB/T 50500-2024 clause 8.7.6 lists eight classes never adjusted for pric…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.3.5条、第3.3.6条、第8.7.2条、第8.7.3条、第8.7.5条、第8.7.6条2026-10-18 - 04
GB/T 50500-2024 comparison of specialist-work provisional amounts (VAT-inclusive) and material provisional prices (VAT-exclusive): listing, taxation, and adjustment rules
Under GB/T 50500-2024 "Standard for BOQ pricing of construction works"…
GB/T 50500-2024 建设工程工程量清单计价标准(第2.0.14、2.0.15、3.1.6、3.2.11、6.2.5、8.4.1、8.4.6、8.4.7、8.10节,App. ETable E.1.1、Table E.2.3、Table E.4.3)2026-09-25 - 05
Full-process handling rules for prime cost (PC) sums for materials included in the all-in unit rate across tender, performance and settlement (GB/T 50500-2024)
For prime cost (PC) sums for materials (tax-exclusive unit prices), tend…
GB/T 50500-2024 建设工程工程量清单计价标准中华人民共和国招标投标法实施条例T/ZBD 100.5-2023 建设工程结算审核作业指引2026-09-25 - 06
GB/T 50500-2024 rules for adjusting price differences, management fee, and tax after the actual price of provisionally priced materials/equipment is determined (Section 8.4)
Per GB/T 50500-2024 Section 8.4, once the actual price of provisionally…
GB/T 50500-2024 第 8.4.1、8.4.5、8.4.6 条GB/T 50500-2024 第 2.0.14、3.2.11、8.1.8 条2026-09-25 - 07
Provisional sums at final account: settlement line item, replacement paths, VAT basis and review essentials (GB/T 50500-2024)
At final account, provisional sums are dealt with as "the actually deter…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准T/ZBD 100.5-2023 建设工程结算审核作业指引2026-09-25 - 08
Determining material cost within the all-in unit rate: the two-step norm resource consumption × material unit price method, special situations, and the tax-exclusive boundary
Material cost = norm material consumption × norm-based material price fo…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准GB/T 51095-2015 建设工程造价咨询规范2026-09-25