Highway investment estimate — permanent equipment procurement cost at the project-proposal stage: by the Appendix C rate on the norm-based cost of works (excluding special fees and itself) (JTG 3820-2018 Clause 3.1.3)

Per Clause 3.1.3 item 1 of JTG 3820-2018 "Measures for Compiling Investment Estimates of Highway Works Construction Projects", at the project-proposal stage: permanent equipment procurement cost = norm-based cost of works (excluding special fees and itself) x the Appendix C rate; the permanent equipment procurement cost attracts no preliminaries or overheads (company and site). At the feasibility-study stage the list method applies instead (equipment quantity x equipment budget price, incl. original price / freight and handling charges / transport insurance / purchasing and custody charges) or the reference values of Appendix I of the "Highway Works Estimation Indicators" JTG/T 3821-2018.

Applicable Codes

  • JTG 3820-2018 · Measure for Compilation of Investment Estimates of Highway Construction Projects 第3.1.3条
  • JTG/T 3821—2018 · Estimate Indicators of Highway Engineering 附录一
  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.3条

Topic Positioning

This card covers the computation rule for permanent equipment procurement cost in highway investment estimates, focusing on the "rate method" of the project-proposal stage (Clause 3.1.3 item 1, JTG 3820-2018 "Measures for Compiling Investment Estimates of Highway Works Construction Projects"), contrasted with the list/reference-value methods of the feasibility-study stage, to prevent cross-stage misuse of bases.

Core Conclusions

Per Clause 3.1.3 of JTG 3820-2018:

  • Definition: the permanent equipment procurement cost covers equipment forming fixed assets that is purchased to meet the needs of initial operation and management of the highway, and equipment below the fixed-asset threshold that the design expressly lists in the equipment schedule — including ferry equipment; power equipment for tunnel lighting, fire protection and ventilation; and toll, monitoring, communication, road-network operation monitoring, emergency-response, travel-service, power supply/distribution and lighting equipment.
  • Project-proposal stage (item 1): "the permanent equipment procurement cost is calculated by the rates specified in Appendix C of these Measures, on the base of the norm-based cost of works (excluding special fees and itself)", i.e. permanent equipment procurement cost = norm-based cost of works (excluding special fees and itself) x the Appendix C rate.
  • Base definition: norm-based cost of works (Clause 3.1.1) = norm-based direct cost + 40% of the norm-based permanent equipment procurement cost + preliminaries + overheads (company and site) + statutory fees + profit + tax + special fees; "excluding itself" means removing the norm-based permanent equipment procurement cost component contained in it, so as to prevent circular charging.
  • Charging restriction: the filling notes to the permanent equipment procurement cost computation form state expressly that "the permanent equipment procurement cost attracts no preliminaries or overheads (company and site)".
  • Feasibility-study stage (item 2 — do not mix with the project-proposal stage): (1) where the design can produce an equipment procurement list, compute by quantity x equipment budget price; the permanent equipment procurement cost covers the equipment original price, freight and handling charges, transport insurance and purchasing and custody charges, with taxes and levies calculated per the requirements of the relevant authorities at the time of compilation; equipment requiring installation is given its installation cost per the relevant provisions for the cost of works; the criterion for dividing equipment from materials is given in Appendix D of these Measures. (2) where the design cannot produce a list, use the permanent equipment procurement cost reference values in Appendix I of the "Highway Works Estimation Indicators" (JTG/T 3821-2018).

Applicable Boundaries

  • Applies only to the investment-estimate stage (project proposal / feasibility study); at the estimate (概算) and budget (预算) stages the permanent equipment procurement cost is itemised per Clause 3.1.3 of JTG 3830-2018 as "equipment original price + freight and handling charges + transport insurance + purchasing and custody charges" — the two must not be mixed.
  • The specific values of the Appendix C rate table must be taken from the original Appendix C of JTG 3820-2018 — this card's evidence contains no rate values, and none may be invented.
  • At the feasibility-study stage, the list method first requires the Appendix D equipment/material division to decide whether the item is included.
  • Jiao Gong Lu Fa [1996] No. 611 "Measures for Compiling Investment Estimates of Highway Capital Construction Projects" has been superseded and serves only as a historical comparison.

Further Reading

  • See Clauses 3.1.1 and 3.1.3 of JTG 3820-2018, Appendix C (rates), Appendix D (equipment/material division); and the "permanent equipment procurement cost computation form" in the appendix tables of those Measures together with its filling notes (which state that "the permanent equipment procurement cost attracts no preliminaries or overheads (company and site)").
  • Where no list is available at the feasibility-study stage, use the permanent equipment procurement cost reference values in Appendix I of the "Highway Works Estimation Indicators" JTG/T 3821-2018.
  • For the estimate/budget stage basis, compare Clause 3.1.3 of JTG 3830-2018.