The direction of price adjustment for legal and policy changes during delay (extension) periods: contractor-caused delay takes no rises but all falls; employer-caused the reverse; neither-party delay adjusts on actuals (GB/T 50500-2024 clauses 8.8.1~8.8.4)
Direction follows fault: for contractor-caused extension, policy changes in the extension window bring no upward adjustment and all downward adjustments; for employer-caused extension, no downward and all upward; neither-party extension adjusts on actuals (save contract or other provision). Events are limited to legal and policy changes after the contract base date (enactment / amendment / repeal / changed government interpretation). Basis: GB/T 50500-2024 clauses 8.8.1~8.8.4; the model contract parallels GF-2017-0201 clause 11.2.
Applicable Codes
- GB/T 50500-2024 第8.8.1、8.8.2、8.8.3、8.8.4条,第8.7节,App. A.2.1
- GB 50500-2013 第3.4.2、9.2.1、9.2.2条(已被GB/T 50500-2024替代)
- GF-2017-0201《建设工程施工合同(示范文本)》第11.2款
- GB/T 51262-2017 第5.7.6条
Positioning
When extension (delay) periods meet legal and policy change - which way does the price go, who bears it. The base-date line, the trigger scope, the four direction rules by fault, the link to price-move rules, and the 2013 / model-contract parallels.
Core conclusions
1. Time line - the contract base date: GB 50500-2013 clause 9.2.1 - tendered: 28 days before the tender deadline; non-tendered: 28 days before signature; later cost changes from laws, regulations, rules and policies adjust per the provincial / sectoral or authorised cost authority's published rules. GB/T 50500-2024 keeps the term; the base price C0 likewise sits 28 days before the deadline / signature (A.2.1). Rules published or effective before the base date never trigger this clause set.
2. Trigger scope (8.8.1 verbatim): 'During performance, the following legal and policy changes after the base date causing price change and / or delay adjust per the contract and the rules of national, provincial or sectoral authorities: 1 enactments; 2 amendments; 3 repeals; 4 changed government interpretations.'
3. Direction by fault (8.8.2~8.8.4)
- Contractor-caused extension (8.8.2): 'upward adjustments are not made; downward adjustments are.' - gains to the employer, losses to the contractor.
- Employer-caused extension (8.8.3): 'downward adjustments are not made; upward adjustments are.' - gains to the contractor, losses to the employer.
- Neither-party extension (8.8.4): 'adjusts on actuals, save contract or legal provision.'
4. Link to price moves (shared closing of 8.8.1~8.8.4): 'Where legal and policy change causes material extension and the works after the planned progress date meet market price changes and abnormal fluctuation, the parties adjust the affected prices under the price-move rules.' Two steps: fix the policy change itself under 8.8 (price and extension); the resulting material extension then runs 8.7 (the 5% band, 8.7.3 negotiation, 8.7.4 delay-period pricing).
5. Model contract (GF-2017-0201 clause 11.2): 'After the base date, legal changes raising costs beyond clause 11.1 are borne by the employer; reductions deduct from the price. Legal changes delaying the works extend the duration. Failing agreement, the engineer determines per clause 4.4. Contractor-caused delay meeting legal change - the added cost and / or delay are the contractor's.' The model text follows 'the defaulter bears the adverse' - aligned with 8.8.2 but without 8.8.3's mirror rule.
Applicable boundaries
- Events must be legal and policy changes; pure supply-and-demand swings run 8.7.
- Direction presupposes fault: fix actual versus contract duration, then attribute (GB/T 51262-2017 clause 5.7.6); concurrent delays share by fault.
- Contract and superior provisions prevail (8.8.4's proviso); adjustments also follow the authorities' published rules.
- Legacy: GB 50500-2013 clause 9.2.2 covered contractor-caused delay only one way ('after the original completion date, increases not adjusted, decreases adjusted'); clause 3.4.2 put legal change, published labour adjustments (save bids above), and government-priced materials on the employer, bidders carrying no such risk. 2024 splits the cases three ways.
Further reading
GB/T 50500-2024 clauses 8.8.1~8.8.4, clause set 8.7, clause set 8.11, A.2.1; GB 50500-2013 clauses 3.4.2, 9.2.1, 9.2.2 (superseded); GF-2017-0201 clauses 11.2 and 4.4; GB/T 51262-2017 clause 5.7.6.
Keywords
- 法律法规及政策性变化
- 法律变化引起的调整
- 工期延误 调增不调
- base date
- GB/T 50500-2024 8.8.1
- GF-2017-0201 11.2