Determining the pricing risk scope within the all-in unit rate: contract agreement first + statutory fallback of GB/T 50500-2024 Sections 3.3/8.7

Risk-scope determination follows 'contract agreement first, statutory fallback second': the employer and contractor must specify the content, scope and risk band (no-adjustment tolerance, e.g. ±5%) of measurement and pricing risks in the tender documents/contract, and clauses providing for uncapped risk allocation to one party and 'all risks' are prohibited; where not agreed or unclear, the risks are statically divided per GB/T 50500-2024 Clauses 3.3.2/3.3.3 (employer: BOQ errors / omissions, errors in raw data, approved changes, acceleration/stoppage, changes in laws and policies, cost fluctuations beyond the risk band; contractor: accuracy of the bill of preliminaries, BOQ errors / omissions in lump-sum contracts, own scheme/machinery/management, cost fluctuations within the risk band), with Section 8.7 as the dynamic quantitative fallback (where no risk band is agreed, the portion exceeding 5% is adjusted per Appendix A; the price difference carries value added tax (VAT) only, with no management fee or profit).

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第3.3.1~3.3.6条
  • GB/T 50500-2024 第8.7节
  • GB/T 50500-2024 App. A
  • GB/T 50500-2024 App. G Table G.2.1-1/-2

Topic Positioning

This card covers how the pricing risk scope within the all-in unit rate is determined: static responsibility division under the equitable risk allocation principle and the quantitative fallback for cost fluctuations, applicable to tender (priced offer), contract review and settlement disputes.

Core Conclusions

General principle (Clause 3.3.1): the risk content, scope or risk band must be specified in the tender documents/contract; clauses providing for uncapped risk allocation to one party and 'all risks' are prohibited. Static division — borne by the employer (Clause 3.3.2): BOQ errors / omissions in the employer-provided BOQ under re-measurable (unit-rate) contracts (except the bill of preliminaries), errors in raw data, approved changes, acceleration/stoppage, changes in laws and policies, cost fluctuations beyond the risk band; borne by the contractor (Clause 3.3.3): accuracy and completeness of the bill of preliminaries, BOQ errors / omissions in lump-sum contracts, all costs of completing the billed (BOQ) items, own scheme/machinery/management-level causes, cost fluctuations within the risk band. Dynamic rules — where agreed, the agreement governs (Clause 3.3.5; adjustable materials may use Appendix G Tables G.2.1-1/-2 as contract annexes); where no risk band is agreed, the portion of cost fluctuation exceeding 5% is adjusted per Appendix A (Clause 8.7.2), the base price (reference price for adjustment) being the published price information (government guidance prices) current 28 days before the tender deadline (= FIDIC Base Date) (A.2.4); unforeseeable abnormal fluctuations are shared by negotiation. Cost embodiment — the risk cost enters the all-in unit rate; the price difference carries value added tax (VAT) only, with no management fee or profit (Clause 8.7.6).

Applicable Boundaries

Applies to construction employer-contractor relations under the GB/T 50500-2024 BOQ-based pricing system; where the contract has agreements, they govern, the standard serving as the fallback; not applicable to engineering, procurement and construction (EPC/Turnkey) pricing.

Further Reading

See GB/T 50500-2024 Clauses 3.3.1-3.3.6, Section 8.7, Appendix A, and Appendix G Tables G.2.1-1/-2; extensions: the 'four elements of material price adjustment' and 'validity boundary of uncapped risk allocation clauses' cards.