Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Highway estimate (budget) work-safety fee: base = construction-installation costs excluding the fee itself, rate >=1.5% (JTG 3830-2018 clause 3.1.11), fee content and management requirements

Highway work-safety fee = construction-installation works costs (excluding the work-safety fee itself) x work-safety rate, the rate at not less than 1.5% (JTG 3830-2018 clause 3.1.11); it is one of the 'special costs' in the 8-item composition, covering eight categories of safety expenditure; per Article 21 of Ministry of Transport Order No. 25 of 2017, it must be separately accrued in bid prices and not treated as a competitive price item, reviewed and signed off by the supervising engineer, and, with the employer's consent, disbursed against actual costs within the project construction cost — diversion strictly prohibited. Comparison: railway (TB 10811-2024) books 3.0% of construction-installation costs — the two bases differ, so do not mix them.

Applicable Codes

  • 《公路工程建设项目概算预算编制办法》JTG 3830-2018 第 3.1.11 条
  • 《公路水运工程安全生产监督管理办法》(交通运输部令 2017 年第 25 号)第二十一条

Topic Positioning

The rules for charging the 'work-safety fee' in highway estimate and budget compilation: the base and rate, the scope of fee content, and the non-competitive and earmarked-use management requirements, per JTG 3830-2018 'Measures for compiling estimates and budgets of highway construction projects' and the 'Measures for the work safety supervision and administration of highway and waterway works' (Ministry of Transport Order No. 25 of 2017).

Core Conclusions

  1. Classification: per clause 3.1.1, highway construction-installation costs = direct costs + permanent equipment procurement cost + preliminaries + overheads (company and site) + statutory levies and fees + profit + taxes and duties + special costs (8 items); the work-safety fee sits alongside the site construction fee under 'special costs' (clause 3.1.11).

  2. Formula (clause 3.1.11 verbatim): the work-safety fee is computed as construction-installation works costs (excluding the work-safety fee itself) x the work-safety fee rate, the rate taken at not less than 1.5%. That is: work-safety fee = construction-installation works costs (deducting the fee itself) x 1.5% (the floor; in compilation, 1.5% is usually applied directly, and it may be raised to reflect actual project risk).

  3. Content (clause 3.1.11 verbatim): costs of improving, upgrading and maintaining safety facilities and equipment; equipping, maintaining and servicing emergency-rescue equipment; assessing and rectifying major hazard installations and accident potentials; work-safety inspections, evaluations and consulting; providing and renewing on-site personal protective equipment for the workforce; work-safety publicity, education and training; inspection and testing of safety facilities and special equipment; construction-safety risk assessment, emergency drills and related work; and other costs directly related to work safety.

  4. Management requirements (Article 21 of MOT Order No. 25 of 2017, verbatim): when compiling the tender documents and the project estimate/budget, the employer shall determine the work-safety costs needed to secure a safe working environment and safe construction measures, and they shall not be lower than the state-prescribed standard; in their tender price, contractors shall include the work-safety fee and accrue it separately, and it shall not be treated as a competitive price item; the work-safety costs shall, after review and sign-off by the supervising engineer and with the employer's consent, be disbursed against actual costs within the project construction cost, and diversion is strictly prohibited.

  5. Sector comparison: railway works book work-safety fees at 3.0% of construction-installation costs (TB 10811-2024), while highway works use not less than 1.5% — the two bases differ, so do not mix them.

Applicable Boundaries

  • Applies to the compilation of estimates and budgets for highway construction projects (JTG 3830-2018 pricing system); it does not apply to other sectors' bases, such as railway (3.0%) or building and municipal works, where mandatory health, safety and environmental (HSE) provisions are priced at rates set by state and provincial rules.
  • The base must exclude the fee itself ('excluding the work-safety fee itself') to avoid circular charging; the fee must likewise not be double-listed in other parts of the estimate (budget).
  • 1.5% is a floor, not a fixed value; it may be raised to reflect project risk.
  • The work-safety fee is non-competitive: it must be accrued separately in the tender price and must not be treated as a competitive price item.

Further Reading

  • JTG 3830-2018, clause 3.1.11 (special costs: site construction fee + work-safety fee), Table 3.1.11 (site construction fee rate table), clause 3.1.1 (the 8-item composition of construction-installation costs).
  • 'Measures for the work safety supervision and administration of highway and waterway works' (Ministry of Transport Order No. 25 of 2017), Article 21 (determination, separate accrual, disbursement against actual costs, and prohibition of diversion).
  • For comparison: railway 'Measures for compiling estimates and budgets of railway works' TB 10811-2024, clause 2.11.9 (work-safety fee booked at 3.0% of construction-installation costs).

Keywords

Cited By