Highway estimate/budget project-table compilation rules: ten items of Part 1 cost of works (temporary works through special fees) and the part-item-sub-item-section-detail five-level coding (JTG 3830-2018 Section 2.4, Appendix B)
Per Clause 2.4.2 Figure 2.4.2 of JTG 3830-2018 (see Appendix B Table B.0.1), Part 1 cost of works divides into ten items: (1) temporary works; (2) subgrade works; (3) pavement works; (4) bridge and culvert works; (5) tunnel works; (6) intersection works; (7) traffic engineering and route facilities; (8) greening and environmental protection works; (9) other works; (10) special fees ((1) construction site development fee (2) work safety fee); item numbering uses the five levels part(1 digit)-item(2)-sub-item(2)-section(2)-detail(2), the ten items being numbered 101-110.
Applicable Codes
- JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第2.4节、App. B
Topic Positioning
This card covers Section 2.4 "estimate and budget items and coding rules" of the "Measures for compiling estimates and budgets of highway engineering construction projects" (JTG 3830-2018): the five-part framework of the project table, the ten "items" of Part 1 cost of works, and the part-item-sub-item-section-detail five-level numbering (Appendix B, Table B.0.1).
Core Conclusions
Per Clause 2.4.2 Figure 2.4.2 (details in Appendix B), the project table has five parts: Part 1 cost of works; Part 2 land use and demolition compensation cost; Part 3 other construction costs; Part 4 reserve funds; Part 5 construction-period loan interest.
Part 1 cost of works divides into ten items:
- Item 1 temporary works
- Item 2 subgrade works
- Item 3 pavement works
- Item 4 bridge and culvert works
- Item 5 tunnel works
- Item 6 intersection works
- Item 7 traffic engineering and route facilities
- Item 8 greening and environmental protection works
- Item 9 other works
- Item 10 special fees (1. construction site development fee; 2. work safety fee)
Coding rule (Clause 2.4.3, verbatim): "Item numbers consist of part (1 digit), item (2 digits), sub-item (2 digits), section (2 digits), detail (2 digits), expanded layer by layer; see Appendix B." The ten items are numbered 101-110; unified item numbering is mandatory when compiling.
Compilation rule (Clause 2.4.1, verbatim): "Estimates and budgets shall be compiled per the sequence and contents of the project table. Where the works and cost items actually arising do not fully match the table, the serial numbers and contents of parts 1-5 and of the 'items' remain unchanged; sub-items below 'item' keep their numbers and contents when cited; missing sub-item content may be added nearby as needed, arranged in table order at the level actually appearing, without keeping the numbers of missing items below 'item'." That is, the five parts and the item-level numbers are immutable; missing items may be added nearby but no gaps are kept.
Applicable Boundaries
- Applies to highway estimate and budget compilation (JTG 3830-2018, effective 1 May 2019, replacing JTG B06-2007 "Measures for compiling estimates and budgets of highway capital construction projects").
- The official table names are "bridge and culvert works" and "traffic engineering and route facilities" — do not abbreviate to "bridge works" or "traffic works"; list items by their official names.
- Items 1, 2, 3, 4, 5, 7, 8, etc., each carry sub-tables of works items (subgrade, pavement, culverts, bridges, tunnels, traffic safety facilities, tunnel electromechanics, greening and environmental protection, etc.); expand level by level per the sub-tables; units and main work contents are in Appendix B Table B.0.1.
- This card covers only the framework and coding; computation methods of each fee (e.g., rates of the construction site development fee and work safety fee within special fees) are in the referenced cards.
Further Reading
- See JTG 3830-2018 Section 2.4 (2.4.1-2.4.3) and Appendix B "estimate and budget project table" (Table B.0.1, with each item number, unit, main work content, and notes).
- Charging rules are in Chapter 3 of the same measures (3.1 cost of works composition and charging, 3.3 other construction costs), with the Ministry of Transport's companion highway cost-management documents. Desktop evidence is OCR text of Appendix B — a few characters may be misread; the official standard text prevails.