Consumption basis at the highway investment-estimation stage: "Highway Works Estimation Indicators" JTG/T 3821 (JTG 3820-2018 clause 2.1.1 labor/material/plant cost computation, clause 2.2.1 basis list)
In highway investment estimation, the labor, material/equipment and plant-shift consumption follows the current "Highway Works Estimation Indicators" JTG/T 3821 (2018 edition, published with JTG 3820-2018 by MOT Announcement No. 86, effective 1 May 2019). Per JTG 3820-2018 clause 2.1.1, labor/material/plant costs = indicator consumption x project-location workday labor, material budget and plant shift prices at compilation time; the clause 2.2.1 basis list also includes the estimate quota JTG/T 3831, budget quota JTG/T 3832 and plant shift fee quota JTG/T 3833.
Applicable Codes
- JTG 3820—2018 · Measure for Compilation of Investment Estimates of Highway Construction Projects
- JTG/T 3821 · Estimate Indicators of Highway Engineering (2018版)
- JTG/T 3831 · Estimate Quota of Highway Engineering
- JTG/T 3832 · Budget Quota of Highway Engineering
- JTG/T 3833 · Quota for Shift Costs of Highway Engineering Machinery
- 交通运输部公告第86号(2019年05月01日实施)
Topic Positioning
Answers which estimation indicators govern labor, material/equipment and plant-shift consumption in highway investment estimation: the "Highway Works Estimation Indicators" JTG/T 3821 (2018 edition), with the labor/material/plant cost computation (clause 2.1.1), the full basis list (clause 2.2.1) and document composition (clause 2.3) of JTG 3820-2018 — for compiling and reviewing investment estimates (project proposal, feasibility study stages) of highway new-build and rebuild (expansion) projects.
Core Conclusions
Consumption basis: JTG/T 3821 (2018 edition). JTG 3820-2018, JTG/T 3821, JTG/T 3831, JTG/T 3832 and JTG/T 3833 were published together by MOT Announcement No. 86, effective 1 May 2019, and are current; the old "Measures for compiling investment estimates of highway capital construction projects" and "Highway Works Estimation Indicators" (Jiao Gong Lu Fa [1996] No. 611) are superseded — the 2018 editions must be used.
Labor/material/plant cost computation (clause 2.1.1, original text): "When compiling investment estimates, compute the labor, material and plant costs of the project from the labor, material/equipment and plant-shift consumption specified in the current Highway Works Estimation Indicators (JTG/T 3821), at the project-location workday labor unit prices, material budget prices and plant shift unit prices at the estimation compilation time fixed by these measures, and compute the various fees per these measures." I.e. costs = indicator consumption x project-location prices at compilation (workday labor / material budget / plant shift prices) — the same pricing logic as the estimate/budget stage, differing only in consumption from estimation indicators rather than quotas.
Estimation basis (clause 2.2.1, 8 items): (1) national laws and regulations; (2) the current JTG/T 3821, JTG/T 3831, JTG/T 3832, JTG/T 3833 and these measures; (3) supplementary provisions and quotas of the provincial transport authority at the project location; (4) design documents such as project-proposal or feasibility-study drawings and implementation schemes; (5) approved project proposal and related materials; (6) local labor, material/equipment and plant prices; (7) relevant contracts and agreements; (8) other relevant materials.
Scope and general provisions: clause 1.0.2 "these measures apply to compiling investment estimates of new-build and rebuild (expansion) highway projects"; clause 1.0.3 the investment estimate is an important part of the project proposal and feasibility study report; clause 1.0.5 multi-section estimates must unify principles and summarize into the total project investment estimate — connecting lines, branch lines and larger-scale auxiliary/connecting works needing separate cost presentation are compiled separately and summarized into the total; clause 1.0.6 specialty works not covered may execute the corresponding industry quotas; clause 1.0.7 provincial authorities may supplement; clause 1.0.8 compilation must also comply with current national and industry standards.
Document composition (clause 2.3): estimation documents consist of cover, title page, contents, explanatory notes and all computation tables; cover and title page follow the current "Measures for compiling feasibility study reports of highway construction projects", the title page's second page and contents per appendix A of these measures.
Applicable Boundaries
- Applies only to highway investment estimation (project proposal, feasibility study stages); design estimates use JTG/T 3831 and construction-drawing budgets JTG/T 3832 — estimation indicators are not for estimate/budget stages, never mix.
- Prices are "project-location at compilation time" — results vary with location and time; this card carries no rate values or price data; standards and indicator consumption follow the current JTG/T 3821 and companion indicators.
- Specialty works beyond the indicators execute the corresponding industry quotas per clause 1.0.6; provincial supplements must be adopted together.
- Version pairing: JTG 3820-2018 pairs with the 2018 indicators/quotas — never mix with the 1996 edition (Jiao Gong Lu Fa [1996] No. 611).
Further Reading
- JTG 3820-2018: clauses 1.0.1-1.0.8 (general), section 2.1 (clause 2.1.1 labor/material/plant costs), section 2.2 (clause 2.2.1 basis), section 2.3 (document composition), appendix A (title page and contents formats).
- JTG/T 3821 (2018 edition) — consumption tables of each indicator item.
- Companion quota system: JTG/T 3831, JTG/T 3832, JTG/T 3833.
- Publication: MOT Announcement No. 86 (effective 1 May 2019).
- Estimate/budget stage comparison: JTG 3830-2018.