cost of works (construction and installation)
- 01
Why the 'statutory withdrawal coefficient' of the work safety levy and the fee rates of pricing bases differ: the hierarchy of Work Safety Law article 23, the withdrawal standards of Cai Zi [2022] No. 136, and the differences of base, content and function across sector fee schedules
Work Safety Law (2021 revision) article 23 itself sets no percentage - o…
《中华人民共和国安全生产法》(2021修正,主席令第88号)第二十三条《企业安全生产费用提取和使用管理办法》(财资〔2022〕136号)第十七条 http://www.mof.gov.cn/gkml/caizhengwengao/wg2022/wg202212/202304/t20230407_3877736.htm财资〔2022〕136号 办法全文附件 https://www.mof.gov.cn/gkml/caizhengwengao/wg2022/wg202212/202304/P020230407569760184890.docx2026-11-12 - 02
Computation procedure and cost make-up of item-wise estimates (budgets) for railway works of construction and installation, including the equipment item-wise procedure - TB 10801-2024 Section 2.6 Tables 2.6.2 and 2.6.3
Per TB 10801-2024 Article 2.6.2 Table 2.6.2, the item-wise estimate (bud…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第2.6节(Table 2.6.2、Table 2.6.3)TB 10811-2024 铁路基本建设工程设计概(预)算费用定额2026-10-11 - 03
Highway estimate/budget project-table compilation rules: ten items of Part 1 cost of works (temporary works through special fees) and the part-item-sub-item-section-detail five-level coding (JTG 3830-2018 Section 2.4, Appendix B)
Per Clause 2.4.2 Figure 2.4.2 of JTG 3830-2018 (see Appendix B Table B.0…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第2.4节、App. B2026-09-25 - 04
Highway works estimate/budget works insurance fee rules: base = construction-installation cost (excluding equipment), rate 0.4% (JTG 3830-2018 clause 3.3.9)
Per clause 3.3.9 of JTG 3830-2018 "Measures for compiling estimates and…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.3.9条JTG 3830-2018 综表362026-09-25 - 05
Highway 2018 quota-norm system — taxes and duties: VAT output tax listed separately; taxes and duties = (direct cost + permanent equipment procurement cost + preliminaries + overheads (company and site) + statutory levies and fees + profit) × construction VAT rate (JTG 3830-2018 clause 3.1.10)
Per clause 3.1.10 of JTG 3830-2018 "Administrative Compilation Rules for…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.10条(税金定义与公式)、第3.1.1条(价税分离)财政部 税务总局 海关总署公告2019年第39号(建筑业增值税税率9%)2026-09-25 - 06
Highway JTG 3830-2018 Table 3.6.1 computation sequence for the cost of works (construction and installation): how the 8 components add up, the 7.42% profit, and the two different tax bases
Per Clause 3.6.1, Table 3.6.1 of JTG 3830-2018 (computation procedure an…
JTG 3830-2018 公路工程建设项目概算预算编制办法JTG/T 3832—2018 公路工程预算定额JTG/T 3833 公路工程机械台班费用定额2026-09-25 - 07
Highway 2018 quota norms system: composition of the cost of works (construction and installation) — 8 cost items, separation of net price and VAT, and bases to which percentage rates are applied (JTG 3830-2018 section 3.1)
Per JTG 3830-2018 clause 3.1.1, highway cost of works (construction and…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1节JTG/T 3832-2018 · Budget Quota of Highway Engineering 附录四JTG/T 3833 · Quota for Shift Costs of Highway Engineering Machinery2026-09-25 - 08
Railway construction-installation single-item estimate calculation program (TB 10801-2024 Table 2.6.2): 16-step accumulation and percentage-rate base rules — labor + machinery in the base; materials / out-of-price freight / price differences / fill material out; VAT separately listed
The single-item estimate for cost of works (construction and installatio…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第2.6节(图2.6.1、Table 2.6.2、Table 2.6.3)、第3.4节、第3.12条TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works2026-09-25 - 09
Three bases for the composition of the construction price: cost elements, BOQ-based pricing, and final-account listing
The construction price (cost of works (construction and installation)) h…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准2026-09-25 - 10
Highway estimate (budget) work-safety fee: base = construction-installation costs excluding the fee itself, rate >=1.5% (JTG 3830-2018 clause 3.1.11), fee content and management requirements
Highway work-safety fee = construction-installation works costs (excludi…
《公路工程建设项目概算预算编制办法》JTG 3830-2018 第 3.1.11 条《公路水运工程安全生产监督管理办法》(交通运输部令 2017 年第 25 号)第二十一条2026-09-25