Engineering Knowledge Cards.
Confidence HighUpdated 2026-11-08

Valuation rules for the four variables of material price adjustment (adjustment based on published price information) and the step-by-step calculation flow: base price C0, risk band r, measurement-period market price Ci and adjustable quantity Q (GB/T 50500-2024 Annex A.2)

The published-price-information method takes its values in five steps. (1) C0 = the market price level 28 days before the tender submission deadline (for non-tendered works, 28 days before the contract signing date), one source chosen from three (the market price used in setting the tender price ceiling / the quarterly (monthly) published price information of the cost administration body / award prices of comparable projects published for the same period by the trading centre); the tender documents must state the source, the issuing body and the specific quarter (month). (2) r: the contractual agreement prevails; where none exists or it is unclear, adjustment is allowed once the movement exceeds 5% (clause 8.7.2), the sign of r following the sign of dC (positive on increase, negative on decrease). (3) Ci takes the current price of the measurement period; with multiple prices, use the arithmetic mean / the weighted mean against executed quantities / the price over the main-consumption construction period; where a price is missing or disputed, published price information may be used provisionally and trued up later; purchase prices must be submitted to the employer for verification before purchase, silence within the time limit being deemed approval. (4) Q is calculated under the contractual quantity calculation rules. (5) Adjustment only where |Ci - C0| / C0 > r; on increase the excess unit differential = Ci - C0(1+r), on decrease = C0(1-r) - Ci; multiplied by Q it bears VAT only, with no overheads or profit.

Applicable Codes

  • GB/T 50500-2024 App. A.2.1
  • GB/T 50500-2024 App. A.2.2
  • GB/T 50500-2024 App. A.2.3
  • GB/T 50500-2024 App. A.2.4
  • GB/T 50500-2024 App. A.2.5
  • GB/T 50500-2024 App. G Table G.2.1-1
  • GB/T 50500-2024 第3.3.5条
  • GB/T 50500-2024 第8.7.2条
  • GB/T 50500-2024 第8.7.4条
  • GB/T 50500-2024 术语2.0.21

Topic positioning

This card unpacks the valuation rule for each variable in the Annex A.2 adjustment formula of GB/T 50500-2024 (base price C0, risk band r, measurement-period market price Ci, adjustable quantity Q), and gives a directly applicable step-by-step calculation flow with worked increase/decrease example frameworks.

Core conclusions

Formula (Annex A.2.1; the original is a graphic formula, restored here from the variable definitions): dP = sum(dC x Q); on increase (dC > 0), dC = Ci - C0(1+r); on decrease (dC < 0), dC = C0(1-r) - Ci; the adjustment amount bears VAT only, with no overheads or profit (3.3.5-4).

Step 1 Base price C0. Annex A.2.1 original text: 'the base price is the market price 28 days before the tender submission deadline (for non-tendered works, 28 days before the contract signing date); the source of the base price may be the market price used by the employer in setting the tender price ceiling, or the quarterly (monthly) published price information issued by the construction cost administration body, or tender award prices published for comparable projects, in the same period (within the preceding month) and under the same conditions, by the trading centre at the location of the works, provided that each represents the market price level 28 days before the tender submission deadline (for non-tendered works, 28 days before the contract signing date); the tenderer shall state clearly in the tender documents the price source, the issuing body and the specific quarter (month) adopted for the base price (C0).' That date is the contract base date (term 2.0.21: for tendered works, the 28th day before the tender submission deadline; for non-tendered works, 28 days before the contract signing date). Annex G table G.2.1-1 note 1: the base price and the risk band are filled in by the tenderer, and the tenderer fills in the tendered price in the tendered-price column. A contractor with objections shall, within the prescribed time before tendering, request clarification or correction from the employer.

Step 2 Risk band r. The contractual agreement prevails (table G.2.1-1 'risk band' column); clause 8.7.2: 'where the contract stipulates no band or the stipulation is unclear, where the market price movement exceeds 5%, the contract price may be adjusted by one of the methods in Annex A of this standard'. Sign rule, original text: 'r - the risk band coefficient; where dC is over 0, r is positive; where dC is under 0, r is negative'. Only the excess beyond the band is adjusted; within the band the contractor absorbs it. Annex A.2.4 further fixes the base-selection rule for three tendered-price relationships: where the tendered price is below the base price, a rise in the measurement-period published price is judged on the base price, or a fall on the tendered price, whenever the movement exceeds the band value, and adjustment is made on the actuals; where the tendered price is above the base price, a fall is judged on the base price and a rise on the tendered price; where the tendered price equals the base price, both rise and fall are judged on the base price.

Step 3 Measurement-period market price Ci. Original text: 'the measurement-period market price: the current market price may be the market price of the measurement period confirmed by the employer and the contractor, or the quarterly (monthly) published price information issued by the construction cost administration body, or tender award prices published for comparable projects, in the same period (within the preceding month) and under the same conditions, by the trading centre at the location of the works, provided that each represents the current market price level of the measurement period'. Selecting among multiple prices (A.2.3): 'where multiple market prices arise from cost fluctuation within the measurement period, the arithmetic mean of the market prices within the measurement period, or the weighted mean of the market prices and the corresponding executed quantities, or the market price over the main-consumption construction period may be adopted as the current price used in the adjustment formula. The employer and the contractor shall agree which method to adopt, or the order of priority of the methods in different circumstances.' Missing or disputed prices (A.2.2): 'where no measurement-period market price information is available in calculating the adjustment differential, or the dispute between the parties is substantial, the price information published by the construction cost administration body for that measurement period may be used provisionally, with adjustment later in subsequent payments against the actual market price information.' Purchase-price method (A.2.5): before purchasing the materials, the contractor submits the quantities and unit prices to the employer for verification; the employer verifies and confirms within the agreed time and the calculation is made at the prices confirmed by both parties; for batch purchases a weighted average may be taken; 'where the employer fails to reply within the agreed period after receiving the confirmation materials submitted by the contractor, it may be deemed to have approved, and the submission may serve as a basis for adjusting the contract price.'

Step 4 Adjustable quantity Q. Original text: 'the quantity of the adjustable factors, referring to the quantity of the adjustable factors. Where another calculation method is used for the quantity of the adjustable factors, it shall be specified in detail in the tender documents and the special conditions of contract'; final sentence: 'the quantity of the adjustable materials shall be calculated and determined under the quantity calculation rules agreed by the employer and the contractor in the contract'; table G.2.1-1 note 2: 'quantity' is calculated and determined under the quantity calculation method the employer and the contractor specify in the contract.

Step 5 Trigger test. 'Where the market price movement does not exceed the market price movement band borne by the contractor as agreed in the contract, the amounts of the BOQ items occurring in the relevant adjustment period need not be adjusted' (8.7.2) - first compare |Ci - C0| / C0 against r.

Step 6 Worked example framework (with the base price normalised to C0 = 1.00, r = 5%, Q the contract-agreed quantity):

  • Increase: Ci = 1.15, movement 15% over 5%, triggered -> upper edge of the risk band C0(1+r) = 1.05 -> excess unit differential = 1.15 - 1.05 = 0.10 -> pre-tax differential = 0.10Q -> including VAT (VAT rate 13%) = 0.113Q;
  • Decrease: Ci = 0.875, movement 12.5% over 5% -> lower edge of the risk band C0(1-r) = 0.95 -> excess unit differential = 0.95 - 0.875 = 0.075 -> VAT-inclusive clawback = 0.075Q x (1+13%) = 0.08475Q (a negative adjustment of the contract price);
  • Within the band (e.g. Ci = 1.03): no adjustment for the period. The VAT rate is inserted per the contract and the applicable tax law; overheads and profit are never counted.

Step 7 Pricing where the works are delayed (8.7.4): where the employer causes the extension, prices for the works after the planned progress date take the higher of the planned and the actual progress date; where the contractor causes it, the lower; where neither party is responsible, adjustment under 8.7.2, unless the contract or the laws and regulations provide otherwise.

Boundaries of application

Applies only to the labour cost, the main material cost and the fuel and power cost within the plant and small tools cost agreed in the contract as adjustable (3.3.5, Annex G.2); construction consumables, preliminaries, overheads and profit do not adjust for cost fluctuation. C0 and Ci must share the same basis and source (not one from published price information and the other from a market price enquiry), and C0 and r must be set separately per material specification. Where no adjustable scope and band are agreed, the standard provides only the fallback (movement beyond 5% adjustable); lump-sum contracts are in principle not adjusted for cost fluctuation. The worked figures in this card are normalised illustrations and do not represent the prices of any actual project; actual values follow the contract and the tender documents.

Further reading

GB/T 50500-2024: Annex A.2.1 (differential formula and variable definitions), A.2.2 (provisional adjustment differentials), A.2.3 (selecting among multiple prices in a measurement period), A.2.4 (base-selection rules for the three tendered-price / base-price relationships), A.2.5 (verification and confirmation of purchase prices); Annex G table G.2.1-1 (for the published-price-information adjustment method) and table G.2.1-2 (for the index-based adjustment method); clause 3.3.5 (adjustable scope and VAT only); clause 8.7.2 (the 5% fallback and no adjustment within the band); clause 8.7.4 (pricing on extension of time); term 2.0.21 (contract base date).