Determining the pricing risk scope within the all-in unit rate: contract agreement first + statutory fallback of GB/T 50500-2024 Sections 3.3/8.7
Risk-scope determination follows 'contract agreement first, statutory fallback second': the employer and contractor must specify the content, scope and risk band (no-adjustment tolerance, e.g. ±5%) of measurement and pricing risks in the tender documents/contract, and clauses providing for uncapped risk allocation to one party and 'all risks' are prohibited; where not agreed or unclear, the risks are statically divided per GB/T 50500-2024 Clauses 3.3.2/3.3.3 (employer: BOQ errors / omissions, errors in raw data, approved changes, acceleration/stoppage, changes in laws and policies, cost fluctuations beyond the risk band; contractor: accuracy of the bill of preliminaries, BOQ errors / omissions in lump-sum contracts, own scheme/machinery/management, cost fluctuations within the risk band), with Section 8.7 as the dynamic quantitative fallback (where no risk band is agreed, the portion exceeding 5% is adjusted per Appendix A; the price difference carries value added tax (VAT) only, with no management fee or profit).
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第3.3.1~3.3.6条
- GB/T 50500-2024 第8.7节
- GB/T 50500-2024 App. A
- GB/T 50500-2024 App. G Table G.2.1-1/-2
Topic Positioning
This card covers how the pricing risk scope within the all-in unit rate is determined: static responsibility division under the equitable risk allocation principle and the quantitative fallback for cost fluctuations, applicable to tender (priced offer), contract review and settlement disputes.
Core Conclusions
General principle (Clause 3.3.1): the risk content, scope or risk band must be specified in the tender documents/contract; clauses providing for uncapped risk allocation to one party and 'all risks' are prohibited. Static division — borne by the employer (Clause 3.3.2): BOQ errors / omissions in the employer-provided BOQ under re-measurable (unit-rate) contracts (except the bill of preliminaries), errors in raw data, approved changes, acceleration/stoppage, changes in laws and policies, cost fluctuations beyond the risk band; borne by the contractor (Clause 3.3.3): accuracy and completeness of the bill of preliminaries, BOQ errors / omissions in lump-sum contracts, all costs of completing the billed (BOQ) items, own scheme/machinery/management-level causes, cost fluctuations within the risk band. Dynamic rules — where agreed, the agreement governs (Clause 3.3.5; adjustable materials may use Appendix G Tables G.2.1-1/-2 as contract annexes); where no risk band is agreed, the portion of cost fluctuation exceeding 5% is adjusted per Appendix A (Clause 8.7.2), the base price (reference price for adjustment) being the published price information (government guidance prices) current 28 days before the tender deadline (= FIDIC Base Date) (A.2.4); unforeseeable abnormal fluctuations are shared by negotiation. Cost embodiment — the risk cost enters the all-in unit rate; the price difference carries value added tax (VAT) only, with no management fee or profit (Clause 8.7.6).
Applicable Boundaries
Applies to construction employer-contractor relations under the GB/T 50500-2024 BOQ-based pricing system; where the contract has agreements, they govern, the standard serving as the fallback; not applicable to engineering, procurement and construction (EPC/Turnkey) pricing.
Further Reading
See GB/T 50500-2024 Clauses 3.3.1-3.3.6, Section 8.7, Appendix A, and Appendix G Tables G.2.1-1/-2; extensions: the 'four elements of material price adjustment' and 'validity boundary of uncapped risk allocation clauses' cards.
Keywords
Related Cards
- →
Quantity-price risk boundaries compared across lump-sum, unit-rate (re-measurable) and cost-plus contracts
The three contract types form a gradient of quantity and price risk transferred from contractor to employer: lump sum = both quantity and price fixed (the contractor bears quantity variances and cost fluctuations within the agreed range, except variations, changes in laws and regulations, and force majeure); unit-rate (re-measurable) = unit rate fixed, quantities measured as executed (BOQ errors / omissions and quantity variances lie with the employer); cost-plus = costs reimbursed as actually incurred (nearly all quantity and price risk lies with the employer). Basis: MOC Decree No. 107, Article 12; GB/T 50500-2024, Clauses 3.3.1-3.3.8; GB/T 50875-2013, Clauses 3.3.6-3.3.8.
- →
Steel price adjustment calculation: price-information adjustment formula, per-specification per-period threshold checks with adjustment on actual basis, and tax treatment (GB/T 50500-2024 Appendix A.2)
Steel price adjustment uses the price-information adjustment method (GB/T 50500-2024 Appendix A.2): △P = Σ[(Ci − C0·(1±r)) × Q] × (1 + VAT rate), adjusting only the portion beyond the risk band on an actual basis; the agreed risk band prevails, with the beyond-5% fallback where not agreed or unclear (8.7.2). Each specification must be checked independently each period for exceeding the risk band (base prices, published price information, and increase rates differ; specifications within the risk band are not adjusted for the period); the price difference carries VAT only, no management fee or profit (3.3.5); when checking adjustment tables, first look at whether the bid price is above or below the base price (A.2.4 determines the excess-calculation base).
- →
Unbalanced bidding: definition, common tactics, risks for both employer and contractor, and response paths
Unbalanced bidding is a tender-pricing method that adjusts the unit prices of BOQ items after the total tender price is fixed in order to maximize returns ('total unchanged, unit prices mismatched'); it is lawful in itself. Common tactics: front-loading, quantity gaming, and high pricing of provisional items. The employer bears cash-flow occupation, settlement overruns and audit exposure; the contractor bears blowback from quantity misforecasting, locked-in all-in unit rates and compliance risks. The normative hedge: clear evaluation criteria in the tender documents plus organized adjustment at the bid-clarification stage (without changing the total price, confirmed by both parties).
- →
Contractor's objection period and tiered remedies against final account review results (GB/T 50500-2024)
After receiving the settlement verification/review result, the contractor must raise itemized written objections within the agreed objection period (28 days absent agreement), failing which the result is deemed accepted (GB/T 50500-2024 Clauses 10.3.8, 10.3.10); if dissatisfied, escalate through the ladder: recheck → incomplete settlement first for undisputed parts → negotiation/professional conferencing → dispute review/mediation → administrative mediation (within one month) → arbitration/litigation, while continuing performance during the dispute.
- →
Definition and cost composition of the all-in unit rate (GB/T 50500-2024 Clause 2.0.9, GB/T 50875-2013 Clause 2.2.58)
All-in unit rate = labour cost + material cost (including engineering equipment) + plant and small tools cost + overheads (company and site) + profit + risk cost within the agreed scope and range, required to complete one specified unit of measurement of a billed (BOQ) item; VAT is excluded (a price-exclusive tax). Basis: GB/T 50500-2024 Clause 2.0.9 and GB/T 50875-2013 Clause 2.2.58; building works BOQ-based pricing uses the "incomplete-cost" caliber excluding statutory levies and fees and taxes, while highways and other industries may use the fully loaded caliber including statutory levies and fees and taxes — confirm the applicable industry standard before citing.
- →
Validity limits of "all risks borne by the contractor" clauses and statutory exclusions (GB/T 50500-2024 + Civil Code)
"All risks borne by the contractor" clauses are "uncapped risk allocation to one party" agreements prohibited by GB/T 50500-2024 Article 3.3.1—not automatically void wholesale, but limited in effect: valid for the contractor's own operational, technical, and managerial risks (Article 3.3.3, eight items); not waivable for statutory events—force majeure (Civil Code 590), personal injury and intentional/gross negligence (506), unfairly one-sided standard clauses (497), change of circumstances (533), legislative/policy changes and unforeseeable abnormal cost fluctuations at signing (8.7.3)—which judicial practice reallocates under the equitable risk allocation principle.
Cited By
- ←
Main-material price surge beyond the risk band: sequencing between GB/T 50500-2024 Section 8.7/Appendix A price adjustment and Civil Code Article 533 change of circumstances
When main-material prices surge far beyond the contractual risk band, first complete price adjustment per GB/T 50500-2024 Section 8.7 and Appendix A (agreed risk band first; 5% fallback when unspecified/unclear; portions beyond the risk band at actual values, differences carrying VAT only, no management fee/profit); only the residual loss still grossly unfair after adjustment proceeds to 8.7.3 negotiation, and failing negotiation to Civil Code Article 533 modification or termination — a "contract first, statutory fallback" progression, not either-or. Judicial appraisal per GB/T 51262-2017 5.6.2: as agreed if agreed; adjustable but without an agreed risk band — the appointing party decides judicial appraisal per the national standard (unless already index-adjusted); agreed non-adjustable — government-priced/guided materials appraised per old Contract Law Article 63 (now Civil Code Article 513).
- ←
Rules for handling contract price adjustment for cost fluctuation in final account review and construction cost expert assessment: routing by contract type, price-dating principles for delay periods, the exception for government-priced materials, and the eight categories of costs not adjusted for changes in costs listed in GB/T 50500-2024 clause 8.7.6
Final account review and expert assessment proceed on two levels. (i) Routing by contract type: for lump-sum contracts, unless otherwise agreed, cost fluctuation is generally not adjusted, and a contractor claiming adjustment for change of circumstances or prolonged duration must proceed by claim; for unit-rate contracts the agreement prevails, and absent or unclear agreement the matter is resolved by reference to national, local or sector provisions, with labour, materials and plant outside the contractually adjustable scope not adjustable. Price-dating during delay: where the delay is not attributable to the contractor, the higher of the prices at the planned and actual progress dates applies; where attributable to the contractor, the lower applies; concurrent delay is shared by sequence and responsibility. (ii) Hard constraint on the scope of adjustment: GB/T 50500-2024 clause 8.7.6 lists eight categories of costs not adjusted for changes in costs (construction consumables, small and medium tools, preliminaries, plant and small tools costs other than fuel and power, material costs of items outside the agreed adjustable list, changes beyond the agreed scope or band, overheads and profit, and costs arising from the contractor's own causes); where the contract sets no band or sets it unclearly, fluctuation beyond 5% may be adjusted per Annex A (8.7.2), and abnormal movements of other materials outside the agreed adjustable scope may be handled by equitable risk allocation, by negotiation or by adjustment to actual costs (8.7.3, 3.3.6).
- ←
The direction of price adjustment for legal and policy changes during delay (extension) periods: contractor-caused delay takes no rises but all falls; employer-caused the reverse; neither-party delay adjusts on actuals (GB/T 50500-2024 clauses 8.8.1~8.8.4)
Direction follows fault: for contractor-caused extension, policy changes in the extension window bring no upward adjustment and all downward adjustments; for employer-caused extension, no downward and all upward; neither-party extension adjusts on actuals (save contract or other provision). Events are limited to legal and policy changes after the contract base date (enactment / amendment / repeal / changed government interpretation). Basis: GB/T 50500-2024 clauses 8.8.1~8.8.4; the model contract parallels GF-2017-0201 clause 11.2.
- ←
Pricing clash-detour increments of MEP services: the attribution boundary of detailing versus variation, the valuation entries (8.9.1 / 8.9.2 and 2013's 9.3.1), the material and labour increments of cable-tray extended metres, bends and supports, and the separate claim channel for stoppage and the site-record anchors
Three gates before pricing a detour: (1) difference nature - contract versus actual drawings = variation; refinement within one drawing set is no variation; (2) attribution - the employer's design errors and base-data faults are employer risk; the contractor's routine detailing avoidance is contractor risk, generally unadjusted (T/ZBD 100.4-2023 clause 4.4.6) save contracts settling on the contractor's detailing drawings; (3) the entry - variations with quantity moves within 15% price on the five bands of 8.9.1, beyond 15% on 8.9.2 with purchase-discount adjustments. Quantity magnitude fixes 'how to price', never 'whether to pay'. Stoppage, waiting and idle losses claim separately under 8.11.9 / 8.11.10 - never merged into variation rates.
- ←
Contract price adjustment for changes in laws, regulations and policies: the base date (28 days before the tender deadline / 28 days before contract signature) and the rule for contractor-caused delay that 'upward adjustments are denied, downward adjustments are granted' (GB 50500-2013 Section 9.2; GB/T 50500-2024 Section 8.8)
GB 50500-2013 Clause 9.2.1: for tendered works the base date is 28 days before the tender submission deadline, and for non-tendered works 28 days before contract signature; where changes in State laws, regulations, rules and policies afterwards increase or decrease the construction cost, the contract price is adjusted per the provisions issued accordingly by the provincial or sectoral construction authority or its authorised construction cost administration. Clause 9.2.2: where the time is delayed for reasons attributable to the contractor, upward adjustment of the contract price after the originally scheduled completion time is denied and downward adjustment is granted. Changes in laws and policies are a risk borne by the employer (Clause 3.4.2 item 1). GB/T 50500-2024 carries this forward in Clause 8.8.1 (four categories: newly added, amended, repealed, re-interpreted) and Clause 8.8.2 (during delay, increases denied, decreases granted).
- ←
Recognition criteria for force majeure events, item-by-item sharing of losses, costs and time, supporting insurance, and the conditions for terminating the contract for force majeure (GF-2017-0201 clauses 17.1/17.3/17.4 compared with GB/T 50500-2024 clauses 8.11.12 to 8.11.15)
Force majeure is recognised by the three criteria of being unforeseeable at contract signing, unavoidable and insurmountable during performance (GF-2017-0201 clause 17.1). The sharing basis: the employer bears damage to the permanent works and to materials/construction equipment delivered to site, third-party casualties and property losses caused by damage to the works, wages that must be paid to workers during suspension, care/cleaning/repair costs and the wages of necessary personnel kept on site at the employer's request, and acceleration costs requested by the employer; the contractor bears damage to its own construction plant and preliminaries facilities, and each party bears its own casualties and other property; the contractor's other suspension costs are reasonably shared by both parties and the time for completion is extended accordingly; losses enlarged by failure to mitigate are borne by the party that failed to mitigate, and force majeure encountered during delayed performance does not relieve liability for breach (clause 17.3.2; GB/T 50500-2024 clause 8.11.12). Where force majeure prevents performance of the contract continuously for more than 84 days or cumulatively for more than 140 days, either party may terminate; after termination the seven heads of payment under clause 17.4 are paid within 28 days of being agreed or determined.
- ←
The relationship between the risk allowance inside the all-in unit rate and contractual price adjustment for fluctuation: within the band the risk allowance absorbs the movement, beyond the band only the excess is adjusted, and the two are never counted twice
The risk allowance and contractual price adjustment are a two-stage allocation of the same pricing risk against the risk band r agreed in the contract: within r, the movement is absorbed by the risk allowance implied in the all-in unit rate (not billed as a separate item, not repaid at settlement); when the movement exceeds r, the adjustment rules adjust only the excess. The exclusion of double counting runs both ways - GB 50500-2013 Clause 6.2.2 states that 'when the risk content and its scope (band) that arises falls within the range agreed in the contract, the contract price shall not be adjusted'; GB/T 50500-2024 Clause 3.3.5 states that the price differential adjustment 'shall carry VAT but shall not carry management fee or profit', and Clause 8.7.6 states that management fee and profit, preliminaries and other plant and small tools costs shall not be adjusted for changes in costs, that is, an above-band adjustment may not be stacked with risk allowance / management fee / profit. Clause numbers must not be mixed across editions: in the 2013 edition the all-in unit rate is Clause 2.0.8 and the risk allowance is Clause 2.0.9; in the 2024 edition the all-in unit rate is Clause 2.0.9 (excluding VAT).
- ←
Defining and selecting construction contract price forms: unit-rate, lump-sum and cost-plus contracts chosen by design depth, technical difficulty, time and pricing risk
GB/T 50500-2024 clause 3.4.1 fixes the selection: clear requirements, controllable measurement and pricing and small price-fluctuation risk suit the lump-sum contract; requirements not yet clear, high technical difficulty, many uncontrollable pricing factors and large price risk suit the unit-rate contract; extreme urgency precluding detailed planning and full negotiation, or specially complex works with large pricing risk, suits cost-plus - clause 3.4.3 adds emergency rescue, disaster relief or specially complex works. The statutory definitions are clauses 2.0.6~2.0.8 (unit-rate: quantities as executed, rates fixed within agreement; lump-sum: price fixed within agreement, no adjustment for quantity changes while drawings and conditions stand; cost-plus = cost + agreed fee). The choice also binds the BOQ-error liability (3.1.8), risk allocation (3.3.2/3.3.3) and settlement treatment (GB/T 51095-2015 clause 8.2.5).
- ←
The non-adjustment boundary of material price adjustment: the eight cost classes never adjusted for price moves, the BOQ items outside routine adjustment, and the negotiated handling of abnormal fluctuation (GB/T 50500-2024 clauses 8.7.3 / 8.7.5 / 8.7.6)
GB/T 50500-2024 clause 8.7.6 lists eight classes never adjusted for price moves: construction consumables, small tools, preliminaries, other plant costs, materials outside the agreed adjustable items, price moves beyond the agreed scope and band, overheads and profit, and contractor-cause costs; clause 8.7.5 keeps the adjustment away from employer-supplied material items and provisionally priced material items; clauses 8.7.3 and 3.3.6 are the negotiated channels for abnormal fluctuation or missing agreement. Differences carry VAT only, never overheads or profit.
- ←
May quantities cut by design variation be listed as negative BOQ items: the contract BOQ itself never goes negative - increases and decreases fall to the "variation increase-and-decrease price" item at final account; under lump-sum (fixed-price) contracts BOQ defects do not adjust, only differences between as-built and contract drawings form priceable variations (GB/T 50500-2024)
Quantity cuts from design variations must never be written as negative quantities in the original contract BOQ - BOQ quantities compute on design-shown dimensions and, under lump-sum contracts, divisional BOQ quantities need no re-measurement (clause 7.2.2); the cuts land at the settlement adjustment layer, item 9 of GB/T 50500-2024 clause 10.3.2, "variation increase-and-decrease price" (which may be negative), the contract-BOQ-total line standing unchanged. Under lump-sum contracts only the difference between as-built and contract drawings constitutes a priceable variation (clause 7.4.3); contract-drawing versus contract-BOQ differences are BOQ defects and never adjust (7.4.2, 8.2.3). Variation pricing splits on whether contract rates apply: applying, adjust under 8.9.1 (quantity change within 15%, inclusive) or 8.9.2 (over 15%, exclusive - cuts reasonably raise rates); not applying, the parties negotiate the all-in rates (8.9.3).
- ←
The mechanism for determining the scope of price-adjustable materials and typical categories (GB/T 50500-2024 appendix G.2)
GB/T 50500-2024 sets no statutory "list of price-adjustable materials": the employer and contractor define the scope of adjustable main materials and lock it in as a contract annex by completing table G.2.1-1 (price-information adjustment method) or G.2.1-2 (price-index adjustment method) of appendix G.2; the statutory adjustable factors are only three classes — labor cost, main material cost, and fuel/power cost of construction plant; price differences carry VAT only, with no management fee or profit.
- ←
Rules for determining the material adjustment base price (C0): base date, one-of-three sources and the adjustment computation base (GB/T 50500-2024)
The base price C0 = the market price level 28 days before the bid closing date (for non-tendered works, 28 days before contract signing); that instant is the contract base date (term 2.0.21). The source is one of: (1) the market price used in the maximum bid price; (2) the current quarter's (month's) guidance price of the cost management agency; (3) the winning-bid price of analogous works under the same conditions published by the local trading center — all must represent the base-date price level, and the tender documents must state the source, publishing agency and specific quarter (month). Where the guidance price is the base, whether the bid is below/above/equal to the base decides the computation base of the excess portion (appendix A.2.4, preventing high/low-bid arbitrage); the price-index method corresponds to the basic price index F0.
- ←
Adjustment of the contract price (GB/T 50500-2024 Chapter 8): eleven triggering events, mechanism by section, and FIDIC mapping
Adjustment of the contract price is the mechanism for changing the contract price during performance. GB/T 50500-2024 Cl. 8.1.1 lists eleven triggering events: BOQ errors, provisional sums, PC sums (provisional estimates), contractor's services, dayworks, changes in costs, changes in laws and policies, variations, additional works, claims, and other events agreed by the parties; the procedure runs submit, check, re-check, review and confirm (8.1.2). Key mechanics: BOQ errors and variations share one re-rating ladder (identical items at contract rates; analogous items converted; different items negotiated), with a 15% quantity boundary for re-rating (8.2/8.9); provisional sums are controlled by the employer and any unused balance reverts at final account (8.3); PC-sum items are replaced by tender prices — materials pre-VAT, specialist works VAT-inclusive (8.4); dayworks are measured under 7.5 (certified dayworks records) and priced at the BOQ daywork rates (8.6, with deemed approval if verification is overdue, 7.5.5); changes in costs are adjusted beyond the agreed band — 5% by default — by index-based (formula) adjustment or adjustment based on published price information (8.7 + Annex A), the differential carrying VAT only; changes in laws pivot on the base date, adjusting price and/or time for enactments, amendments, repeals or new interpretations after it, with no upward adjustment during contractor-caused delay (8.8); additional works may follow contract rates or freshly negotiated rules under a supplementary agreement (8.10); claims cover events outside 8.2-8.10 — compensatory, not punitive, and mutual, with profit added for eight categories of employer-risk events (8.11). FIDIC counterparts sit scattered across Clause 13 (variation valuation 13.3, provisional sums 13.4, changes in laws 13.6, changes in cost 13.7 — 2017 numbering) and Clause 20 claims (28-day hard time bar): adjacent institutions, not chapter-for-chapter equivalents.
- ←
Price adjustment for wires and cables: itemized by full specification, copper-linkage agreements, and handling missing published price information (government guidance prices) (GB/T 50500-2024 Appendix A.2)
Cable price adjustment shares the same mechanism as steel (GB/T 50500-2024 Appendix A.2 adjustment based on published price information (government guidance prices)): difference = SUM[(Ci - C0 x (1 +/- r)) x Q], only the portion exceeding the risk band is adjusted on an actual basis; r as agreed takes precedence, and if not agreed, fluctuation beyond 5% is adjustable (8.7.2); C0 = market price 28 days before the tender deadline (= FIDIC Base Date) (for non-tendered projects: 28 days before contract signing); the difference carries value added tax (VAT) only, no management fee or profit. Cables must be listed item by item in Table G.2.1-1 by full specification (voltage class x cores x cross-section x armor x flame-retardance) and adjusted separately — merging and averaging is strictly prohibited; the copper-linkage method must fix in the contract the copper content/conversion coefficient and the copper-price source; for missing published price information, the paths are employer's approval of material prices / market price enquiry, with symmetric unit bases.
- ←
Appendix A price adjustment (for fluctuation) methods for changes in costs, GB 50500-2013 vs GB/T 50500-2024: weighting coefficient basis and adjustment threshold differences
The two editions share the same formula skeleton in Appendix A (index-based (formula) adjustment dP = P0[A + sum BiFit/Fi0 - 1]; adjustment based on published price information adjusts the portion beyond the risk band (no-adjustment tolerance, e.g. ±5%) at actual values); differences lie in the basis and mechanisms: (1) weighting — 2013 variable weights are 'proportions of the total tender price in the tender letter' (including VAT), 2024 uses 'weights of the contract price excluding VAT' (separation of net price and VAT), and 2024 adds A.1.4 fallback 'where variable weights are not agreed, the corresponding weights of the tender price ceiling may be used' and A.1.1 merges the fluctuation range into the base price index F0; (2) thresholds — both editions' fallback is 5% (beyond which actual-value adjustment applies; 2013 clause 9.8.2, 2024 clause 8.7.2), and 2024 adds the sign rule for the r risk band coefficient, defines the base price (reference price for adjustment) as the market price 28 days before the tender deadline (= FIDIC Base Date) (28 days before contract signing for non-tendered works), and the 8.7.6 list of items not subject to price adjustment. GB 50500-2013 was mandatory (replaced); 2024 is recommended national standard GB/T.
- ←
Price-difference calculation method after material prices exceed the risk band (price-information adjustment method, GB/T 50500-2024 Appendix A.2)
The excess beyond the risk band is adjusted per actuals: when prices rise, unit price difference = Ci - C0 x (1 + r); when prices fall, = C0 x (1 - r) - Ci; adjustment amount = unit price difference x adjusted quantity Q; where the contract does not agree a risk band, fluctuation beyond 5% triggers adjustment (Clause 8.7.2); where the bid price differs from the base price, the cross-basis rule of A.2.4 applies to prevent arbitrage; the price difference carries VAT only, with no management fee or profit.
- ←
Alternative adjustment paths when price information lacks the specification: mutually confirmed price / purchase price / awarded-bid price fallbacks + the same-caliber red line for C0 and Ci (GB/T 50500-2024 Appendix A.2)
Price information is only one of the Ci sources listed in A.2.1; lacking the specification does not mean adjustment is impossible: determine Ci per (1) contract agreement, (2) the market price of the measurement period confirmed by both parties, (3) the purchase price determined by the employer (submitted before purchase; deemed accepted upon overdue silence), (4) the awarded bid price of the trading center for similar works under similar conditions in the same period; C0 takes prices by the same rules; where information is temporarily missing, provisionally account per the published price and settle later. Red lines: C0 and Ci must be of the same caliber; the alternative price must represent the market price level of the measurement period; keep a full trail of certified records of agreed material prices.
- ←
Mechanism for material price changes under fixed unit-price contracts: unit price locked + quantities at actuals + beyond-band adjustment (GB/T 50500-2024)
Under unit-price contracts the all-in unit rate is fixed within the contract-agreed risk conditions and quantities are determined at what is actually completed and should be measured (2.0.6); material prices follow "contract agreement first, statutory fallback": an express adjustment clause adjusts per the agreement -> agreement of adjustability without method follows industry pricing documents -> express non-adjustment is executed (unless the clause is invalid) -> no agreed band: fluctuation beyond 5% adjusts per Appendix A (8.7.2); the difference carries VAT only, no management fee or profit (3.3.5).
- ←
GB/T 50500-2024 list of measurement and pricing risk allocation: Clause 3.3.2 seven employer-borne risks, Clause 3.3.3 eight items for the contractor's tender, and the Clause 6.1.8 tender link
Under GB/T 50500-2024, Clause 3.3.2 lists 7 employer-borne risks (errors and omissions in the BOQ of a re-measurable contract, errors in the employer's original data and datum, approved variations, directed acceleration/early completion/suspension or slowing of the works, changes in laws, regulations and policies, cost fluctuation beyond the agreed range, others), which the contractor's tender need not consider; Clause 3.3.3 lists 8 items the contractor shall consider in its tender (accuracy and completeness of the bill of preliminaries, errors and omissions in the BOQ of a lump-sum contract, the cost of completing all work per the contract drawings, specifications and measurement standards, changes to the contractor's own scheme, causes attributable to the contractor's own plant, technique or management, the contractor's own acceleration or suspension, cost fluctuation within the agreed band, others). The contractor bears its own technical and management risks (e.g. management fees) and a certain market risk, but not the risk of changes in laws, regulations and policies; the tender price shall include the risk costs within the agreed ranges (6.1.8), and where the tender documents are silent, bidders shall seek written clarification from the employer within the prescribed time.
- ←
Can final account review/audit adjust awarded all-in unit rates? — rate locking under re-measurable contracts, statutory exceptions, and the limits of audit authority
In principle, no. Under a re-measurable (unit-rate) contract, awarded all-in unit rates within the contractual risk range remain fixed at final account review; the review checks each rate item by item against the priced bill of quantities (BOQ); absent other contractual agreement, rates adjust only upon adjustment events such as variations, errors and omissions in the BOQ, quantity deviations exceeding 15%, changes in costs beyond the risk range, and substitution of provisional sums. Government fiscal review of project cost / audit is administrative supervision and does not affect contract validity — its conclusions serve as the basis for settlement only where the contract expressly provides that they do so.
- ←
Rules for determining the quantity (Q) of materials subject to price adjustment: contractual agreement takes precedence, and key points on matching the quantity basis and the period (GB/T 50500-2024)
There is no unified statutory formula for the adjustable-factor quantity Q; it is determined by the calculation method agreed by the employer and contractor in the contract (Appendix A.2.1 + Note 2 of Table G.2.1-1), and must be detailed and clarified in the tender documents / contract special clauses. In practice, the most common basis is "quantities measured for the current period x material consumption under quota norms (prescribed resource consumption standards)/mix ratio (including wastage)", or the purchase quantities confirmed by the employer (A.2.5). Q must correspond to the basis of the price adjustment period and to the price Ci for the measurement period; where the contract is silent, the standard provides no fallback determination and disputes easily arise.