Price-difference calculation method after material prices exceed the risk band (price-information adjustment method, GB/T 50500-2024 Appendix A.2)
The excess beyond the risk band is adjusted per actuals: when prices rise, unit price difference = Ci - C0 x (1 + r); when prices fall, = C0 x (1 - r) - Ci; adjustment amount = unit price difference x adjusted quantity Q; where the contract does not agree a risk band, fluctuation beyond 5% triggers adjustment (Clause 8.7.2); where the bid price differs from the base price, the cross-basis rule of A.2.4 applies to prevent arbitrage; the price difference carries VAT only, with no management fee or profit.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1~A.2.5
- GB/T 50500-2024 第8.7.1~8.7.4条
- GB/T 50500-2024 第3.3.5条
- GB/T 50500-2024 术语2.0.21
- GB/T 50500-2024 App. G.2
Topic Positioning
This card gives the calculation logic and formulas for the price difference after material market prices fluctuate beyond the agreed risk band under the price-information adjustment method (GB/T 50500-2024 Appendix A.2) — "how to calculate the excess" following "how to set the four elements" (see the referenced card).
Core Conclusions
(1) Trigger determination: adjustment applies only when the actual fluctuation exceeds the contractually agreed risk band r; where not agreed or unclearly agreed, exceeding 5% allows adjustment per Appendix A (Clause 8.7.2). (2) Adjust-actual-difference formulas (corresponding to A.2.1, dP = sum of dC x Q): when prices rise, unit price difference = Ci - C0 x (1 + r); when prices fall, unit price difference = C0 x (1 - r) - Ci; in between, no adjustment; adjustment amount = unit price difference x adjusted quantity Q. C0 is the base price (the market price 28 days before the bid submission deadline for tendered works, or 28 days before contract signing for non-tendered works, with the source specified in the tender documents); Ci is the market price of the measurement period. (3) Where the bid price differs from the base price, the cross-basis rule of A.2.4 applies: if the bid price is lower than the base price, a rising overrun is computed on the base price and a falling overrun on the bid price; if the bid price is higher, the opposite — preventing the arbitrage of bidding low to bet on rises or bidding high to bet on falls. (4) Where a measurement period has multiple prices, the arithmetic mean, the weighted mean with completed quantities, or the price of the main-consumption construction period may be used (A.2.3); the method and its priority order should be agreed in the contract. (5) The price difference carries VAT only, with no management fee or profit (Clause 3.3.5, item 4).
Applicable Boundaries
Applies only to the price-information adjustment method (corresponding to Table G.2.1-1); the price-index adjustment method follows Appendix A.1 and Table G.2.1-2. Premises: the contract has specified the adjustable material scope as an attached table, and quantities are determined per the contractual calculation rules. Where the contract provides otherwise, its provisions prevail; where data are missing or disputes are significant, the difference may be provisionally determined per the published price information and later settled per actuals (A.2.2).
Further Reading
See GB/T 50500-2024 Code for BOQ pricing of construction works, Appendix A.2.1-A.2.5, Clauses 8.7.1-8.7.4, Clause 3.3.5, term 2.0.21 "contract base date", and Appendix G.2 Table G.2.1-1.
Keywords
Related Cards
- →
Overview of material price adjustment in construction works: applicable conditions, base price (reference price for adjustment), risk band, and calculation methods (GB/T 50500-2024 Sections 3.3/8.7 and Appendices A, G)
Four indispensable elements of material price adjustment: ① adjustable scope (only labour cost, principal material cost, and construction machinery fuel and power cost, listed per Appendix G.2 Tables G.2.1-1/2 as a contract annex); ② base price (reference price for adjustment) C₀ (the market price level 28 days before the tender deadline (= FIDIC Base Date), or for non-tendered works 28 days before contract signing); ③ risk band r (contractual agreement takes precedence, in practice 3%–5%; where absent or unclear, a cost fluctuation beyond 5% triggers); ④ quantities subject to price adjustment Q (per the contract's agreed rules). Trigger |Ci−C₀|/C₀>r; upward unit price for the excess beyond the band = Ci−C₀(1+r), downward = C₀(1−r)−Ci; price difference = Σ unit price for the excess beyond the band × Q, carrying value added tax (VAT) only, with no management fee or profit.
- →
Steel price adjustment calculation: price-information adjustment formula, per-specification per-period threshold checks with adjustment on actual basis, and tax treatment (GB/T 50500-2024 Appendix A.2)
Steel price adjustment uses the price-information adjustment method (GB/T 50500-2024 Appendix A.2): △P = Σ[(Ci − C0·(1±r)) × Q] × (1 + VAT rate), adjusting only the portion beyond the risk band on an actual basis; the agreed risk band prevails, with the beyond-5% fallback where not agreed or unclear (8.7.2). Each specification must be checked independently each period for exceeding the risk band (base prices, published price information, and increase rates differ; specifications within the risk band are not adjusted for the period); the price difference carries VAT only, no management fee or profit (3.3.5); when checking adjustment tables, first look at whether the bid price is above or below the base price (A.2.4 determines the excess-calculation base).
- →
Order of applicable bases for material price adjustment: contract agreement prevails, pricing standard as fallback (GB/T 50500-2024 "agreement governs" and the 5% band rule)
Material price adjustment follows the contract agreement first (agreement governs, clause 1.0.3): adjustable material scope, base price, risk band, quantity calculation, price-information source and adjustment period all follow the contract, completing appendix G table G.2.1 as a contract annex; where the contract fixes no band or unclearly, fluctuation beyond 5% may be adjusted per appendix A (clause 8.7.2 fallback); the contract may neither violate mandatory laws and regulations nor depart from the substantive content of the tender documents (law prevails; clause 3.4.4); the price difference carries VAT only, no management fee or profit.
- →
Determining the pricing risk scope within the all-in unit rate: contract agreement first + statutory fallback of GB/T 50500-2024 Sections 3.3/8.7
Risk-scope determination follows 'contract agreement first, statutory fallback second': the employer and contractor must specify the content, scope and risk band (no-adjustment tolerance, e.g. ±5%) of measurement and pricing risks in the tender documents/contract, and clauses providing for uncapped risk allocation to one party and 'all risks' are prohibited; where not agreed or unclear, the risks are statically divided per GB/T 50500-2024 Clauses 3.3.2/3.3.3 (employer: BOQ errors / omissions, errors in raw data, approved changes, acceleration/stoppage, changes in laws and policies, cost fluctuations beyond the risk band; contractor: accuracy of the bill of preliminaries, BOQ errors / omissions in lump-sum contracts, own scheme/machinery/management, cost fluctuations within the risk band), with Section 8.7 as the dynamic quantitative fallback (where no risk band is agreed, the portion exceeding 5% is adjusted per Appendix A; the price difference carries value added tax (VAT) only, with no management fee or profit).
- →
The mechanism for determining the scope of price-adjustable materials and typical categories (GB/T 50500-2024 appendix G.2)
GB/T 50500-2024 sets no statutory "list of price-adjustable materials": the employer and contractor define the scope of adjustable main materials and lock it in as a contract annex by completing table G.2.1-1 (price-information adjustment method) or G.2.1-2 (price-index adjustment method) of appendix G.2; the statutory adjustable factors are only three classes — labor cost, main material cost, and fuel/power cost of construction plant; price differences carry VAT only, with no management fee or profit.
Cited By
- ←
Valuation rules for the four variables of material price adjustment (adjustment based on published price information) and the step-by-step calculation flow: base price C0, risk band r, measurement-period market price Ci and adjustable quantity Q (GB/T 50500-2024 Annex A.2)
The published-price-information method takes its values in five steps. (1) C0 = the market price level 28 days before the tender submission deadline (for non-tendered works, 28 days before the contract signing date), one source chosen from three (the market price used in setting the tender price ceiling / the quarterly (monthly) published price information of the cost administration body / award prices of comparable projects published for the same period by the trading centre); the tender documents must state the source, the issuing body and the specific quarter (month). (2) r: the contractual agreement prevails; where none exists or it is unclear, adjustment is allowed once the movement exceeds 5% (clause 8.7.2), the sign of r following the sign of dC (positive on increase, negative on decrease). (3) Ci takes the current price of the measurement period; with multiple prices, use the arithmetic mean / the weighted mean against executed quantities / the price over the main-consumption construction period; where a price is missing or disputed, published price information may be used provisionally and trued up later; purchase prices must be submitted to the employer for verification before purchase, silence within the time limit being deemed approval. (4) Q is calculated under the contractual quantity calculation rules. (5) Adjustment only where |Ci - C0| / C0 > r; on increase the excess unit differential = Ci - C0(1+r), on decrease = C0(1-r) - Ci; multiplied by Q it bears VAT only, with no overheads or profit.
- ←
Rules for handling contract price adjustment for cost fluctuation in final account review and construction cost expert assessment: routing by contract type, price-dating principles for delay periods, the exception for government-priced materials, and the eight categories of costs not adjusted for changes in costs listed in GB/T 50500-2024 clause 8.7.6
Final account review and expert assessment proceed on two levels. (i) Routing by contract type: for lump-sum contracts, unless otherwise agreed, cost fluctuation is generally not adjusted, and a contractor claiming adjustment for change of circumstances or prolonged duration must proceed by claim; for unit-rate contracts the agreement prevails, and absent or unclear agreement the matter is resolved by reference to national, local or sector provisions, with labour, materials and plant outside the contractually adjustable scope not adjustable. Price-dating during delay: where the delay is not attributable to the contractor, the higher of the prices at the planned and actual progress dates applies; where attributable to the contractor, the lower applies; concurrent delay is shared by sequence and responsibility. (ii) Hard constraint on the scope of adjustment: GB/T 50500-2024 clause 8.7.6 lists eight categories of costs not adjusted for changes in costs (construction consumables, small and medium tools, preliminaries, plant and small tools costs other than fuel and power, material costs of items outside the agreed adjustable list, changes beyond the agreed scope or band, overheads and profit, and costs arising from the contractor's own causes); where the contract sets no band or sets it unclearly, fluctuation beyond 5% may be adjusted per Annex A (8.7.2), and abnormal movements of other materials outside the agreed adjustable scope may be handled by equitable risk allocation, by negotiation or by adjustment to actual costs (8.7.3, 3.3.6).
- ←
Choosing among the three bases of material price adjustment (bid price / base-period published information / jointly confirmed price): statutory sources, defaults, difference-rate versus risk-band linkage and item-by-item locking (GB/T 50500-2024 term 2.0.21, Appendix A.2, G.2.1)
Per GB/T 50500-2024 Appendix A.2.1, the base price C0 is 'the market price level at the base date (28 days before the tender deadline; non-tendered, 28 days before contract signature)' with only three statutory sources: the market prices used for the tender price ceiling, the cost authority's current-quarter (month) published information, and award prices of like works from the trading centre of the same period and conditions - the tenderer must state the source, publisher and specific quarter (month). The bid price is thus not a statutory C0 source (Table G.2.1-1: base price and risk band by the tenderer, bid price by the bidder), and the confirmed price corresponds in A.2.1 to a source of the current period price Ci - both rise to C0 only by express contract. Difference rate = (Ci - C0) / C0 x 100%; against the risk band r only the excess adjusts: rising, unit difference = Ci - C0 x (1 + r); falling, = C0 x (1 - r) - Ci; the amount x Q carries VAT only, never overheads or profit (3.3.5); absent an agreed band, swings beyond 5% adjust (8.7.2).
- ←
The step chain of adjusting on published price information: fix the adjustable list -> lock base price C0 -> take period prices Ci -> difference x adjustable quantity Q -> adjust the excess over the risk band -> book into progress and settlement, with fallbacks for missing periods and items and the Q test (GB/T 50500-2024 Appendix A.2; against superseded GB 50500-2013 Appendix A.2)
Six steps: (1) fix the adjustable material / labour list (2024: 3.3.5 item 2 + Appendix G Tables G.2.1-1/-2; 2013: 9.8.2 agreed scope, else over 5% adjusts the excess) -> (2) lock C0 = the market price 28 days before the tender deadline (non-tendered: signature), source, publisher and quarter (month) stated (A.2.1; 2013 A.2.3) -> (3) take Ci per measurement period; several prices within a period take the arithmetic mean, the quantity-weighted mean or the main-consumption-period price (A.2.1, A.2.3) -> (4) difference x Q (2024 A.2.1 formula; 2013 has only the 'excess on actuals' principle, no explicit formula) -> (5) adjust only beyond the agreed band r (rising Ci - C0(1+r), falling C0(1-r) - Ci; absent a band, over 5% - 8.7.2 / 2013 9.8.2) -> (6) book into cumulative progress and pay with progress and interim settlements (9.4.6, 8.1.6). Missing periods fall back in order: contract rule -> same-period alternative source -> in-period averaging -> provisional posting on current information with later truing (A.2.2) -> employer-recognised purchase price (A.2.5; 2013 A.2.3 item 4: 3 working days' silence deems approval; unreported self-purchase refused by the employer never adjusts) -> market enquiry by three parties; 'carry the last period forward' has no national-text basis outside the index method (2013 A.1.2). Q follows the contractual quantity rule; the default is the consumption of measured completed work - never signed list quantities or purchase / invoice totals; differences carry VAT only (3.3.5 item 4).
- ←
Direction-specific base rules in the price adjustment method based on published price information when the contractor's tender price deviates from the base price (GB/T 50500-2024 Annex A.2.4, corresponding to Section 9.7 of the superseded GB 50500-2013): rises judge on the higher of the two prices, falls on the lower, a two-way disadvantage that blocks arbitrage, with the selection boundary against the Annex A.1 index method
Under GB/T 50500-2024 Annex A.2.4, the published-price-information adjustment applies a direction-specific base: the base for upward adjustment (price rise) is the higher of the base price C0 and the tender price P, and the base for downward adjustment (price fall) is the lower of the two. Hence when the contractor's price is below the base price (P < C0), rises are judged on the base price C0 and falls on the tender price P; when the price is above the base price (P > C0) the reverse applies; when the price equals the base price, both directions are judged on C0. Only the portion crossing the risk band threshold is adjusted as actually incurred; below the threshold nothing is adjusted; and the price differential carries VAT only, with no overheads or profit (3.3.5).
- ←
Selecting between the two methods of contract price adjustment for changes in costs: comparison of applicable conditions, clause-by-clause contrast and same-contract mixing boundaries of the Appendix A.1 index-based adjustment and the Appendix A.2 adjustment based on published price information under GB/T 50500-2024
The two methods share an identical adjustable scope, base time point and trigger threshold (only labour cost, key material cost and the fuel and power cost of construction plant are adjustable; the base time point is 28 days before the tender deadline; where the contract sets no band or sets it unclearly, fluctuations beyond 5% are adjustable; the differential carries VAT only, never overheads or profit). The difference lies only in the price variable. A.1, index-based (formula) adjustment, takes the VAT-exclusive contract price P0 as the base and weights the fixed weight A and the variable weights B1...Bn of each adjustable factor by the ratio 'current index / base index' - the index source is agreed in the contract, the agreed fluctuation band is folded into the base price index, and where an index is missing the previous measurement period's index may be used provisionally. A.2, adjustment based on published price information, takes the adjustable factor quantity Q as the base and computes the money price differential between the base price C0 and the measurement-period market price Ci less the risk band coefficient r; the base price and the market price are each chosen from three sources (market price used in setting the tender price ceiling / published price information of the cost management agency / tender-winning prices published by the trading centre), whether the band is exceeded is determined by scenarios of the tender price against the base price, and under the purchase-price route the contractor must submit quantity and unit price to the employer for checking before purchase (no reply in time is deemed approval). The standard itself has no dedicated 'applicable conditions' clause, only 'one of the methods of Appendix A'; the choice is first a matter for the contract; where one contract assigns different methods to different adjustable factors, they must be entered separately in Table G.2.1-1 (published price information method) / Table G.2.1-2 (index method), without double counting the same differential.
- ←
Can published price information directly serve as the basis for material price adjustment: legality + three preconditions (listing / beyond band / tax) (GB/T 50500-2024)
Published price information (government guidance prices) is a price source expressly recognized for price adjustment (for fluctuation) (Appendix A.2.1: both the base price C0 and the measurement-period price Ci may adopt the current published price information issued by the cost management agency; A.2.4: where published price information serves as both base price and current price, adjust within the agreed risk band), but adjustment is not unconditional and full-scope: (1) the material must be listed in the contract annex "schedule of price-adjustable key materials" (Table G.2.1-1; not listed, not adjusted); (2) only the portion beyond the contract-agreed risk band is adjusted to actual, the band being contractor-borne; (3) where the contract sets no band, fluctuation beyond 5% is the fallback trigger (8.7.2). The price difference carries value added tax (VAT) only, not management fee or profit (3.3.5).
- ←
Appendix A price adjustment (for fluctuation) methods for changes in costs, GB 50500-2013 vs GB/T 50500-2024: weighting coefficient basis and adjustment threshold differences
The two editions share the same formula skeleton in Appendix A (index-based (formula) adjustment dP = P0[A + sum BiFit/Fi0 - 1]; adjustment based on published price information adjusts the portion beyond the risk band (no-adjustment tolerance, e.g. ±5%) at actual values); differences lie in the basis and mechanisms: (1) weighting — 2013 variable weights are 'proportions of the total tender price in the tender letter' (including VAT), 2024 uses 'weights of the contract price excluding VAT' (separation of net price and VAT), and 2024 adds A.1.4 fallback 'where variable weights are not agreed, the corresponding weights of the tender price ceiling may be used' and A.1.1 merges the fluctuation range into the base price index F0; (2) thresholds — both editions' fallback is 5% (beyond which actual-value adjustment applies; 2013 clause 9.8.2, 2024 clause 8.7.2), and 2024 adds the sign rule for the r risk band coefficient, defines the base price (reference price for adjustment) as the market price 28 days before the tender deadline (= FIDIC Base Date) (28 days before contract signing for non-tendered works), and the 8.7.6 list of items not subject to price adjustment. GB 50500-2013 was mandatory (replaced); 2024 is recommended national standard GB/T.
- ←
Which period's published price applies to settlement material prices: the two-date system — base price locked at the contract base date (28 days before bid closing) plus period-by-period pricing per measurement cycle (GB/T 50500-2024 Annex A.2 price-information method)
Settlement material prices are not taken from a single period (completion date or submission date) but from the "base price locked at the contract base date + current prices per measurement cycle" two-date system: base C0 at 28 days before bid closing (non-tendered: 28 days before contract signing); current Ci per measurement cycle from the cost authority's published price information (or jointly confirmed market prices, or same-period trading-center award prices); differences beyond the contractual risk band are computed per cycle and totalled into the final account; with no band agreed, a 5% fluctuation triggers adjustment; express contracts govern.
- ←
Cement price adjustment calculation: determining the adjustment object by usage path (site-mixed / ready-mixed concrete / direct purchase) + price-information adjustment method formulas and caliber points (GB/T 50500-2024 Appendix A.2)
Cement adjustment first fixes the object by usage path: site-mixed concrete/mortar and direct purchase adjust cement (CNY/t, quantity per mix-ratio cement usage or the employer-confirmed purchase quantity), ready-mixed concrete adjusts concrete (CNY/m3) with cement not separately adjusted (the published price information already includes raw-material costs, preventing double-counting). Formulas (Appendix A.2): rising overrun unit price difference = Ci − C0×(1+r), falling = C0×(1−r) − Ci, amount = unit price difference × Q; absent an agreed risk band, fluctuation beyond 5% triggers (8.7.2); the price difference carries VAT only, without management fee or profit (3.3.5); bagged/bulk calibers consistent, listed by type and strength grade, rising and falling adjusted symmetrically in both directions.
- ←
GB/T 50500-2024 rules for determining the base date: agreement first; tendered works = 28 days before the tender deadline, non-tendered works = 28 days before contract signing (term 2.0.21)
The base date (GB/T 50500-2024 term 2.0.21) is the date on which the contractor, during the tender period, determined the tender total price, the BOQ all-in unit rates and their sums, and it serves as the price datum for adjustment for changes in costs and for adjustment arising from changes in laws, regulations and policies. Determination order: agreement first, statutory fallback — where the tender documents (inquiry documents for non-tendered works) and the contract are silent, tendered works take 28 days before the tender deadline (= FIDIC Base Date) and non-tendered works 28 days before contract signing. That point is at once the base period of index-based (formula) adjustment (A.1.6), the base price C₀ of adjustment based on published price information (A.2.1), and the common starting point for adjustment for changes in laws, regulations and policies (8.8.1).
- ←
GB/T 50500-2024, China's BOQ pricing standard: positioning, 2024-vs-2013 changes, chapter map and card-group navigation
GB/T 50500-2024, the China national pricing standard for BOQ-based pricing (MOHURD Announcement No. 212 of 2024, approved 26 November 2024), came into force on 1 September 2025 and repealed GB 50500-2013. Its status shifted from a partly mandatory code to a recommended national standard (GB to GB/T), aiming to regularise pricing rules and let the market form construction costs. It governs pricing activity in tendering, contracting and execution for construction works; EPC and other general-contracting models apply it by reference, and the requirement that state-funded projects use BOQ pricing is carried by a MOHURD ministerial order. Nine headline revisions (per the foreword): risk scope and allocation rules by contract form; a new bid clarification mechanism; revised pricing of preliminaries; the 'contract price agreement' chapter replaced by contract selection and requirements; revised measurement and adjustment rules; site visas abolished and additional-works pricing introduced; interim settlement by construction stage added; dispute resolution revised; the cost-expert-assessment chapter deleted. The structure was rebuilt from 16 chapters into 12 chapters plus annexes: 'tender control price' renamed tender price ceiling; completion settlement and contract-termination settlement merged into 'works settlement and payment' (absorbing stage settlement); dispute resolution and expert assessment merged; pricing tables moved to annexes (with a new Annex G, schedule of price-adjustable key materials).
- ←
Overview of the full-chain use rules for construction cost published price information: nature, price calibers, stage-by-stage pricing, and frequent misconceptions
Published price information means reference guide prices issued by cost management agencies, running through the whole chain "price-limit compilation - bid verification - adjustment base - settlement fallback". Five iron rules: contract agreement first; caliber unification (tax-inclusive/exclusive, delivered/ex-factory, procurement-keeping fee); period alignment (base price locked 28 days before the bid deadline, measurement price matched to the measurement period); adjust only beyond band (±5% if not agreed); confirmation with records (submit to the employer before purchase, silence deemed acceptance).