Whether published price information / base-period prices include freight and miscellaneous charges: price-caliber determination (ex-factory caliber excludes, delivered-to-site caliber includes) and the A/B/C classification of railway base-period prices
Whether price information includes transport charges depends on the publication caliber: the ex-factory/market-price caliber excludes freight and miscellaneous charges (to be listed separately when compiling budgets), while the delivered-to-site caliber includes them (usable directly for price assembly). Railway base-period prices per TB 10813-2024 fall into three classes: Class A = original price x (1 + procurement-and-keeping rate) and Class B = comprehensive ex-factory price x (1 + procurement-and-keeping rate) both exclude freight and miscellaneous charges; only Class C = (original price + freight-and-miscellaneous charges within the price) x (1 + procurement-and-keeping rate) includes them. Always read the current issue's publication notes to confirm the caliber before use.
Applicable Codes
- GB/T 50875-2013
- TB 10801-2024
- TB 10813-2024
- T/ZBD 100.1-2022
Topic Positioning
How to determine whether published price information / base-period prices include transport charges: the publication caliber decides whether freight and handling charges are included, with the specific A/B/C classification of railway base-period prices.
Core Conclusions
Norm-based material price for estimating = (material price at source + freight and handling included in the material price) × (1 + purchasing and custody charges rate) (TB 10801-2024 Clause 3.2.5); freight and handling charges are an independent component of that price — never assume the published price information already includes freight. Whether it does depends on the publication caliber: (1) ex-works / market price caliber (ex-works price or price at a designated delivery point) — excludes freight and handling charges, which must be listed separately per the transport plan when compiling estimates; (2) delivered-to-site caliber (including transport, loading and unloading charges to site) — includes freight and handling charges and can be used directly in estimates. Railway base-period prices (TB 10813-2024) fall into three classes: Class A = price at source × (1 + purchasing and custody charges rate) and Class B = comprehensive ex-factory price × (1 + purchasing and custody charges rate), both excluding freight and handling charges; only Class C = (price at source + freight and handling included in the material price) × (1 + purchasing and custody charges rate) includes them. Base-period prices are at the 2020 price level and exclude deductible input VAT.
Applicable Boundaries
Applies to judging the caliber of published price information in cost compilation and price adjustment. Published price information is a reference price issued by cost administration agencies (GB/T 50875-2013 Clause 2.1.16); market prices, published price information and manufacturer quotations must be built as three separately classified channels and strictly never mixed (T/ZBD 100.1-2022 Clause 7.2.3). Publication calibers differ by region — read the current issue's notes before use; when a contract provides for "price adjustment based on published price information", state clearly whether freight and handling charges are included, otherwise disputes easily arise at settlement. Base-period prices are used only for quota, estimate, budget estimate and budget compilation; prices at the implementation stage are determined by the market.
Further Reading
Composition of the norm-based material price for estimating: TB 10801-2024 Section 3.2 (material cost); base-period price classification and formulas: TB 10813-2024 Base-period prices of railway works materials, Clauses 1.0.2–1.0.4; term definitions: GB/T 50875-2013 Clause 2.1.16 (published construction cost information), Clause 2.2.16 (material freight and handling charges); three-channel classification: T/ZBD 100.1-2022 Clause 7.2.3.
Keywords
Related Cards
- →
Building an enterprise material-price database: a three-channel-separated price fact table, collection-and-review workflow, and dynamic maintenance mechanism
An enterprise database holds "tradable, voucher-backed real prices" rather than published prices: build market prices/published prices/vendor quotations as three separately classified channels, never mixed, dominated by transaction prices; the core is a traceable price fact table (material identifier + price attributes + region and period + source voucher + quality status), supported by a material master-data table, a supplier table, and an inquiry ledger; transaction data updates in real time, estimate/approximate-estimate libraries adjust monthly/quarterly, and prices without vouchers are not entered.
- →
Guidance price vs market price: definition sources, essential difference and role positioning (official term definitions + three-channel classification rule)
The guidance price (construction cost information) is the labor/material/plant-shift price information plus cost indices and indicators periodically published by cost management agencies — a reference, guidance price (GB/T 50875-2013 clause 2.1.16); the market price is the actually transacted price, acquired mainly through transactions. The two differ essentially; per T/ZBD 100.1-2022 clause 7.2.3 they must be developed as data under the three channels market/guidance/vendor-quotation prices, strictly never mixed. Guidance prices serve maximum bid prices, adjustment base prices and dispute fallbacks; market prices serve actual procurement cost verification, filling gaps of materials without guidance prices, and — after joint confirmation — as settlement bases.
- →
Calculation rules for railway material transport costs (out-of-price freight and miscellaneous charges) and secondary haulage (TB 10801/10811/10821)
Out-of-price freight and miscellaneous charges = sum(freight + loading/unloading + other transport charges) x (1 + procurement-and-keeping rate); train tariffs split by business line/temporary line/work trains into formulas multiplied by K1/K2 composite coefficients; truck tariffs computed as highway x 1.05, haul road x 1.2; on-site small hauling within 50 m is already in quota labor and not charged again; short-haul beyond 50 m is charged per TB/T 10821 short-haul transport quotas.
- →
Determining material cost within the all-in unit rate: the two-step norm resource consumption × material unit price method, special situations, and the tax-exclusive boundary
Material cost = norm material consumption × norm-based material price for estimating: consumption is taken from the factor quantities of the budget quota norms (prescribed resource consumption standards) line item; the material unit price is the composite average price from the place of origin to the site warehouse up to issuance from the warehouse, with industry-specific formulas (railway: (original price + freight and handling included in the material price) × (1 + purchasing and custody percentage rate); highway: (original price + freight and handling charges) × (1 + off-site transport wastage rate) × (1 + purchasing and custody percentage rate)). Prime cost (PC) sums for materials are included at the tax-exclusive unit price stated in the BOQ; cost fluctuations beyond the agreed risk band (no-adjustment tolerance, e.g. ±5%; if not agreed, 5%) are adjusted per Appendix A, the price difference carrying value added tax (VAT) only, with no management fee or profit; material cost never includes VAT.
- →
Published price information vs actual procurement price: issuing body, basis and timeliness, settlement effect (practice comparison)
The published price information is a regional statistical composite price periodically issued by cost management agencies (monthly/quarterly issues, lagging, excluding brand, batch, haul distance and payment terms); the actual procurement price is the enterprise's real current transaction price (including brand/model, batch, haul distance and freight, payment terms, VAT rate, bargaining power and other specifics) — either can be higher or lower: batch purchase plus cash payment is often below the published price information, while small-batch urgent purchase or long-distance haul is often above. The published price information is used for tender price ceilings, contract-agreed adjustment base prices and dispute fallback references; the procurement contract price and the invoice price only prove actual cost and must first be confirmed by the employer as an agreed material price (certified record of agreed material prices) before being upgraded to a basis for settlement.
Cited By
- ←
Reading published price information as tax-inclusive or net, and the de-taxing conversion: de-tax by element (goods 13%, transport 9%, levy rate 3%), then custody, then into the all-in unit rate - with the order-bias test and double-tax prevention
Published prices are often tax-inclusive or freight-inclusive: read the release notes first. Tax-inclusive prices de-tax by each element's own rate (goods 13%, transport services 9%, simplified levy 3%) before purchasing and custody; a tax-inclusive delivered price divided once by 1.13 never adds freight or custody again. 'Add freight then divide the whole by 13%' differs algebraically from 'divide first, add later' only in form - both de-tax freight at 13%; the bias test is delta = F x (1/1.09 - 1/1.13) x (1+k). Net prices enter the all-in unit rate with VAT listed separately - one VAT only, throughout (GB/T 50500-2024 clauses 2.0.9, 3.1.6, 3.2.11).
- ←
Where material wastage is booked, and the double counting and omission tests: off-site transport and storage losses into the material unit price (price factor) versus site haulage and operation losses into the quota consumption (quantity factor), with the site warehouse / designated stockpile point as the boundary, plus a comparison of booking positions for typical work items and settlement audit checkpoints
Material wastage may enter only one of the material unit price (price factor) or the quota consumption (quantity factor); the dividing line is the site warehouse / designated stockpile point. Losses before the line (source to site warehouse) - transport loss and store-keeping loss - go into the material unit price (highway lists an off-site transport wastage rate separately; railway folds it into purchasing and custody charges; building works list a transport loss charge plus a storage loss); losses after the line (warehouse / stockpile point to the point of working or installation) - transport, processing, working and on-site stockpiling losses - go into the quota consumption. Since material cost = quota material consumption x norm-based material price, each factor carries only its own segment of wastage and nothing repeats: multiplying the same segment into both factors (overstating by roughly that wastage rate) is double counting; missing from both is omission. When applying quotas to compile a budget, the wastage rate must not be applied once more on top of the quota consumption (consumption = net quantity x (1 + wastage rate) is an algorithm at the level of quota compilation and measurement only).
- ←
Four cost components of the material price (norm-based material price for estimating) and the step-by-step computation: the formula, the charging base of purchasing and custody, the double pass of transport wastage and the placement of inspection and testing costs
Material price (norm-based material price for estimating) = (material price at source + freight and handling) x (1 + transport wastage rate) x (1 + purchasing and custody rate); purchasing and custody charges take price at source + freight and handling + transport wastage, i.e. the wastage-inclusive source price and freight, as their base (wastage passes through both the wastage and custody stages - the sanctioned basis, not double counting), and the two rates must not simply be added; at 2% wastage and 3% custody the combined factor is 1.02 x 1.03 = 1.0506 (simple addition gives 1.05, about 0.06% short). The material price contains only four items - source price, freight and handling, transport wastage, purchasing and custody; inspection and testing costs of the contractor's ordinary verification sit in overheads, not in the material price. The railway basis differs: transport wastage merges into purchasing and custody, the formula being (source price + freight included in price) x (1 + custody rate), with no separate wastage multiplier.
- ←
Three-step test for the unit price basis of cofferdam and island-building clay (borrowed fill): no extra charge where the quota already includes borrowing; priced per quota consumption where clay is listed as a material and adjusted as executed; purchased fill follows the fill material cost / norm-based material price basis
Cofferdam clay unit prices follow a three-step test (a decision order, not three alternatives): (1) where the quota item's work content already includes borrowing, no clay material cost is charged - the railway TB/T 10823-2024 Volume 2 plastic woven sack cofferdam work content includes excavation, manual bagging and haulage within 20 m, and its consumption table lists no soil material; (2) where the quota lists clay in the material consumption, price by the quota consumption and adjust at settlement per the actual borrowing (SJG 181.2-2024 Article 8.1.7 paragraph 2); (3) where purchase is genuinely required, the railway uses the fill material cost basis - fill material cost = sum of fill consumption x fill price (TB 10801-2024 Article 3.5.2), the fill price excluding deductible input VAT and being determined by the design institute through investigation and analysis (TB 10811-2024 Article 2.5.1); highways take purchased materials by reference to published prices combined with surveyed market prices, and self-quarried clay at the quota winning price plus auxiliary production on-costs and mineral resources tax.
- ←
Quota application and the four-stage pricing and measurement method (mixing, haulage, spreading and rolling, curing) for cement-stabilised crushed stone (cement-stabilised base) base courses
Pricing a cement-stabilised crushed stone base starts from the mix source: with purchased commercial mix, only one base spreading-and-rolling item is applied - mixing is already in the priced material and is not itemised again, and curing is in the item's work content and not itemised; with site mixing (in-place road mixing / central plant mixing) the works split into mixing + haulage + spreading and rolling. Haulage stacks a base haul distance plus increment hauls; where the average haul exceeds 15 km the haulage cost is calculated at market rates; where the mix proportion differs, materials are converted by Ci = [Cd + Bd x (H - H0)] x Li / Ld; where the compacted thickness exceeds the limit and mixing and rolling are done in layers, grader and roller machine-shifts are doubled per the quota quantities (DB63 road base over 15 cm: doubled plus 1.5 workdays per 1000 m2; TB/T 10834 station surfaces over 15 cm and base and cushion courses over 20 cm: x 2.0 coefficient).
- ←
Railway 2024 quotas: looking up base-period prices of sand — TB/T 10813-2024 sand table, medium-coarse sand by use, machine-made sand listed separately
The authoritative source is the "1. sand and mortar" subtable of Section 8 aggregate, Chapter 2 common materials, TB/T 10813-2024. Sands are not split by fineness modulus into medium/coarse: one "medium-coarse sand" by use in four bands — filling 60.63, masonry 65.48, beams 72.02, track slabs 73.46 yuan/m3; machine-made sand listed separately at 65.50; also fine sand 48.50 and refined sand (for CA mortar) 53.10. All Class A (base price = original price x (1 + procurement and custody rate); sand 4.47%), unit weight 1.43 t/m3. Base prices are 2020-level, ex-deductible-VAT; match the computer codes cited by each quota item — different parts use different codes of medium-coarse sand; do not mix.
- ←
Deciding how the pumping charge for ready-mixed concrete is applied: reading whether the published price information includes pumping, and the three mutually exclusive quota paths (a separate pumping item / convert materials by delivery method and apply the conveying item / included in the item, not charged again)
There is no national unified rule for pumping charges; two lines decide. (1) The publication notes of the current published price information - where issued as "ready-mixed concrete (pump type)" or marked as including pumping, it is included and never charged again; where issued by strength grade with a remark "pumping charge: truck pump +X, trailer (boom) pump +X yuan per m3", it is excluded and must be added. (2) The compilation basis of the quota item applied - "a separate concrete pumping item" (e.g. TB/T 10831-2024 Volume 10, FY-531 pump wagon 79.57 yuan per 10 m3, FY-532 stationary pump 107.25 yuan per 10 m3); "items exclude conveying - convert materials by delivery method and apply the conveying items of the chapter" (SJG 181.2-2024 Volume 2, clause 2.1.4); "items already include conveying, no further computation" (SJG 181.3-2024, SJG 181.4-2024 general rules). The three are mutually exclusive - one only; double charging is a high-frequency audit disallowance. Where no pumping item exists, charge by pumping plant machine-shifts (JTG/T 3833-2018 pump wagon 1781.5-2194.98 yuan per machine-shift, conveying pump 257.77-1241.61 yuan per machine-shift).
- ←
Scope of the "delivered price" basis of published material price information: the mainstream basis includes the material price at source, freight and handling charges, transport wastage and purchasing and custody charges, but exceptions exist by region and category; read the notes of the current issue before use, and never count twice charges already included
The mainstream basis of published price information is the "delivered price" - it includes the material price at source, freight and handling charges, transport wastage and purchasing and custody charges (GB/T 50875-2013 defines the material unit price as the comprehensive average price formed from the source of the building material to the site warehouse up to issue from stock). But the basis is not uniform nationwide: Beijing Construction Cost Information states that steel members exclude freight and handling charges, which may be increased on the facts where transport conditions are constrained. The notes of the current issue must be read before use, and freight and handling charges or purchasing and custody charges already included must not be counted again in the rates.
- ←
Matching material specifications in price information with actual materials: four-element matching, grade/unit conversion, and adjustment-specification locking
Price-taking from price information matches precisely by the four elements name + specification + model + unit (the GB/T 50500-2024 Appendix G adjustment table is listed accordingly); with no same specification, convert by the adjacent grade or grade price difference with records (marked "converted"); inconsistent measurement units are converted first (e.g., rebar in t vs kg/m using theoretical weight); missing items are filled by market inquiry (>=3 suppliers); when adjusting per price information, lock the specification caliber at contract signing via the adjustable main materials table (Appendix G.2.1) and match one-to-one at settlement; where the current issue lacks the corresponding specification, provisionally compute per the current price information and adjust later per actuals (Appendix A.2.2).
- ←
Railway estimate (budget) price adjustment rules: the labour/materials/plant three-line adjustment method and its place in the item-estimate procedure (TB 10801-2024 section 4.1, Table 2.6.2)
TB 10801-2024 clause 4.1.1: price adjustment means the reasonable adjustment of prices from the base period to the estimate (budget) compilation period, computed by the design organization when compiling and listed in the item estimate (budget). Clause 4.1.2 has three lines: labour cost differential = norm labour consumption (excluding labour inside machine-shifts) x (compilation-period composite labour rate − base-period composite labour rate); material price differential = norm consumption x (compilation-period price − base-period price) (water/electricity excluding machine-shift consumption; main materials per the clause-4.1.2-item-2 list); plant and small tools cost differential = norm machine-shift and instrument-shift consumptions x (compilation-period shift rate − base-period shift rate). Total differentials enter the item estimate's direct works costs (Table 2.6.2 items 6-9); price fluctuation provision (3.14) is separately computed per TB 10811 as a dynamic-investment reserve — do not confuse with price differentials.
- ←
Pricing rules for cross-region material procurement: purchase-origin price + freight compose the delivered price; adjustment per contract and the price-confirmation procedure
Budget compilation does not force a binary "project location vs purchase location": material budget price = (material original price + freight within price) x (1 + procurement-and-keeping rate), the purchase-origin price serving as the original price and freight reflecting the inter-region difference; multi-source procurement is weighted by supply share. Settlement adjustment follows the contract first; absent agreement, the base price is the published price information (government guidance prices) for the project location or the mutually confirmed price 28 days before the bid deadline, the benefit of regional price differences accrues to the contractor, and prices must be submitted to the employer for confirmation before purchase — silence is deemed acceptance.
- ←
Building a material published-price-information vs actual purchase-price comparison table: four-segment table structure, deviation analysis, and the four-party certification and sign-off process
The comparison table = base segment (name/specification precise to the grade, unit, work location and period) + price segment (published price information stating the issuing agency, period, and tax-inclusive/delivered basis; purchase price on the same basis, side by side) + analysis segment (deviation rate = (purchase price − published price information)/published price information × 100%, each deviation explained and checked against the contract risk band) + signature segment (applicant/supervision/employer signatures and seals). Based on the GB/T 51095-2015 Appendix E.0.4 enquiry (price verification) form, extended with "published price information (agency + period)" and "deviation rate" columns; process: ≥ 3 enquiries → comparison → supervision price verification → employer confirmation before purchase (failure to reply within the time limit deemed acceptance) → contract at the approved price → archive into the price library. The signed and sealed comparison table is the certified record of agreed material prices — a basis for preparing the settlement.
- ←
Railway 2024 quotas: budgeting self-built aggregate yards producing machine-made sand with combined plants (TB/T 10821-2024 Chapter 6 YY-70) and the unit-price composition of self-quarried aggregate
Machine-made sand uses Chapter 6 YY-70 of TB/T 10821-2024 (unit 100 m3 of finished aggregate; 2020 base 3,386.81 yuan/100 m3 — labor 270.66, plant 3,116.15, materials 0, raw feed separate). Chapter 6 is not a direct BOQ item: per the compilation measures 3.2.2 "material cost = sum of (quota consumption x material budget price)", it analyzes the self-quarried yard price (material original price) entering the material cost of concrete and other items. Self-quarried unit price: material budget price = (original price + freight-within-price) x (1 + procurement and custody rate) (TB 10801-2024 Clause 3.2.5); sand 4.47%, crushed stone (including ballast and medium/small cobbles) 3.45% (TB 10811-2024 Table 2.2.2); aggregate is Class A — base prices exclude freight, booked separately.
- ←
Railway 2024 quota: distinguishing surveyed-price materials from base-period-price materials — the Appendix A computer-code test and the main-material list (TB 10811/10801/10813-2024)
The sole test for surveyed-price vs base-period-price materials: check whether the material's computer code falls within Table A.0.1 of Appendix A of TB 10811-2024 "Railway capital construction design estimate (budget) fee quota". Within = main material: compilation-period price is exclusive of deductible input VAT and determined by the design organization's investigation, with price difference = quota-tabulated consumption x (compilation-period price − base-period price) listed as material price difference (TB 10801-2024 clause 4.1.2 item 2 sub-item 2)); outside = auxiliary material: base-period price used directly (TB/T 10813-2024, 2020 price level, exclusive of deductible input VAT), no survey, no compilation-period difference. Special cases: petrol/diesel compilation-period differences go into the construction-plant-use price difference; water and electricity are not on the surveyed list — their difference is computed separately as consumption x (compilation-period price − base-period price) (base prices: water 0.55 yuan/t, electricity 0.0.47 yuan/kWh).
- ←
Railway construction-installation single-item estimate calculation program (TB 10801-2024 Table 2.6.2): 16-step accumulation and percentage-rate base rules — labor + machinery in the base; materials / out-of-price freight / price differences / fill material out; VAT separately listed
The single-item estimate for cost of works (construction and installation) accumulates in 16 steps per TB 10801-2024, Table 2.6.2: quota direct works cost = (1)+(2)+(3) (base-period labour cost + base-period material cost + base-period plant and small tools cost) -> direct works cost = (4)+(5)+(9)+(10) (+ out-of-price freight and handling charges + price differences total + fill material) -> direct cost = (11)+(12)+(13) (+ preliminaries + special construction increases) -> single-item estimate value = (14)+(15) (+ on-costs). Only base-period labour cost plus base-period plant and small tools cost form the base to which percentage rates are applied: preliminaries = [(1)+(3)] x preliminaries rate, on-costs = [(1)+(3)] x on-costs rate; the exception is special construction increases, based on compilation-period labour cost + compilation-period plant and small tools cost. Base-period material cost, out-of-price freight and handling charges, price differences and fill material enter direct works cost only and never form the base to which percentage rates are applied. VAT is outside the single-item estimate procedure and is listed separately at the comprehensive/total estimate level as VAT = VAT on cost of works (construction and installation) + VAT on permanent equipment procurement cost + VAT on other costs.
- ←
Highway JTG 3830-2018 purchasing and custody charge rates for materials: steel 0.75%, fuel and explosives 3.26%, other materials 2.06%, purchased components 0.42%, commercial mixes exempt — and the basis for the norm-based material price for estimating
Per clause 3.1.2 of JTG 3830-2018 "Administrative compilation rules for estimates and budgets of highway construction projects", the purchasing and custody charge is calculated on the combined base "material price at source + freight and handling charges + off-site transport wastage" multiplied by the rate: steel 0.75%; fuel and explosive materials 3.26%; other materials 2.06%; purchased components, products and semi-products 0.42%; commercial cement concrete, asphalt mixes and all types of stabilized-soil mixes carry no purchasing and custody charge. Material price for estimating = (material price at source + freight and handling charges) x (1 + off-site transport wastage rate) x (1 + purchasing and custody charge rate).
- ←
Whether published price information / base-period prices include the procurement and keeping fee: caliber determination (railway base-period prices fully include, most provincial price information excludes, highway adds separately)
The procurement and keeping fee is added by rate and not merged into the material original price. Railway base-period prices (TB/T 10813-2024), Classes A/B/C, all include the procurement and keeping fee (rates per TB 10811-2024 Table 2.2.2); the price information published by most provinces and cities uses the market-price caliber and excludes the fee, so it must be added separately when compiling budgets; a few publish "comprehensive prices including the fee", which must not be double-counted. Highway JTG 3830-2018 adds the fee separately on the basis of (original price + freight and miscellaneous charges + off-site transport loss). Always read the current issue's publication notes before use.
- ←
Price-taking rules when one material has multiple published prices / original prices: weighted average by supply quantity at compilation, three agreed methods at adjustment, unified caliber
When one material has multiple prices, take prices by scenario: at compilation, original prices from multiple origins/supply channels are determined by weighted average per supply proportions (TB 10811-2024 Clause 2.2.1 — neither the high nor the low); at adjustment, multiple market prices within the same measurement period use one of the three contractually agreed methods and its priority — arithmetic mean, weighted mean with completed quantities, or the price of the main-consumption construction period (GB/T 50500-2024 Appendix A.2.3); for multi-agency publications with no agreement, follow the caliber of the agency at the project location; before taking prices, unify the tax-inclusive/exclusive, delivered/ex-factory, and specification-grade calibers; market prices, published prices, and manufacturer quotations are used by classified channels and strictly never mixed.
- ←
Railway 2024 quota subgrade purchased-fill material fee: when chargeable, how the fill price is built up, and the caliber distinction from material costs (TB 10801-2024 clause 3.5 / TB 10811-2024 clause 2.5.1)
The fill-material fee is charged only for filling materials obtained by **purchase** (soil, rock, permeable material, mineral material etc. not treated as materials), built up as "fill fee = sum(fill consumptions x fill price)" (TB 10801-2024 clause 3.5.2); the fill price is exclusive of deductible input VAT and is determined by investigation and analysis by the design organization (TB 10811-2024 clause 2.5.1) — it does not enter the material library, carries no purchasing and custody charges, and is not subject to price adjustment (for fluctuation). Self-excavated reuse (cut-to-fill) carries no fill fee; land-related costs of borrowing from temporarily occupied land go under Chapter 1 temporary land-use fees. This differs sharply from the clause-3.2 works material cost (norm-based material price for estimating = (material price at source + freight and handling included in the material price) x (1 + purchasing and custody rate)); in practice the test is "whether it appears in the quota consumption table".
- ←
Overview of the full-chain use rules for construction cost published price information: nature, price calibers, stage-by-stage pricing, and frequent misconceptions
Published price information means reference guide prices issued by cost management agencies, running through the whole chain "price-limit compilation - bid verification - adjustment base - settlement fallback". Five iron rules: contract agreement first; caliber unification (tax-inclusive/exclusive, delivered/ex-factory, procurement-keeping fee); period alignment (base price locked 28 days before the bid deadline, measurement price matched to the measurement period); adjust only beyond band (±5% if not agreed); confirmation with records (submit to the employer before purchase, silence deemed acceptance).