Order of applicable bases for material price adjustment: contract agreement prevails, pricing standard as fallback (GB/T 50500-2024 "agreement governs" and the 5% band rule)
Material price adjustment follows the contract agreement first (agreement governs, clause 1.0.3): adjustable material scope, base price, risk band, quantity calculation, price-information source and adjustment period all follow the contract, completing appendix G table G.2.1 as a contract annex; where the contract fixes no band or unclearly, fluctuation beyond 5% may be adjusted per appendix A (clause 8.7.2 fallback); the contract may neither violate mandatory laws and regulations nor depart from the substantive content of the tender documents (law prevails; clause 3.4.4); the price difference carries VAT only, no management fee or profit.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第1.0.3、3.3.5、3.4.4、8.7.2条及App. A、App. G
Topic Positioning
Answers "does material price adjustment follow the contract or the pricing provisions first": the order of application and hierarchy of effect between contract agreement and pricing standard when adjusting for price changes.
Core Conclusions
Hierarchy: law prevails > agreement governs > standard as fallback. (1) GB/T 50500-2024 general clause 1.0.3 establishes "law prevails, agreement governs": pricing activities comply with laws and regulations, and where the contract provides, the contract governs — material adjustment looks to the contract first. (2) Adjustment elements the contract should define (clause 3.3.5): scope of adjustable main materials, quantity calculation method, fluctuation band, price-information source and determination rules, adjustment period, completing appendix G table G.2.1-1 (price-information method) or G.2.1-2 (price-index method) as a contract annex; base price and risk band of adjustable materials are filled by the tenderer, bid prices by the bidder. (3) Standard fallback (clause 8.7.2): where the contract fixes no fluctuation band or unclearly, market-price fluctuation of labor, materials and fuel/power beyond 5% may adjust the contract price by one of the appendix A methods; within the agreed band, no adjustment. (4) Upper constraints: contract agreements may not violate mandatory laws and regulations nor depart from the substantive content of the tender documents — works scope, schedule, price, quality etc. (clause 3.4.4); the price difference takes VAT only, not management fee or profit (clause 3.3.5 item 4).
Applicable Boundaries
Applies to price-change adjustment of employer-contractor projects priced by BOQ (GB/T 50500-2024 is a recommended national standard GB/T); where the contract clearly provides adjustment clauses, the contract governs and the standard only fills gaps; statutory situations such as government-priced/guidance-priced items prevail over contract agreement. Fuel/power costs of construction plant may be adjusted by the main-material method if the contract allows. Projects under the 2013 edition follow the same structure but must be checked against the old clauses.
Further Reading
See GB/T 50500-2024: clause 1.0.3 (pricing principles), clause 3.3.5 (price-change adjustment and tax caliber), clause 3.4.4 (substantive tender content), clause 8.7.2 (5% fallback band), chapter 8 (contract price adjustment), appendix A (price-index/price-information methods), appendix G tables G.2.1-1/2 (contractor's adjustable main-materials table).
Keywords
- 材料价格调整
- contractual agreement takes precedence
- adjustment for cost fluctuation
- GB/T 50500-2024
- risk band (no-adjustment tolerance, e.g. ±5%)
- 5%兜底
- 调差依据
Related Cards
- →
Four-tier progressive identification of high-risk bid-pricing clauses in tender documents (rejection clauses -> substantive requirements -> price locking -> performance funding)
Read tender documents as risk-allocation contracts: (1) rejection clauses (the seven statutory grounds of Implementation Regulations Article 51 as baseline, sector measures expand with catch-all clauses; below-cost is the hidden trap); (2) substantive requirement clauses ("must/shall/shall not" wording + deviation tables—non-response is statutory rejection); (3) price-locking clauses (GB/T 50500-2024: risk-scope clarification, three elements of price adjustment, lump-sum by total, lump-sum per item, preliminaries responsibility, unbalanced bidding); (4) performance funding clauses (Article 3.4.8 14-item checklist, performance deposit <=10%, seven quality-reserve agreements).
- →
Priority of price bases for construction payment settlement: contract agreement > price confirmed by both parties > published price information > market price enquiry (purchase contract / invoice prices require the employer's approval of material prices)
Bases for settlement by priority: ① contract-agreed price (fundamental basis); ② price confirmed by the employer and contractor (certified record of agreed material prices — report quantity and unit price to the employer for verification before purchase; deemed approval upon lapse of the response period); ③ published price information (base price for adjustment / dispute fallback); ④ market price enquiry (for provisional sums and materials without published prices). Purchase contract prices and invoice prices only prove actual cost and become a basis for settlement only after the employer's approval of material prices.
- →
Steel price adjustment calculation: price-information adjustment formula, per-specification per-period threshold checks with adjustment on actual basis, and tax treatment (GB/T 50500-2024 Appendix A.2)
Steel price adjustment uses the price-information adjustment method (GB/T 50500-2024 Appendix A.2): △P = Σ[(Ci − C0·(1±r)) × Q] × (1 + VAT rate), adjusting only the portion beyond the risk band on an actual basis; the agreed risk band prevails, with the beyond-5% fallback where not agreed or unclear (8.7.2). Each specification must be checked independently each period for exceeding the risk band (base prices, published price information, and increase rates differ; specifications within the risk band are not adjusted for the period); the price difference carries VAT only, no management fee or profit (3.3.5); when checking adjustment tables, first look at whether the bid price is above or below the base price (A.2.4 determines the excess-calculation base).
Cited By
- ←
The price-taking order for deducting employer-supplied materials where the contract is silent: fix the 2013 / 2024 pricing basis first, then descend supply-contract unit price -> the signed Schedule of Employer-Supplied Materials -> the parties' pre-purchase confirmed price -> the Civil Code statutory fallback, with the price and quantity rules of cost expert assessment
Silence never means a blanket published price or market price. Under GB/T 50500-2024 (free-issue prices never enter the all-in rate, clause 3.6.1) the deduction price takes first the unit price of the corresponding supply contract (clause 3.6.3), deducting only the contractor-fault over-draw; under GB 50500-2013 (free-issue prices already in the rate, clause 3.2.1) recovery runs in full at the unit price of the signed Schedule of Employer-Supplied Materials and Equipment x quantity (clause 10.3.5). Next the parties' pre-purchase confirmed price (2024 Appendix A clause A.2.5, silence in time deeming approval; GB/T 51262-2017 clause 5.6.4(1)); unreported purchases take the contractual price (item 2 of the same clause); only a wholly missing evidence chain falls to Civil Code Article 510 (supplementary agreement, related terms or trade usage) and Article 511(2) - 'the market price at the place of performance when the contract was concluded', with the assessment fallback per T/ZBD 100.4-2023 clause 3.1.6's three routes. Quantity runs its own basis: actual consumption = issues - stock (T/ZBD 100.4-2023 clause 4.5.7); the 2013 basis takes the consumption of like items in the pricing quotas (2013 clause 3.2.4).
- ←
Re-measurement and price splitting after rebar substitution: re-measure from the variation drawings, count the quantity once only (lap and wastage coverage), the splitting formula of the quantity difference at the contract rate plus the material price difference carrying VAT only, and the 15% clause boundary among adopting the contract rate / converting an analogous rate / building up a new rate (GB/T 50500-2024 cl. 7.4.2, 8.2.1, 8.9.1, 8.9.2 and 3.3.5)
After a rebar substitution, re-measure from the variation instruction and the as-built construction drawings (GB/T 50500-2024 cl. 7.4.2) and count the quantity once only (laps only where shown by the design or by codes; erection wastage enters the quota content). Price splitting: dC = dQ x P1 + Q2 x dp - the quantity difference is priced at the contract (or re-banded) all-in unit rate, and the material price difference carries VAT only, with no overheads or profit (cl. 3.3.5). Rate banding takes 15% as the line: where the billed quantity change does not exceed 15% (inclusive), the five bands of cl. 8.9.1 apply (same conditions and same item description -> the contract rate; analogous description or analogous conditions -> a converted analogous rate; otherwise a negotiated rate build-up); beyond 15% (exclusive), cl. 8.9.2 applies and the rate is lowered or raised for the change in procurement discounts brought by the quantity gain or loss. Routine grade and size substitutions mostly land in the 'adopt the contract rate / convert an analogous rate' bands, not in a new rate build-up.
- ←
Splitting the remedy paths and procedural requisites when material prices rise: whether to go first for contract price adjustment (price adjustment for cost fluctuation) or for a works claim; the time limits, written requisites and negotiation sequence of each path; and the consequences of a missed or wrong procedure (GB/T 50500-2024 cl. 8.7, cl. 8.11 and Annex A; Civil Code art. 533; Fa Shi [2026] No. 12 art. 9)
The first path for a material price rise is contract price adjustment, not a claim: GB/T 50500-2024 cl. 8.11.2 states that where an event has already had its price adjustment calculated under the contract price adjustment provisions (excluding claims), no further works claim shall be calculated - duplicate claims will be disallowed. The adjustment path runs: report quantities and unit prices before procurement -> employer checks and confirms (no reply within the agreed period is deemed approval; GF-2017-0201 general conditions 11.1 gives 5 days) -> adjust under cl. 8.7.2 (fluctuation beyond 5% where the contract sets no band) per Annex A -> submit the price adjustment report, employer verifies and confirms (cl. 8.1.3) -> confirm, sign and pay together with the progress payments / interim settlement by construction stage payments (cl. 8.1.6). Only where the contract provides no adjustable price, for abnormal fluctuation of non-adjustable materials (cl. 8.7.3), or where the rise intertwines with delay losses does the claim path open: Notice of Claim (within the contract-agreed period after the event, 28 days where unspecified) -> claim report (28 days after the notice) -> employer 14 days to request further particulars, 28 days to reply -> confirm, sign and pay; a late notice 'may be treated as waived', and the other party's late reply 'may be deemed accepted'. For fixed-price settlement, requests to adjust solely for major changes in labour cost or key material prices within the construction period are not supported by the courts (Fa Shi [2026] No. 12 art. 9), unless otherwise agreed or qualifying as change of circumstances under Civil Code art. 533.
- ←
Valuation rules for the four variables of material price adjustment (adjustment based on published price information) and the step-by-step calculation flow: base price C0, risk band r, measurement-period market price Ci and adjustable quantity Q (GB/T 50500-2024 Annex A.2)
The published-price-information method takes its values in five steps. (1) C0 = the market price level 28 days before the tender submission deadline (for non-tendered works, 28 days before the contract signing date), one source chosen from three (the market price used in setting the tender price ceiling / the quarterly (monthly) published price information of the cost administration body / award prices of comparable projects published for the same period by the trading centre); the tender documents must state the source, the issuing body and the specific quarter (month). (2) r: the contractual agreement prevails; where none exists or it is unclear, adjustment is allowed once the movement exceeds 5% (clause 8.7.2), the sign of r following the sign of dC (positive on increase, negative on decrease). (3) Ci takes the current price of the measurement period; with multiple prices, use the arithmetic mean / the weighted mean against executed quantities / the price over the main-consumption construction period; where a price is missing or disputed, published price information may be used provisionally and trued up later; purchase prices must be submitted to the employer for verification before purchase, silence within the time limit being deemed approval. (4) Q is calculated under the contractual quantity calculation rules. (5) Adjustment only where |Ci - C0| / C0 > r; on increase the excess unit differential = Ci - C0(1+r), on decrease = C0(1-r) - Ci; multiplied by Q it bears VAT only, with no overheads or profit.
- ←
Main-material price surge beyond the risk band: sequencing between GB/T 50500-2024 Section 8.7/Appendix A price adjustment and Civil Code Article 533 change of circumstances
When main-material prices surge far beyond the contractual risk band, first complete price adjustment per GB/T 50500-2024 Section 8.7 and Appendix A (agreed risk band first; 5% fallback when unspecified/unclear; portions beyond the risk band at actual values, differences carrying VAT only, no management fee/profit); only the residual loss still grossly unfair after adjustment proceeds to 8.7.3 negotiation, and failing negotiation to Civil Code Article 533 modification or termination — a "contract first, statutory fallback" progression, not either-or. Judicial appraisal per GB/T 51262-2017 5.6.2: as agreed if agreed; adjustable but without an agreed risk band — the appointing party decides judicial appraisal per the national standard (unless already index-adjusted); agreed non-adjustable — government-priced/guided materials appraised per old Contract Law Article 63 (now Civil Code Article 513).
- ←
Hierarchy of effect and order of interpretation when tender documents, bid documents and the awarded contract conflict over material price adjustment (adjustment of the works price): substantive content follows the tendering and bidding documents; conflicts that are not substantive follow the priority order of contract documents (particular conditions first; later signing of the same class first) and the limits of those rules
A price-adjustment clause is part of the pricing and adjustment method of the 'works price' and so falls within the reach of substantive content: where the awarded contract differs from the tender documents, bid documents or letter of acceptance, those documents govern settlement of the works price (Bidding Law Art. 46; Implementation Regulations Art. 57; Fa Shi [2020] No. 25 Arts. 2 and 22). Internal conflicts not amounting to substantive departure are construed by the priority order of contract documents (GF-2017-0201 Clause 1.5: contract agreement > letter of acceptance > letter of tender with appendices > particular conditions > general conditions > technical standards > drawings > priced BOQ > other documents; for documents of the same class the latest signing prevails), that is 'particular over general, later over earlier within the same class'; but 'later over earlier' is a rule of interpretation, not a power of variation, and cannot give variation effect to a later agreement that departs from substantive content (Civil Code Art. 544: a variation whose content is unclear is deemed not varied). Where the position still cannot be fixed, construe comprehensively under Civil Code Arts. 142 and 466 and Fa Shi [2023] No. 13 Art. 1.
- ←
Construction Interpretation II, Article 9: where the contract stipulates settlement of the project price at fixed prices, a request to adjust the price on the ground of material changes in labour costs or the prices of key building materials within the construction period is not supported, leaving only two exits: 'the parties have otherwise agreed' and 'change of circumstances under Article 533 of the Civil Code'
In principle, not supported. Under Fa Shi [2026] No. 12 Article 9, where a construction contract stipulates settlement of the project price at fixed prices and a party requests adjustment on the ground of material changes in labour costs or the prices of key building materials within the agreed construction period, the people's court shall not support the request, unless the parties have otherwise agreed or the case satisfies Article 533 of the Civil Code on change of circumstances. Three points of distinction: (1) the rule negates 'adjustment requests premised on material price changes'; it does not invalidate the fixed-price clause; (2) 'the parties have otherwise agreed' is the most-used channel - where the contract lists adjustable materials, agrees a base price and a risk band, an adjustment formula or a source of published price information, adjustment follows the agreement and is not blocked by this Article; (3) only one judicial channel remains, change of circumstances, with a high threshold (unforeseeable at contract formation, a material change outside commercial risk, and manifest unfairness on continued performance) and prior negotiation required.
- ←
Whether a supplier may seek a price adjustment when building material prices rise sharply during a fixed-price procurement (sales) contract: routing by contract type (procurement contracts via sales contract rules plus change of circumstances; construction contracts via Interpretation II Article 9; government pricing via Civil Code Article 513), a comparison of three adjustable exceptions and five unsupported scenarios, a legal basis list, and points on evidence, time limits and jurisdiction
As a rule, no. A supplier who has signed a fixed-price procurement contract cannot request an increase merely because building material prices have risen sharply: a fixed price is itself the allocation of price risk, and rises and falls are commercial risks the supplier should bear at the time of contracting. Only three exceptions allow an adjustment: (1) the contract provides otherwise for price adjustment / price fluctuation adjustment (including provisional prices, market-following pricing, or settlement at published price information), adjusted within the agreed band; (2) the subject matter is under government pricing or government guidance pricing and the government adjusts the price within the delivery period, in which case the price at the time of delivery applies (Civil Code Article 513); (3) the case satisfies change of circumstances under Civil Code Article 533 (unforeseeable at contracting, not a commercial risk, continued performance manifestly unfair, and renegotiation required first), and the subject matter is not a bulk commodity of active market attributes with large long-term price fluctuations -- steel, cement and other principal building materials fall squarely within the exclusion proviso of Article 32(1) of Fa Shi [2023] No. 13, so this route usually fails. Fixed prices in construction contracts are governed separately by Article 9 of Fa Shi [2026] No. 12, which leaves only two exits: contrary agreement or change of circumstances.
- ←
Rules for handling contract price adjustment for cost fluctuation in final account review and construction cost expert assessment: routing by contract type, price-dating principles for delay periods, the exception for government-priced materials, and the eight categories of costs not adjusted for changes in costs listed in GB/T 50500-2024 clause 8.7.6
Final account review and expert assessment proceed on two levels. (i) Routing by contract type: for lump-sum contracts, unless otherwise agreed, cost fluctuation is generally not adjusted, and a contractor claiming adjustment for change of circumstances or prolonged duration must proceed by claim; for unit-rate contracts the agreement prevails, and absent or unclear agreement the matter is resolved by reference to national, local or sector provisions, with labour, materials and plant outside the contractually adjustable scope not adjustable. Price-dating during delay: where the delay is not attributable to the contractor, the higher of the prices at the planned and actual progress dates applies; where attributable to the contractor, the lower applies; concurrent delay is shared by sequence and responsibility. (ii) Hard constraint on the scope of adjustment: GB/T 50500-2024 clause 8.7.6 lists eight categories of costs not adjusted for changes in costs (construction consumables, small and medium tools, preliminaries, plant and small tools costs other than fuel and power, material costs of items outside the agreed adjustable list, changes beyond the agreed scope or band, overheads and profit, and costs arising from the contractor's own causes); where the contract sets no band or sets it unclearly, fluctuation beyond 5% may be adjusted per Annex A (8.7.2), and abnormal movements of other materials outside the agreed adjustable scope may be handled by equitable risk allocation, by negotiation or by adjustment to actual costs (8.7.3, 3.3.6).
- ←
The step chain of adjusting on published price information: fix the adjustable list -> lock base price C0 -> take period prices Ci -> difference x adjustable quantity Q -> adjust the excess over the risk band -> book into progress and settlement, with fallbacks for missing periods and items and the Q test (GB/T 50500-2024 Appendix A.2; against superseded GB 50500-2013 Appendix A.2)
Six steps: (1) fix the adjustable material / labour list (2024: 3.3.5 item 2 + Appendix G Tables G.2.1-1/-2; 2013: 9.8.2 agreed scope, else over 5% adjusts the excess) -> (2) lock C0 = the market price 28 days before the tender deadline (non-tendered: signature), source, publisher and quarter (month) stated (A.2.1; 2013 A.2.3) -> (3) take Ci per measurement period; several prices within a period take the arithmetic mean, the quantity-weighted mean or the main-consumption-period price (A.2.1, A.2.3) -> (4) difference x Q (2024 A.2.1 formula; 2013 has only the 'excess on actuals' principle, no explicit formula) -> (5) adjust only beyond the agreed band r (rising Ci - C0(1+r), falling C0(1-r) - Ci; absent a band, over 5% - 8.7.2 / 2013 9.8.2) -> (6) book into cumulative progress and pay with progress and interim settlements (9.4.6, 8.1.6). Missing periods fall back in order: contract rule -> same-period alternative source -> in-period averaging -> provisional posting on current information with later truing (A.2.2) -> employer-recognised purchase price (A.2.5; 2013 A.2.3 item 4: 3 working days' silence deems approval; unreported self-purchase refused by the employer never adjusts) -> market enquiry by three parties; 'carry the last period forward' has no national-text basis outside the index method (2013 A.1.2). Q follows the contractual quantity rule; the default is the consumption of measured completed work - never signed list quantities or purchase / invoice totals; differences carry VAT only (3.3.5 item 4).
- ←
Defining the scope of adjustable (price-adjustable) materials: locked by contract annex tables, not share thresholds; auxiliary and low-value materials outside adjustment (neither coefficient-merged nor overheads-lumped); the negotiation channel for unlisted materials' abnormal swings (GB/T 50500-2024 clauses 3.3.1, 3.3.5, 8.7.3, 8.7.5, 8.7.6; Appendix G.2, A.2.1)
GB/T 50500-2024 sets no material-cost share threshold: the adjustable scope locks item by item in annex Tables G.2.1-1 / G.2.1-2 (Appendix G.2) - tenderer filling name, specification, unit, base price and risk band, bidder the price, quantities per the contractual rule (3.3.5, G.2.1). Auxiliary and low-value materials (consumables, small tools, preliminaries, non-agreed materials) plus overheads and profit never adjust for price moves (8.7.6) - there is no national channel 'merging auxiliaries by coefficient', nor are they an overheads lump: their price risk sits inside the material cost of the all-in rate. Unlisted materials adjust in principle never; only on abnormal, unforeseeable-at-contracting moves making performance plainly inequitable may the parties negotiate band or sharing per equitable allocation (8.7.3). Free-issue and provisionally priced items sit outside 8.7.2~8.7.4 (8.7.5). Local share-threshold practices are local documents - verify current numbers.
- ←
Fee boundary for material price adjustment: the price difference carries VAT only, with no management fee or profit; the eight cost categories under Clause 8.7.6 are not adjusted (GB/T 50500-2024)
Per GB/T 50500-2024 Clause 3.3.5 item 4, price differences of labor, materials, and machinery fuel/power carry VAT only — no management fee or profit; Clause 8.7.6 lists eight categories not adjusted for price changes (construction consumables, small tool usage, preliminaries, other machinery usage beyond fuel/power, materials outside agreed adjustable items, changes beyond the agreed scope and band, management fee and profit, contractor's own-cause costs); Clause 8.7.3 opens a negotiation exception for abnormal, unforeseeable fluctuations.
- ←
Direction-specific base rules in the price adjustment method based on published price information when the contractor's tender price deviates from the base price (GB/T 50500-2024 Annex A.2.4, corresponding to Section 9.7 of the superseded GB 50500-2013): rises judge on the higher of the two prices, falls on the lower, a two-way disadvantage that blocks arbitrage, with the selection boundary against the Annex A.1 index method
Under GB/T 50500-2024 Annex A.2.4, the published-price-information adjustment applies a direction-specific base: the base for upward adjustment (price rise) is the higher of the base price C0 and the tender price P, and the base for downward adjustment (price fall) is the lower of the two. Hence when the contractor's price is below the base price (P < C0), rises are judged on the base price C0 and falls on the tender price P; when the price is above the base price (P > C0) the reverse applies; when the price equals the base price, both directions are judged on C0. Only the portion crossing the risk band threshold is adjusted as actually incurred; below the threshold nothing is adjusted; and the price differential carries VAT only, with no overheads or profit (3.3.5).
- ←
Contract price adjustment calculation for VAT rate changes (GB/T 50500-2024 clauses 8.8.6 and 3.2.11) and the negative finding that a mere re-versioning of local charge standards / percentage-rate documents is not a 'change of laws and regulations' (T/ZBD 100.4-2023 clauses 4.4.1, 4.4.8, 3.1.4)
A VAT rate change adjusts the difference only, under clause 8.8.6 of GB/T 50500-2024: works priced and paid after the new rate takes effect are charged VAT at the adjusted rate, and the difference from the VAT computed at the original rate of the contract base date adjusts the contract price; amounts paid before implementation are not retraced. Per clause 3.2.11 the taxable base is the total of the bills of work items, preliminaries and other charges (less provisional sums for nominated specialist works), so delta VAT = B x (r1 - r0), and expressed on the original tax-inclusive price P1 = P0 x (1 + r1) / (1 + r0). Local consumption quota manuals, on-cost norms and charge standards / percentage-rate documents are not themselves laws or regulations; they are the 'provisions issued accordingly' (the calculation basis) in clause 8.8.1, so a mere re-versioning does not constitute an adjustable 'change of laws and regulations' (T/ZBD 100.4-2023 clause 4.4.8: no adjustment for version updates of valuation rules). However, changes after the tender submission deadline in government-fixed and government-guided prices, policy rates, or mandatory national standards fall under the clause 4.4.1 exception: works prices after the change takes effect are adjusted, unless the contract expressly allocates the price risk of such elements.
- ←
Selecting between the two methods of contract price adjustment for changes in costs: comparison of applicable conditions, clause-by-clause contrast and same-contract mixing boundaries of the Appendix A.1 index-based adjustment and the Appendix A.2 adjustment based on published price information under GB/T 50500-2024
The two methods share an identical adjustable scope, base time point and trigger threshold (only labour cost, key material cost and the fuel and power cost of construction plant are adjustable; the base time point is 28 days before the tender deadline; where the contract sets no band or sets it unclearly, fluctuations beyond 5% are adjustable; the differential carries VAT only, never overheads or profit). The difference lies only in the price variable. A.1, index-based (formula) adjustment, takes the VAT-exclusive contract price P0 as the base and weights the fixed weight A and the variable weights B1...Bn of each adjustable factor by the ratio 'current index / base index' - the index source is agreed in the contract, the agreed fluctuation band is folded into the base price index, and where an index is missing the previous measurement period's index may be used provisionally. A.2, adjustment based on published price information, takes the adjustable factor quantity Q as the base and computes the money price differential between the base price C0 and the measurement-period market price Ci less the risk band coefficient r; the base price and the market price are each chosen from three sources (market price used in setting the tender price ceiling / published price information of the cost management agency / tender-winning prices published by the trading centre), whether the band is exceeded is determined by scenarios of the tender price against the base price, and under the purchase-price route the contractor must submit quantity and unit price to the employer for checking before purchase (no reply in time is deemed approval). The standard itself has no dedicated 'applicable conditions' clause, only 'one of the methods of Appendix A'; the choice is first a matter for the contract; where one contract assigns different methods to different adjustable factors, they must be entered separately in Table G.2.1-1 (published price information method) / Table G.2.1-2 (index method), without double counting the same differential.
- ←
The index-based adjustment method (GB/T 50500-2024 Appendix A.1): the adjustment formula, fixing the fixed weight A and variable weights Bi, and the sources and timing of price indices (factors)
The index method computes dP = P0 x [A + sum Bi x (Fti/F0i) - 1]: P0 the net-of-VAT contract price of the measurement period; A the fixed weight and Bi the weights of adjustable factors on the net-of-VAT contract price, with A + sum Bi = 1; weights and base indices are ranged by the employer and fixed in the tenderer's price-index and weight schedule of the tender-letter appendix, absent which the tender price ceiling's weights may be used (A.1.4); base indices at the contract base date (28 days before the tender deadline for tendered works), current indices per period, the previous period's usable provisionally (A.1.2/A.1.5/A.1.6); the index source is contractual (2024 no longer mandates authority indices first); adjustments carry VAT only, never overheads or profit.
- ←
Settlement pricing when the confirmed price of a provisionally priced material differs from published price information: the procedurally formed confirmed price (net award price, or employer-confirmed enquiry price) replaces the provisional sum, published prices serving only as the contractually agreed base or a provisional fallback in disputes
Settlement follows the confirmed price formed under the contractual procedure - for mandatory-tender items, the net-of-VAT material award price replaces the provisional price; otherwise the employer-confirmed (or jointly enquired) net price does (GB/T 50500-2024 clauses 8.4.1, 8.4.5); published price information neither replaces the confirmed price nor caps or floors it - it applies only where the contract makes it the base, or where a period market price is missing or the dispute is large, provisionally, 'to be trued up in later payments against actual market prices' (Appendix A clause A.2.2). The difference adjusts only the material provisional price (net) within the all-in unit rate, other cost heads unchanged, carrying VAT but never overheads or profit (clauses 8.4.6, 3.3.5 item 4).
- ←
GB/T 50500-2024 clause set 8.8: adjustments of contract price and duration for changes in laws, regulations and policies - scope, the one-way adjustment rule during extended durations, and no adjustment of overheads and profit
GB/T 50500-2024 clause 8.8: for laws, regulations, policy provisions or government interpretations newly enacted, amended or repealed after the contract base date, price and/or duration adjust per the contract and the rules published by the authorities; policy changes during contractor-caused extension adjust downward only (8.8.2), during employer-caused extension upward only (8.8.3); where policy change causes material extension and subsequent abnormal market price moves, the price-fluctuation rules apply (8.8.1/8.8.2/8.8.3); overheads and profit inside the total and unit prices never adjust for policy changes (8.8.5).
- ←
The non-adjustment boundary of material price adjustment: the eight cost classes never adjusted for price moves, the BOQ items outside routine adjustment, and the negotiated handling of abnormal fluctuation (GB/T 50500-2024 clauses 8.7.3 / 8.7.5 / 8.7.6)
GB/T 50500-2024 clause 8.7.6 lists eight classes never adjusted for price moves: construction consumables, small tools, preliminaries, other plant costs, materials outside the agreed adjustable items, price moves beyond the agreed scope and band, overheads and profit, and contractor-cause costs; clause 8.7.5 keeps the adjustment away from employer-supplied material items and provisionally priced material items; clauses 8.7.3 and 3.3.6 are the negotiated channels for abnormal fluctuation or missing agreement. Differences carry VAT only, never overheads or profit.
- ←
Charging boundary of material price differentials (construction-period adjustment): VAT only - no overheads or profit, and no participation in the charging bases of total-price preliminaries or statutory levies (GB/T 50500-2024 Article 3.3.5 paragraph 4, Article 8.7.6)
Differentials formed by construction-period material price settlement adjustments carry VAT only - no overheads or profit, and they do not join the charging bases of total-price preliminaries or statutory levies. Basis: GB/T 50500-2024 Article 3.3.5 paragraph 4 - differentials of labour, materials and the fuel-power element of plant within all-in unit rates carry VAT but not overheads or profit; Article 8.7.6 items 3 (preliminaries) and 7 (overheads and profit) are listed among fees not adjusted for cost fluctuation; and since total-price preliminaries charge on labour plus plant, and statutory levies on quota labour, material differentials - being material in nature - fall outside both bases anyway. Express contract terms prevail.
- ←
Adjustment of contract prices of signed works upon quota revision or updates of measurement and pricing rules: pure version updates are not adjusted; policy-based rates, government pricing and mandatory standard changes are adjusted
Where a party seeks a contract price adjustment solely on the ground that the measurement rules or pricing rules have been updated, the expert appraiser maintains the pricing principles of the original price determination or tender in the contract and makes no adjustment (T/ZBD 100.4-2023 Article 4.4.8). The exception is Article 4.4.1: where government-fixed and government-guided price items, policy-based rates or national mandatory standards change after the tender deadline, the appraiser adjusts the price of the works executed after the time of change, whatever the contract says, issuing alternative opinions with explanations; but where the contract has expressly agreed the risk allocation for such element prices, the contract governs. Under BOQ pricing, price changes caused by laws, regulations and policy changes after the base date (newly added, amended or repealed provisions, changed government interpretations) are adjusted per GB/T 50500-2024 Article 8.8.1, and the overheads and profit within the total price and unit rates are not adjusted (8.8.5); where national fiscal and tax policy changes the VAT rate, VAT is computed at the new rate and the price adjusted by the difference between the old and new rates (8.8.6). The appraisal method is also chosen by contract type (T/ZBD 100.4-2023 Article 4.2.4).
- ←
Pricing channels for works outside the contract scope and unforeseen works: recognising and pricing additional works, when dayworks apply, and the rules for using provisional sums
Where the contractor, at the employer's request, completes additional works outside the agreed scope, the price may be computed per the item-setting requirements, measurement rules, contract rates and tendered rate levels of the national and sector quantity take-off standards, or the measurement and pricing rules may be renegotiated and an additional-works contract or supplementary agreement signed (GB/T 50500-2024 clause 8.10.1). In settlement review, where the parties have not jointly recognised additional works, then absent contract agreement otherwise, any of "contract scope = whole project / single work -> a single work added", "single work -> ancillary or independently tenderable specialist works outside the scope added", "specialist subcontract -> other specialist works outside the scope added" recognises the addition; without a supplementary agreement and without clear pricing principles and methods, the original contract's principles do not necessarily apply (T/ZBD 100.5-2023 clause 3.1.10). Ten classes of matters - added or substituted works not measurable from drawings / variations / contract rules etc. - may be measured and priced as dayworks (clause 7.5.2); provisional sums serve insufficiently foreseeable or detailed works, measured and priced under the variation rules, the contract price adjusting for the difference from the provisional sum including VAT (clause 8.3.2).
- ←
Rules for determining the material adjustment base price (C0): base date, one-of-three sources and the adjustment computation base (GB/T 50500-2024)
The base price C0 = the market price level 28 days before the bid closing date (for non-tendered works, 28 days before contract signing); that instant is the contract base date (term 2.0.21). The source is one of: (1) the market price used in the maximum bid price; (2) the current quarter's (month's) guidance price of the cost management agency; (3) the winning-bid price of analogous works under the same conditions published by the local trading center — all must represent the base-date price level, and the tender documents must state the source, publishing agency and specific quarter (month). Where the guidance price is the base, whether the bid is below/above/equal to the base decides the computation base of the excess portion (appendix A.2.4, preventing high/low-bid arbitrage); the price-index method corresponds to the basic price index F0.
- ←
Can published price information directly serve as the basis for material price adjustment: legality + three preconditions (listing / beyond band / tax) (GB/T 50500-2024)
Published price information (government guidance prices) is a price source expressly recognized for price adjustment (for fluctuation) (Appendix A.2.1: both the base price C0 and the measurement-period price Ci may adopt the current published price information issued by the cost management agency; A.2.4: where published price information serves as both base price and current price, adjust within the agreed risk band), but adjustment is not unconditional and full-scope: (1) the material must be listed in the contract annex "schedule of price-adjustable key materials" (Table G.2.1-1; not listed, not adjusted); (2) only the portion beyond the contract-agreed risk band is adjusted to actual, the band being contractor-borne; (3) where the contract sets no band, fluctuation beyond 5% is the fallback trigger (8.7.2). The price difference carries value added tax (VAT) only, not management fee or profit (3.3.5).
- ←
Order of application between contract agreement and national pricing standards in construction cost expert assessment (judicial appraisal): contract prevails where agreed, standards as fallback (GB/T 51262-2017 Section 5.3 layered rules)
Construction cost expert assessment follows "contract prevails where agreed": where the contract is valid and its pricing basis clearly agreed, the appraiser must appraise per the contract and may not overturn the agreement on the ground that "national pricing standards are mandatory"; national pricing standards (the BOQ pricing standard, quota norms, etc.) serve only as fallback reference where the contract has no agreement or the agreement is unclear, and whether to adopt them is decided by the commissioning party (court/arbitral body). GB/T 51262-2017 Clauses 5.3.3-5.3.5 layer the handling: unclear agreement -> ascertain the facts of performance and appraise accordingly, or where unperformed suggest "appraising by reference to the pricing bases, pricing methods, and market price information at signing applicable at the project's location in the same period"; no agreement -> likewise propose the reference suggestion and appraise per the commissioning party's decision; contradictions -> refer the choice of applicable clause to the commissioning party, and where not yet clarified, issue separate appraisal opinions under the differing clauses for its judgment.
- ←
Price adjustment (for fluctuation) calculation for ready-mixed (commercial) concrete: whole-factor adjustment per m³, adjustment to actual beyond the risk band, and tax treatment (GB/T 50500-2024 Appendix A.2 adjustment based on published price information)
Ready-mixed concrete is adjusted as one whole adjustable factor per m³ (the published price information (government guidance prices) already includes raw-material cost; cement, sand/gravel, and admixtures must not be adjusted separately again, to avoid double counting), using the GB/T 50500-2024 Appendix A.2 adjustment based on published price information: beyond-band unit price difference = Ci - C0×(1+r) on a rise, or C0×(1-r) - Ci on a fall; adjustment amount = unit price difference × Q; the agreed risk band (no-adjustment tolerance, e.g. ±5%) prevails; where not agreed or unclear, fluctuation beyond 5% is the fallback trigger (8.7.2); the price differential attracts value added tax (VAT) only, not management fee or profit (3.3.5); where the tender price differs from the base price (reference price for adjustment), apply the A.2.4 cross-base rule against arbitrage. Worked example: C0=480 CNY/m³, Ci=530 CNY/m³, r=5%, Q=1000 m³; fluctuation 10.4% triggers; beyond-band unit difference 26 CNY/m³; adjustment 26,000 CNY; including 9% VAT the tax-inclusive amount is 28,340 CNY.
- ←
Appendix G main materials (adjustment) list of GB/T 50500-2024: locking stage and adjustment-quantity caliber (contract annex / completed quantities per measurement cycle)
Tables G.2.1-1/2 are filled during tendering and locked as a whole as a contract annex at signing: the tenderer fills scope/base price (market price level 28 days before the bid deadline)/risk band; bidders fill tender prices and agree price data in the tender-letter appendix (3.3.5 item 2, A.2.1). Adjustment quantities are neither tender quantities nor actual purchase quantities but follow "the quantity calculation method the parties specify in the contract" (table note 2, A.2.1); the default framework is quantities corresponding to completed qualifying work in the measurement cycle, measured in segments per adjustment cycle and accumulated (7.1.3).
- ←
Adjustment of the contract price (GB/T 50500-2024 Chapter 8): eleven triggering events, mechanism by section, and FIDIC mapping
Adjustment of the contract price is the mechanism for changing the contract price during performance. GB/T 50500-2024 Cl. 8.1.1 lists eleven triggering events: BOQ errors, provisional sums, PC sums (provisional estimates), contractor's services, dayworks, changes in costs, changes in laws and policies, variations, additional works, claims, and other events agreed by the parties; the procedure runs submit, check, re-check, review and confirm (8.1.2). Key mechanics: BOQ errors and variations share one re-rating ladder (identical items at contract rates; analogous items converted; different items negotiated), with a 15% quantity boundary for re-rating (8.2/8.9); provisional sums are controlled by the employer and any unused balance reverts at final account (8.3); PC-sum items are replaced by tender prices — materials pre-VAT, specialist works VAT-inclusive (8.4); dayworks are measured under 7.5 (certified dayworks records) and priced at the BOQ daywork rates (8.6, with deemed approval if verification is overdue, 7.5.5); changes in costs are adjusted beyond the agreed band — 5% by default — by index-based (formula) adjustment or adjustment based on published price information (8.7 + Annex A), the differential carrying VAT only; changes in laws pivot on the base date, adjusting price and/or time for enactments, amendments, repeals or new interpretations after it, with no upward adjustment during contractor-caused delay (8.8); additional works may follow contract rates or freshly negotiated rules under a supplementary agreement (8.10); claims cover events outside 8.2-8.10 — compensatory, not punitive, and mutual, with profit added for eight categories of employer-risk events (8.11). FIDIC counterparts sit scattered across Clause 13 (variation valuation 13.3, provisional sums 13.4, changes in laws 13.6, changes in cost 13.7 — 2017 numbering) and Clause 20 claims (28-day hard time bar): adjacent institutions, not chapter-for-chapter equivalents.
- ←
Price adjustment for wires and cables: itemized by full specification, copper-linkage agreements, and handling missing published price information (government guidance prices) (GB/T 50500-2024 Appendix A.2)
Cable price adjustment shares the same mechanism as steel (GB/T 50500-2024 Appendix A.2 adjustment based on published price information (government guidance prices)): difference = SUM[(Ci - C0 x (1 +/- r)) x Q], only the portion exceeding the risk band is adjusted on an actual basis; r as agreed takes precedence, and if not agreed, fluctuation beyond 5% is adjustable (8.7.2); C0 = market price 28 days before the tender deadline (= FIDIC Base Date) (for non-tendered projects: 28 days before contract signing); the difference carries value added tax (VAT) only, no management fee or profit. Cables must be listed item by item in Table G.2.1-1 by full specification (voltage class x cores x cross-section x armor x flame-retardance) and adjusted separately — merging and averaging is strictly prohibited; the copper-linkage method must fix in the contract the copper content/conversion coefficient and the copper-price source; for missing published price information, the paths are employer's approval of material prices / market price enquiry, with symmetric unit bases.
- ←
Steel price adjustment calculation: price-information adjustment formula, per-specification per-period threshold checks with adjustment on actual basis, and tax treatment (GB/T 50500-2024 Appendix A.2)
Steel price adjustment uses the price-information adjustment method (GB/T 50500-2024 Appendix A.2): △P = Σ[(Ci − C0·(1±r)) × Q] × (1 + VAT rate), adjusting only the portion beyond the risk band on an actual basis; the agreed risk band prevails, with the beyond-5% fallback where not agreed or unclear (8.7.2). Each specification must be checked independently each period for exceeding the risk band (base prices, published price information, and increase rates differ; specifications within the risk band are not adjusted for the period); the price difference carries VAT only, no management fee or profit (3.3.5); when checking adjustment tables, first look at whether the bid price is above or below the base price (A.2.4 determines the excess-calculation base).
- ←
Appendix A price adjustment (for fluctuation) methods for changes in costs, GB 50500-2013 vs GB/T 50500-2024: weighting coefficient basis and adjustment threshold differences
The two editions share the same formula skeleton in Appendix A (index-based (formula) adjustment dP = P0[A + sum BiFit/Fi0 - 1]; adjustment based on published price information adjusts the portion beyond the risk band (no-adjustment tolerance, e.g. ±5%) at actual values); differences lie in the basis and mechanisms: (1) weighting — 2013 variable weights are 'proportions of the total tender price in the tender letter' (including VAT), 2024 uses 'weights of the contract price excluding VAT' (separation of net price and VAT), and 2024 adds A.1.4 fallback 'where variable weights are not agreed, the corresponding weights of the tender price ceiling may be used' and A.1.1 merges the fluctuation range into the base price index F0; (2) thresholds — both editions' fallback is 5% (beyond which actual-value adjustment applies; 2013 clause 9.8.2, 2024 clause 8.7.2), and 2024 adds the sign rule for the r risk band coefficient, defines the base price (reference price for adjustment) as the market price 28 days before the tender deadline (= FIDIC Base Date) (28 days before contract signing for non-tendered works), and the 8.7.6 list of items not subject to price adjustment. GB 50500-2013 was mandatory (replaced); 2024 is recommended national standard GB/T.
- ←
Price-difference calculation method after material prices exceed the risk band (price-information adjustment method, GB/T 50500-2024 Appendix A.2)
The excess beyond the risk band is adjusted per actuals: when prices rise, unit price difference = Ci - C0 x (1 + r); when prices fall, = C0 x (1 - r) - Ci; adjustment amount = unit price difference x adjusted quantity Q; where the contract does not agree a risk band, fluctuation beyond 5% triggers adjustment (Clause 8.7.2); where the bid price differs from the base price, the cross-basis rule of A.2.4 applies to prevent arbitrage; the price difference carries VAT only, with no management fee or profit.
- ←
Which period's published price applies to settlement material prices: the two-date system — base price locked at the contract base date (28 days before bid closing) plus period-by-period pricing per measurement cycle (GB/T 50500-2024 Annex A.2 price-information method)
Settlement material prices are not taken from a single period (completion date or submission date) but from the "base price locked at the contract base date + current prices per measurement cycle" two-date system: base C0 at 28 days before bid closing (non-tendered: 28 days before contract signing); current Ci per measurement cycle from the cost authority's published price information (or jointly confirmed market prices, or same-period trading-center award prices); differences beyond the contractual risk band are computed per cycle and totalled into the final account; with no band agreed, a 5% fluctuation triggers adjustment; express contracts govern.
- ←
Alternative adjustment paths when price information lacks the specification: mutually confirmed price / purchase price / awarded-bid price fallbacks + the same-caliber red line for C0 and Ci (GB/T 50500-2024 Appendix A.2)
Price information is only one of the Ci sources listed in A.2.1; lacking the specification does not mean adjustment is impossible: determine Ci per (1) contract agreement, (2) the market price of the measurement period confirmed by both parties, (3) the purchase price determined by the employer (submitted before purchase; deemed accepted upon overdue silence), (4) the awarded bid price of the trading center for similar works under similar conditions in the same period; C0 takes prices by the same rules; where information is temporarily missing, provisionally account per the published price and settle later. Red lines: C0 and Ci must be of the same caliber; the alternative price must represent the market price level of the measurement period; keep a full trail of certified records of agreed material prices.
- ←
Mechanism for material price changes under fixed unit-price contracts: unit price locked + quantities at actuals + beyond-band adjustment (GB/T 50500-2024)
Under unit-price contracts the all-in unit rate is fixed within the contract-agreed risk conditions and quantities are determined at what is actually completed and should be measured (2.0.6); material prices follow "contract agreement first, statutory fallback": an express adjustment clause adjusts per the agreement -> agreement of adjustability without method follows industry pricing documents -> express non-adjustment is executed (unless the clause is invalid) -> no agreed band: fluctuation beyond 5% adjusts per Appendix A (8.7.2); the difference carries VAT only, no management fee or profit (3.3.5).
- ←
GB/T 50500-2024 replacing GB 50500-2013: what GB becoming GB/T means, expiry of the 2013 mandatory provisions, and the 2025-09-01 effective date
MOHURD Announcement (No. 212 of 2024, issued 2024-11-26) approved the "Standard for measure and valuation of construction work with bills of quantities" as national standard GB/T 50500-2024, effective 1 September 2025, repealing GB 50500-2013 simultaneously. GB = mandatory national standard, GB/T = recommended (Standardization Law, 2017 revision, Article 2: mandatory standards must be executed; adoption of recommended standards is encouraged); all 2013 mandatory provisions expire with the standard, and the 2024 edition sets no mandatory provisions. Typical contrast: 2013 Clause 3.1.1 (mandatory) "works contracted with state-owned funds must use BOQ pricing" becomes 2024 3.1.1 with fiscal/state-funded works "shall" and others "should" use BOQ pricing. The binding force of a recommended standard is realized through incorporation in tender documents and contracts.
- ←
Price-taking time point for the tender price ceiling: the latest issue of price information published as at the date of completion of preparation; "28 days before the tender deadline" is the adjustment base price time point, not the price-taking time point
The tender price ceiling (employer's maximum acceptable price) takes prices at the price level of the preparation period: use the latest issue (month/quarter) of construction cost price information published as at the date of completion of preparation, noting the issue in the deliverable; where a difference from actual construction-period conditions exists, adjust reasonably (GB/T 50500-2024 Clause 5.2.9). "28 days before the tender deadline" (for works not subject to tendering, 28 days before the date of contract signing) is the lock-in time point for the contractual adjustment base price C₀ in Appendix A.2.1, used for adjustment for cost fluctuation after award, and is unrelated to price-taking for the tender price ceiling.
- ←
GB/T 50500-2024 rules for determining the base date: agreement first; tendered works = 28 days before the tender deadline, non-tendered works = 28 days before contract signing (term 2.0.21)
The base date (GB/T 50500-2024 term 2.0.21) is the date on which the contractor, during the tender period, determined the tender total price, the BOQ all-in unit rates and their sums, and it serves as the price datum for adjustment for changes in costs and for adjustment arising from changes in laws, regulations and policies. Determination order: agreement first, statutory fallback — where the tender documents (inquiry documents for non-tendered works) and the contract are silent, tendered works take 28 days before the tender deadline (= FIDIC Base Date) and non-tendered works 28 days before contract signing. That point is at once the base period of index-based (formula) adjustment (A.1.6), the base price C₀ of adjustment based on published price information (A.2.1), and the common starting point for adjustment for changes in laws, regulations and policies (8.8.1).
- ←
Whether actual purchase quantities can directly serve as the material adjustment quantity: triple filtering of contract agreement + employer confirmation + not exceeding rational consumption (GB/T 50500-2024)
The purchase quantity cannot directly serve as the adjustment quantity Q; it must pass triple filtering: (1) the contract/special clauses expressly agree the purchase-quantity caliber (A.2.1, Note 2 of Table G.2.1-1); (2) submission to the employer for verification and confirmation before purchase, deemed accepted upon overdue silence, batch purchases averaged by weight (A.2.5); (3) capped by the rational consumption of works completed in the period — the excess is borne by the contractor per 3.6.3, and the appraisal caliber is "actual consumption = requisition quantity − inventory" (T/ZBD 100.4-2023 Clause 4.5.7). Safest: currently measured quantities × quota consumption (including loss).
- ←
Material price adjustment channels under fixed lump-sum contracts: no adjustment within the agreed risk band, adjustment beyond the risk band, mandatory adjustment for statutory causes
Under a fixed lump-sum contract, cost fluctuations within the agreed risk band are not adjusted, but "fixed" ≠ an uncapped lump sum: ① contract-agreed price adjustment clauses are applied as agreed; ② where no risk band is agreed or the agreement is unclear, the portion of labour cost, principal material cost and construction machinery fuel and power cost fluctuating beyond 5% may be adjusted per Appendix A (8.7.2 fallback); the standard prohibits uncapped risk allocation to one party / "all risks" lump-sum wording (3.3.1), and cost movements beyond the agreed risk band are borne by the employer (3.3.2); ③ materials under government pricing/guidance pricing follow the new prices; ④ policy-driven adjustments to labour cost; ⑤ abnormal large fluctuations may be negotiated under the change of circumstances doctrine (8.7.3). Price adjustment claims under lump-sum contracts are procedurally handled as claims (T/ZBD 100.5-2023 3.1.7); price differences carry value added tax (VAT) only, no management fee or profit (3.3.5).
- ←
GB/T 50500-2024, China's BOQ pricing standard: positioning, 2024-vs-2013 changes, chapter map and card-group navigation
GB/T 50500-2024, the China national pricing standard for BOQ-based pricing (MOHURD Announcement No. 212 of 2024, approved 26 November 2024), came into force on 1 September 2025 and repealed GB 50500-2013. Its status shifted from a partly mandatory code to a recommended national standard (GB to GB/T), aiming to regularise pricing rules and let the market form construction costs. It governs pricing activity in tendering, contracting and execution for construction works; EPC and other general-contracting models apply it by reference, and the requirement that state-funded projects use BOQ pricing is carried by a MOHURD ministerial order. Nine headline revisions (per the foreword): risk scope and allocation rules by contract form; a new bid clarification mechanism; revised pricing of preliminaries; the 'contract price agreement' chapter replaced by contract selection and requirements; revised measurement and adjustment rules; site visas abolished and additional-works pricing introduced; interim settlement by construction stage added; dispute resolution revised; the cost-expert-assessment chapter deleted. The structure was rebuilt from 16 chapters into 12 chapters plus annexes: 'tender control price' renamed tender price ceiling; completion settlement and contract-termination settlement merged into 'works settlement and payment' (absorbing stage settlement); dispute resolution and expert assessment merged; pricing tables moved to annexes (with a new Annex G, schedule of price-adjustable key materials).
- ←
Order of application of pricing bases for the final account: contract agreement first (agreed terms prevail); quota norms and construction cost management agency's pricing bases as fallback
Final account prices take the contract as the fundamental basis: pricing activities follow "statutory priority, agreed terms prevail" (GB/T 50500-2024 Clause 1.0.3) — where the contract provides for price determination, adjustment methods, and quantity calculation rules, the agreed terms prevail; only absent or unclear agreement are national, industry, and local pricing bases (including quota norms) referenced (T/ZBD 100.5-2023 Clause 1.4.2). In construction cost expert assessment (judicial appraisal) of price disputes, the fallback order is fair market price → pricing quota norms → cost data + on-cost level (T/ZBD 100.4-2023 Clause 3.1.6).
- ←
Handling paths when published price information clearly deviates from actual market prices: unify the bases of comparison first to exclude illusions, then correct by scenario (temporary adjustment with later true-up / price certification / expert assessment as fallback)
Published price information is only a reference guide price issued by the cost management agency (GB/T 50875-2013 Clause 2.1.16), not a mandatory price. On deviation, first unify the bases of comparison — VAT-inclusive/exclusive, delivered/ex-works, specification and unit — to exclude illusions; where an adjustment dispute is significant, temporarily use the current published price information and true up later against actual market prices, refunding the excess or paying the shortfall (GB/T 50500-2024 Appendix A.2.2); absent agreement or where the agreement is unclear, substitute the price confirmed by mutual market price enquiry and certify the price before purchase (deemed approval upon lapse of the response period, A.2.5); construction cost expert assessment ranks the certified-and-approved price > contract-agreed price > mutually agreed price (GB/T 51262-2017 Clause 5.6.4). Enquiries from >= 3 suppliers with records in a register; adjust only beyond the agreed risk band (5% if not agreed).
- ←
Overview of the full-chain use rules for construction cost published price information: nature, price calibers, stage-by-stage pricing, and frequent misconceptions
Published price information means reference guide prices issued by cost management agencies, running through the whole chain "price-limit compilation - bid verification - adjustment base - settlement fallback". Five iron rules: contract agreement first; caliber unification (tax-inclusive/exclusive, delivered/ex-factory, procurement-keeping fee); period alignment (base price locked 28 days before the bid deadline, measurement price matched to the measurement period); adjust only beyond band (±5% if not agreed); confirmation with records (submit to the employer before purchase, silence deemed acceptance).