base date
- 01
Choosing among the three bases of material price adjustment (bid price / base-period published information / jointly confirmed price): statutory sources, defaults, difference-rate versus risk-band linkage and item-by-item locking (GB/T 50500-2024 term 2.0.21, Appendix A.2, G.2.1)
Per GB/T 50500-2024 Appendix A.2.1, the base price C0 is 'the market pri…
GB/T 50500-2024 术语第2.0.21条(合同基准日)GB/T 50500-2024 App. A.2.1(基准价三来源与价差公式)GB/T 50500-2024 App. A.2.2(暂按信息价计算后按实调整)2026-10-25 - 02
The direction of price adjustment for legal and policy changes during delay (extension) periods: contractor-caused delay takes no rises but all falls; employer-caused the reverse; neither-party delay adjusts on actuals (GB/T 50500-2024 clauses 8.8.1~8.8.4)
Direction follows fault: for contractor-caused extension, policy changes…
GB/T 50500-2024 第8.8.1、8.8.2、8.8.3、8.8.4条,第8.7节,App. A.2.1GB 50500-2013 第3.4.2、9.2.1、9.2.2条(已被GB/T 50500-2024替代)GF-2017-0201《建设工程施工合同(示范文本)》第11.2款2026-10-25 - 03
The index-based adjustment method (GB/T 50500-2024 Appendix A.1): the adjustment formula, fixing the fixed weight A and variable weights Bi, and the sources and timing of price indices (factors)
The index method computes dP = P0 x [A + sum Bi x (Fti/F0i) - 1]: P0 the…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works App. A.1.1~A.1.6GB/T 50500-2024 第3.3.5条GB/T 50500-2024 第8.7.1~8.7.6条2026-10-18 - 04
GB/T 50500-2024 clause set 8.8: adjustments of contract price and duration for changes in laws, regulations and policies - scope, the one-way adjustment rule during extended durations, and no adjustment of overheads and profit
GB/T 50500-2024 clause 8.8: for laws, regulations, policy provisions or…
GB/T 50500-2024 建设工程工程量清单计价标准 第8.8.1条GB/T 50500-2024 第8.8.2条GB/T 50500-2024 第8.8.3条2026-10-18 - 05
Rules for determining the material adjustment base price (C0): base date, one-of-three sources and the adjustment computation base (GB/T 50500-2024)
The base price C0 = the market price level 28 days before the bid closin…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1GB/T 50500-2024 术语2.0.21GB/T 50500-2024 App. A.2.42026-09-25 - 06
Price-difference calculation method after material prices exceed the risk band (price-information adjustment method, GB/T 50500-2024 Appendix A.2)
The excess beyond the risk band is adjusted per actuals: when prices ris…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1~A.2.5GB/T 50500-2024 第8.7.1~8.7.4条GB/T 50500-2024 第3.3.5条2026-09-25 - 07
Which period's published price applies to settlement material prices: the two-date system — base price locked at the contract base date (28 days before bid closing) plus period-by-period pricing per measurement cycle (GB/T 50500-2024 Annex A.2 price-information method)
Settlement material prices are not taken from a single period (completio…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.21条、第3.3.5条、第8.7.1~8.7.4条、第10.2.3条、第10.2.7条、第10.3.2条、App. A.2.1~A.2.4、App. G.2T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第3.1.7条2026-09-25 - 08
GB/T 50500-2024 rules for determining the base date: agreement first; tendered works = 28 days before the tender deadline, non-tendered works = 28 days before contract signing (term 2.0.21)
The base date (GB/T 50500-2024 term 2.0.21) is the date on which the con…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.21条、第8.7.1条、第8.8.1条GB/T 50500-2024 App. A.1.6、A.2.1、A.2.42026-09-25