Matching material specifications in price information with actual materials: four-element matching, grade/unit conversion, and adjustment-specification locking

Price-taking from price information matches precisely by the four elements name + specification + model + unit (the GB/T 50500-2024 Appendix G adjustment table is listed accordingly); with no same specification, convert by the adjacent grade or grade price difference with records (marked "converted"); inconsistent measurement units are converted first (e.g., rebar in t vs kg/m using theoretical weight); missing items are filled by market inquiry (>=3 suppliers); when adjusting per price information, lock the specification caliber at contract signing via the adjustable main materials table (Appendix G.2.1) and match one-to-one at settlement; where the current issue lacks the corresponding specification, provisionally compute per the current price information and adjust later per actuals (Appendix A.2.2).

Applicable Codes

  • GB/T 50500-2024
  • GB/T 50875-2013
  • T/ZBD 100.1-2022
  • TB/T 10813-2024
  • TB 10811-2024

Topic Positioning

Answers "how to match material specifications in price information with actual materials": the complete price-taking method of four-element precise matching, grade/unit conversion, gap-filling for missing items, and adjustment-specification locking, for correct price-taking in price assembly and price-information adjustment and preventing mismatches.

Core Conclusions

(1) Four-element matching: simultaneously verify name, specification, model, and unit (the GB/T 50500-2024 Appendix G adjustment table is listed by these four elements plus the base price); the same name with different specifications means large price differences (e.g., rebar phi12 vs phi25, C30 vs C40 ready-mixed concrete) — never take prices just because "the names are similar". (2) With no same specification: take by the adjacent grade or convert by the grade price difference, keeping records of the conversion (pricing software marks "converted"); inconsistent measurement units are converted first (e.g., rebar price information in t while quota consumption in kg/m — convert using theoretical weight); brand/origin differences follow the contractual confirmed price or manufacturer quotation; missing items are filled by market inquiry (>=3 suppliers), with the settlement priority contract agreement > mutually confirmed price > price information > market inquiry. (3) Adjustment locking: where the contract agrees adjustment per price information, at signing the tenderer fills the "adjustable main materials table provided by the contractor" (serial number, name, specification, model, unit, base price, risk band, Appendix G.2.1) to lock the specification caliber, and settlement takes the current issue's price information matched one-to-one; where the current issue lacks the corresponding specification, provisionally compute per the current cost information and adjust later per actual market prices (Appendix A.2.2).

Applicable Boundaries

Applies to material price assembly and price-information adjustment specification matching under BOQ pricing; not applicable to direct pricing of materials without price information (inquiry and confirmation apply). Price information is a reference-guidance price published by cost administration agencies (GB/T 50875-2013 Clause 2.1.16) and must be built with market prices and manufacturer quotations in three classified channels, strictly never mixed (T/ZBD 100.1-2022 Clause 7.2.3); confirm the price-information caliber before taking prices (whether it includes freight, the procurement-and-keeping fee, and tax).

Further Reading

GB/T 50500-2024 Clause 4.2.2 (complete item features including specification and model), Appendix G.2.1 (adjustable main materials table), Appendices A.2.1-A.2.5 (price-information adjustment and provisional differences); GB/T 50875-2013 Clause 2.1.16 (definition of project cost information); T/ZBD 100.1-2022 Clause 7.2.3 (three-channel classification); railway caliber see TB/T 10813-2024 base-period price Classes A/B/C and TB 10811-2024 Table 2.2.2 procurement-and-keeping rates.