Railway construction-installation single-item estimate calculation program (TB 10801-2024 Table 2.6.2): 16-step accumulation and percentage-rate base rules — labor + machinery in the base; materials / out-of-price freight / price differences / fill material out; VAT separately listed
The single-item estimate for cost of works (construction and installation) accumulates in 16 steps per TB 10801-2024, Table 2.6.2: quota direct works cost = (1)+(2)+(3) (base-period labour cost + base-period material cost + base-period plant and small tools cost) -> direct works cost = (4)+(5)+(9)+(10) (+ out-of-price freight and handling charges + price differences total + fill material) -> direct cost = (11)+(12)+(13) (+ preliminaries + special construction increases) -> single-item estimate value = (14)+(15) (+ on-costs). Only base-period labour cost plus base-period plant and small tools cost form the base to which percentage rates are applied: preliminaries = [(1)+(3)] x preliminaries rate, on-costs = [(1)+(3)] x on-costs rate; the exception is special construction increases, based on compilation-period labour cost + compilation-period plant and small tools cost. Base-period material cost, out-of-price freight and handling charges, price differences and fill material enter direct works cost only and never form the base to which percentage rates are applied. VAT is outside the single-item estimate procedure and is listed separately at the comprehensive/total estimate level as VAT = VAT on cost of works (construction and installation) + VAT on permanent equipment procurement cost + VAT on other costs.
Applicable Codes
- TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第2.6节(图2.6.1、Table 2.6.2、Table 2.6.3)、第3.4节、第3.12条
- TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works
Topic Positioning
This card explains the single-item estimate calculation procedure for cost of works (construction and installation) set out in Section 2.6 of TB 10801-2024, Table 2.6.2, 16 steps: the order in which costs are accumulated, which items form the base to which percentage rates are applied, which items feed only into direct works cost, and why VAT lies outside the single-item estimate procedure. It applies to compiling and reviewing design estimates for railway capital works.
Core Conclusions
1. Single-item estimate procedure for cost of works (construction and installation) (TB 10801-2024, Table 2.6.2, as published)
| No. | Cost item | Calculation |
|---|---|---|
| 1 | Base-period labour cost | Per design quantities and the base-period prices adopted |
| 2 | Base-period material cost | Per design quantities and the base-period prices adopted |
| 3 | Base-period plant and small tools cost | Per design quantities and the base-period prices adopted |
| 4 | Quota direct works cost | (1)+(2)+(3) |
| 5 | Out-of-price freight and handling charges | Freight and handling charges requiring separate listing, calculated per the material supply scheme in the project execution plan and the relevant provisions of this code |
| 6 | Labour cost differential | Base-period to compilation-period differential per the relevant provisions of this code |
| 7 | Material cost differential | Base-period to compilation-period differential per the relevant provisions of this code |
| 8 | Plant and small tools cost differential | Base-period to compilation-period differential per the relevant provisions of this code |
| 9 | Price differences total | (6)+(7)+(8) |
| 10 | Fill material | Per design quantities and the surveyed prices adopted |
| 11 | Direct works cost | (4)+(5)+(9)+(10) |
| 12 | Preliminaries | [(1)+(3)] x preliminaries rate |
| 13 | Special construction increases | Calculated on the corresponding compilation-period labour cost and compilation-period plant and small tools cost as the base |
| 14 | Direct cost | (11)+(12)+(13) |
| 15 | On-costs | [(1)+(3)] x on-costs rate |
| 16 | Single-item estimate value | (14)+(15) |
2. What enters the base and what does not (rules for the base to which percentage rates are applied)
- Only base-period labour cost (1) + base-period plant and small tools cost (3) form the base: both preliminaries (item 12) and on-costs (item 15) are [(1)+(3)] x rate. The base is locked to base-period prices and is unaffected by compilation-period differentials.
- Special construction increases (item 13) are the exception: the base is likewise labour + plant, but at compilation-period labour cost and compilation-period plant and small tools cost, unlike the base-period base used for preliminaries and on-costs; do not confuse the two.
- Items entering no base: base-period material cost (2) (accumulated only in item 4 - the key feature of the railway basis: no material cost in the base), out-of-price freight and handling charges (5), price differences (9) and fill material (10) enter only item 11 (direct works cost); preliminaries (12) and on-costs (15) are themselves the result of applying rates and enter the accumulation (into items 14 and 16 respectively) and do not serve as the base for other costs.
3. VAT is outside the single-item estimate procedure
Item 16, single-item estimate value = (14)+(15), is the end of the procedure; VAT does not appear within it. VAT is a separately listed cost (TB 10801-2024, clause 3.12): VAT = VAT on cost of works (construction and installation) + VAT on permanent equipment procurement cost + VAT on other costs, calculated per TB 10811 and aggregated at the comprehensive estimate/total estimate level. In the cost composition (Fig. 2.6.1), VAT sits at the static investment level: static investment = cost of works (construction and installation) + permanent equipment procurement cost + other costs + VAT; dynamic investment = basic (physical) contingency + price fluctuation provision + construction-period investment loan interest.
4. Companion definitions and formulas
- Out-of-price freight and handling charges (clause 3.4.1): material freight and handling charges that must be listed separately outside material cost when compiling a single-item estimate, per design needs; comprising transport, loading/unloading and other related transport charges incurred from the designated delivery point to site, plus purchasing and custody charges calculated on the sum of those charges to simplify estimate preparation.
- Formula (clause 3.4.2): out-of-price freight and handling charges = sum(transport + loading/unloading + other related transport charges) x (1 + purchasing and custody rate); unit transport prices, loading/unloading prices and the purchasing and custody rate are per TB 10811.
- Equipment single-item estimate procedure (Table 2.6.3): equipment cost (per design equipment quantities and the equipment original prices adopted) -> equipment freight and handling charges = (1) x freight and handling rate -> single-item estimate value = (1)+(2).
One-line memory: the base takes only base-period labour cost + base-period plant and small tools cost (special construction increases being the exception, at compilation-period prices); material cost, out-of-price freight and handling charges, price differences and fill material feed only into direct works cost accumulation and never form the base; VAT is outside the single-item estimate procedure and is calculated separately at the comprehensive/total estimate level.
Applicable Boundaries
- Applies to compiling and reviewing single-item estimates for cost of works (construction and installation) in design estimates for railway capital works prepared under TB 10801-2024; rate values (preliminaries rate, on-costs rate, equipment freight and handling rate, etc.) are given in TB 10811-2024 and are not listed here.
- Preliminaries, on-costs and special construction increases all take labour + plant as the base, but the first two use base-period prices while special construction increases use compilation-period prices; the bases differ and must be distinguished when applying them.
- The railway base excludes material cost, unlike other sectors (e.g. the highway JTG 3830 system); check the relevant sector's estimate preparation rules before applying across sectors.
- VAT is outside the single-item estimate procedure; adding VAT at the single-item estimate level is double counting. Input VAT treatment is linked to the norm-based material price for estimating basis (general taxation excludes creditable input VAT) - see the card on the norm-based material price for estimating.
Further Reading
- See TB 10801-2024 Section 2.6: Fig. 2.6.1 cost composition of the design estimate; Table 2.6.2 single-item estimate procedure for cost of works (construction and installation); Table 2.6.3 equipment single-item estimate procedure.
- Rules for out-of-price freight and handling charges in Section 3.4 (3.4.3 unit transport/loading prices and the purchasing and custody rate per TB 10811; 3.4.4 bridge and tunnel works per work-site material supply scheme, subgrade appurtenances and other bridge/tunnel works by weighted average per single-item estimate unit, culverts and track by the supply scheme with equal main-line material quantities to derive the average haul; long-rail supply-related costs for single rails 200 m and above from the rail welding base to the track-laying base, covering rack usage/maintenance, transhipment, loading, pickup and delivery of cars, locomotive use within the welding base and management costs; used-rail freight and handling charges per design rail type).
- The basis for separate listing of VAT is clause 3.12 (VAT = VAT on cost of works (construction and installation) + VAT on permanent equipment procurement cost + VAT on other costs, calculated per TB 10811).
- Companion knowledge: composition and rate tables of preliminaries/on-costs, freight rate calculation rules for out-of-price freight and handling charges, aggregation of the norm-based material price for estimating, base-period price classes A/B/C, and the quota system and base-period price mechanism - see the cards referenced by this one.