The non-adjustment boundary of material price adjustment: the eight cost classes never adjusted for price moves, the BOQ items outside routine adjustment, and the negotiated handling of abnormal fluctuation (GB/T 50500-2024 clauses 8.7.3 / 8.7.5 / 8.7.6)

GB/T 50500-2024 clause 8.7.6 lists eight classes never adjusted for price moves: construction consumables, small tools, preliminaries, other plant costs, materials outside the agreed adjustable items, price moves beyond the agreed scope and band, overheads and profit, and contractor-cause costs; clause 8.7.5 keeps the adjustment away from employer-supplied material items and provisionally priced material items; clauses 8.7.3 and 3.3.6 are the negotiated channels for abnormal fluctuation or missing agreement. Differences carry VAT only, never overheads or profit.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.3.5条、第3.3.6条、第8.7.2条、第8.7.3条、第8.7.5条、第8.7.6条

Positioning

The boundary questions most often stretched in material price adjustment: which costs by their nature never adjust, which BOQ items are outside routine adjustment, and how abnormal fluctuation is handled where the contract is silent. Basis: GB/T 50500-2024 clauses 8.7.3, 8.7.5, 8.7.6 and 3.3.5, 3.3.6 - complementing the question of what the difference itself carries.

Core conclusions

  1. Eight non-adjustable classes (8.7.6) - save as otherwise agreed, the following costs of performing and completing the contract never adjust the total or unit prices for price moves:
    1. construction consumables;
    2. small and medium tools;
    3. preliminaries;
    4. plant costs other than the fuel/power of clause 8.7.1~8.7.4;
    5. material costs outside the agreed adjustable items, save the abnormal fluctuation of 8.7.3;
    6. price moves beyond the agreed adjustable scope and band, or within the tolerance of 8.7.2;
    7. overheads and profit;
    8. contractor-cause costs. Essence: adjustment addresses only labour, key materials and fuel/power that are listed and beyond the band; everything else - and swings inside the band - is contractor risk priced in the bid.
  2. Items outside routine adjustment (8.7.5): the material adjustments of 8.7.2~8.7.4 "are not suited to items of employer-supplied materials or provisionally priced materials". Employer-supplied items adjust at the employer's actual changes but stay outside the contract total; provisionally priced items follow clause set 8.4 (replace the provisional price itself, add VAT, never touching labour, plant, overheads or profit).
  3. Abnormal fluctuation despite agreed adjustable items (8.7.3): for materials outside the agreed adjustable classes whose prices move abnormally - a major change unforeseeable at contracting that makes continued performance plainly inequitable to the prejudiced party - the parties may negotiate the risk band or sharing ratio per equitable allocation, bearing the relevant plus-or-minus difference or adjusting on actuals.
  4. No agreed adjustable items (3.3.6): where the contract names none, on abnormal fluctuation beyond the agreed band - or with no band agreed, fluctuation unforeseeable by an experienced contractor - the parties may adjust the affected items per 3.3.5, sharing the cost reasonably.
  5. Composition rule (3.3.5): differences "carry VAT only; the risk of overheads and profit is the bidder's, priced in the offer"; labour, material and fuel/power differences inside the all-in unit rate "carry VAT, never overheads or profit". The parties may agree to adjust the fuel/power of large plant for fuel swings - other plant costs need not adjust.

Applicable boundaries

  • 8.7.6 is qualified "save as otherwise agreed": costs expressly made adjustable by contract follow the agreement - this list limits nothing.
  • 8.7.3 is a negotiation mechanism, not automatic formula adjustment: it needs both "unforeseeable at contracting" and "plainly inequitable", on equitable risk allocation.
  • 3.3.6 covers items with no agreed adjustment; 8.7.2 (agreed items, no band - the 5% fallback) covers a different case - never mix.
  • Fixed-price lump-sum contracts generally do not adjust absent agreement (T/ZBD 100.5-2023 clause 3.1.7); the negotiation channels do not unfix the lump sum.
  • This card decides "whether to adjust"; whether the adjusted difference attracts further preliminaries or levies follows 3.3.5 and 7.3.1.

Further reading

GB/T 50500-2024 clauses 8.7.6, 8.7.5, 8.7.3, 8.7.2, 8.7.1, 3.3.5, 3.3.6, clause set 8.4; T/ZBD 100.5-2023 clause 3.1.7.