Price-difference calculation method after material prices exceed the risk band (price-information adjustment method, GB/T 50500-2024 Appendix A.2)

The excess beyond the risk band is adjusted per actuals: when prices rise, unit price difference = Ci - C0 x (1 + r); when prices fall, = C0 x (1 - r) - Ci; adjustment amount = unit price difference x adjusted quantity Q; where the contract does not agree a risk band, fluctuation beyond 5% triggers adjustment (Clause 8.7.2); where the bid price differs from the base price, the cross-basis rule of A.2.4 applies to prevent arbitrage; the price difference carries VAT only, with no management fee or profit.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1~A.2.5
  • GB/T 50500-2024 第8.7.1~8.7.4条
  • GB/T 50500-2024 第3.3.5条
  • GB/T 50500-2024 术语2.0.21
  • GB/T 50500-2024 App. G.2

Topic Positioning

This card gives the calculation logic and formulas for the price difference after material market prices fluctuate beyond the agreed risk band under the price-information adjustment method (GB/T 50500-2024 Appendix A.2) — "how to calculate the excess" following "how to set the four elements" (see the referenced card).

Core Conclusions

(1) Trigger determination: adjustment applies only when the actual fluctuation exceeds the contractually agreed risk band r; where not agreed or unclearly agreed, exceeding 5% allows adjustment per Appendix A (Clause 8.7.2). (2) Adjust-actual-difference formulas (corresponding to A.2.1, dP = sum of dC x Q): when prices rise, unit price difference = Ci - C0 x (1 + r); when prices fall, unit price difference = C0 x (1 - r) - Ci; in between, no adjustment; adjustment amount = unit price difference x adjusted quantity Q. C0 is the base price (the market price 28 days before the bid submission deadline for tendered works, or 28 days before contract signing for non-tendered works, with the source specified in the tender documents); Ci is the market price of the measurement period. (3) Where the bid price differs from the base price, the cross-basis rule of A.2.4 applies: if the bid price is lower than the base price, a rising overrun is computed on the base price and a falling overrun on the bid price; if the bid price is higher, the opposite — preventing the arbitrage of bidding low to bet on rises or bidding high to bet on falls. (4) Where a measurement period has multiple prices, the arithmetic mean, the weighted mean with completed quantities, or the price of the main-consumption construction period may be used (A.2.3); the method and its priority order should be agreed in the contract. (5) The price difference carries VAT only, with no management fee or profit (Clause 3.3.5, item 4).

Applicable Boundaries

Applies only to the price-information adjustment method (corresponding to Table G.2.1-1); the price-index adjustment method follows Appendix A.1 and Table G.2.1-2. Premises: the contract has specified the adjustable material scope as an attached table, and quantities are determined per the contractual calculation rules. Where the contract provides otherwise, its provisions prevail; where data are missing or disputes are significant, the difference may be provisionally determined per the published price information and later settled per actuals (A.2.2).

Further Reading

See GB/T 50500-2024 Code for BOQ pricing of construction works, Appendix A.2.1-A.2.5, Clauses 8.7.1-8.7.4, Clause 3.3.5, term 2.0.21 "contract base date", and Appendix G.2 Table G.2.1-1.