Price adjustment for wires and cables: itemized by full specification, copper-linkage agreements, and handling missing published price information (government guidance prices) (GB/T 50500-2024 Appendix A.2)

Cable price adjustment shares the same mechanism as steel (GB/T 50500-2024 Appendix A.2 adjustment based on published price information (government guidance prices)): difference = SUM[(Ci - C0 x (1 +/- r)) x Q], only the portion exceeding the risk band is adjusted on an actual basis; r as agreed takes precedence, and if not agreed, fluctuation beyond 5% is adjustable (8.7.2); C0 = market price 28 days before the tender deadline (= FIDIC Base Date) (for non-tendered projects: 28 days before contract signing); the difference carries value added tax (VAT) only, no management fee or profit. Cables must be listed item by item in Table G.2.1-1 by full specification (voltage class x cores x cross-section x armor x flame-retardance) and adjusted separately — merging and averaging is strictly prohibited; the copper-linkage method must fix in the contract the copper content/conversion coefficient and the copper-price source; for missing published price information, the paths are employer's approval of material prices / market price enquiry, with symmetric unit bases.

Applicable Codes

  • GB/T 50500-2024 App. A.2
  • GB/T 50500-2024 第3.3.5条
  • GB/T 50500-2024 第8.7节
  • GB/T 50500-2024 App. GTable G.2.1

Topic Positioning

Price adjustment for multi-specification main materials such as wires and cables: key points of applying the GB/T 50500-2024 Appendix A.2 adjustment based on published price information (government guidance prices) to cables.

Core Conclusions

(1) Formula as for general main materials (A.2.1): difference = SUM[(Ci - C0 x (1 +/- r)) x Q], only the portion exceeding the risk band is adjusted on an actual basis; r as agreed takes precedence, and if not agreed, beyond 5% is adjustable (8.7.2); C0 = market price 28 days before the tender deadline (= FIDIC Base Date) (non-tendered: 28 days before contract signing); the difference carries value added tax (VAT) only, no management fee or profit (3.3.5). (2) Cables must be listed item by item in Appendix G Table G.2.1-1 (contract annex) by full specification (voltage class x cores x cross-section x armor x flame retardance) and adjusted item by item — merging and averaging is strictly prohibited. (3) Copper linkage: with copper cost dominating, the contract may agree to adjust by copper content x copper-price movement — the conversion coefficient, copper-price source, base copper price, and risk band must be fixed in writing, or settlement disputes are guaranteed. (4) Missing items and bases: specifications not covered by published price information follow contract agreement -> employer's approval of material prices (A.2.5, deemed approval upon lapse of the response period) -> market price enquiry to fill gaps; the base price (reference price for adjustment) and the measurement period price must share the same unit (km/m) and tax-inclusive basis — quota norms (prescribed resource consumption standards) often price per 100 m.

Applicable Boundaries

Applies to adjustment for cost fluctuation of contract-agreed adjustable main materials (Table G.2.1 as contract annex); not to consumables, small tools, preliminaries, management fee and profit, fluctuations within the risk band, or the contractor's own costs; copper linkage presupposes an express contract agreement; do not mix with price differences during estimate/budget compilation periods.

Further Reading

GB/T 50500-2024: Appendices A.2.1-A.2.5, Clause 3.3.5, Section 8.7, Appendix G Tables G.2.1-1/-2, term 2.0.21; extended reading: steel price adjustment and the Ci determination rules cards.