Highway 2018 quota norms system: composition of the cost of works (construction and installation) — 8 cost items, separation of net price and VAT, and bases to which percentage rates are applied (JTG 3830-2018 section 3.1)

Per JTG 3830-2018 clause 3.1.1, highway cost of works (construction and installation) = direct costs + permanent equipment procurement cost + preliminaries + overheads (company and site) + statutory levies and fees + profit + taxes and duties (VAT under the current standard) + special costs (8 items); except special costs, all follow the separation of net price and VAT rule, computed at prices (percentage rates) excluding deductible input VAT. Norm-based cost of works = norm-based direct cost + 40% of norm-based permanent equipment procurement cost + preliminaries + overheads (company and site) + statutory levies and fees + profit + taxes and duties + special costs. Bases to which percentage rates are applied (Form 08): preliminaries and overheads (company and site) on the sum of norm-based labour cost and norm-based plant cost, or norm-based direct cost; statutory levies and fees on labour cost; profit on (norm-based direct cost + preliminaries + overheads (company and site)); taxes and duties on (direct costs + preliminaries + overheads (company and site) + statutory levies and fees + profit).

Applicable Codes

  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1节
  • JTG/T 3832-2018 · Budget Quota of Highway Engineering 附录四
  • JTG/T 3833 · Quota for Shift Costs of Highway Engineering Machinery

Topic Positioning

Composition, pricing rules and bases to which percentage rates are applied for highway cost of works (construction and installation) under the 2018 quota norms system, per section 3.1 of JTG 3830-2018 'Administrative Compilation Rules for Estimates and Budgets of Highway Construction Projects'.

Core Conclusions

1. Composition (clause 3.1.1, 8 items): the original text — 'The cost of works (construction and installation) comprises direct costs, permanent equipment procurement cost, preliminaries, overheads (company and site), statutory levies and fees, profit, taxes and duties, and special costs', i.e. cost of works (construction and installation) = direct costs + permanent equipment procurement cost + preliminaries + overheads (company and site) + statutory levies and fees + profit + taxes and duties + special costs.

2. Pricing rules (clause 3.1.1):

  1. Separation of net price and VAT: except special costs, all items follow the 'separation of net price and VAT' rule — every cost is computed at prices (percentage rates) excluding deductible input VAT, with VAT rates for specific factor prices per the finance/tax authorities.
  2. Norm-based basis (for fee bases and summary tables): norm-based cost of works comprises norm-based direct cost, 40% of norm-based permanent equipment procurement cost, preliminaries, overheads (company and site), statutory levies and fees, profit, taxes and duties and special costs; norm-based direct cost comprises norm-based labour cost, norm-based material cost and norm-based plant cost. Norm-based labour/material/plant/equipment costs are taken at base prices per Appendix IV 'Norm-Based Labour, Material and Equipment Unit-Price Table' of the 'Highway Works Budget Quota Manual' (JTG/T 3832-2018) and the current 'Highway Works Plant Rate Norms per Machine-Shift' (JTG/T 3833).

3. Direct costs (clause 3.1.2): direct costs = labour cost + material cost + construction plant cost.

  • Labour cost: labour-days from the preliminary estimate/budget quota norms x all-in daily labour rate; the daily labour rate is set, published and dynamically adjusted by provincial transport authorities, and serves only as the basis for compiling preliminary estimates/budgets, not for actual wage payment.
  • Material cost: calculated at the material price at the works location. Norm-based material price for estimating = (material price at source (ex-works / ex-yard) + freight and handling charges) x (1 + off-site transport wastage rate) x (1 + purchasing and custody charges percentage rate) - recoverable packaging value. Material price at source: purchased materials (referring to prices published by the regional transport authority and surveyed market prices) and self-quarried materials (sand, stone, clay — quarrying unit price per the quota norms plus auxiliary-production on-costs (indirect costs) and mineral resource tax, if any). Freight and handling charges are calculated at surveyed market freight rates; with multiple supply points, weighted average by distance, volume and rate; no adjustment coefficient is applied to the average motor-haul distance, and no on-site haul distance or double-handling distance may be added beyond the site warehouse or material stack. When cement is motor-hauled over 500 km, the off-site transport wastage rate for bagged cement increases by 0.5 percentage points. Purchasing and custody charges are calculated by multiplying the sum of material price at source, freight and handling charges and off-site transport wastage by the percentage rate.

4. Bases to which percentage rates are applied (per the Form 08 notes):

  • Preliminaries, overheads (company and site): on (norm-based labour cost + norm-based plant cost) of the item, or norm-based direct cost x percentage rate;
  • Statutory levies and fees: on labour cost of the item x percentage rate;
  • Profit: on (norm-based direct cost + preliminaries + overheads (company and site)) x profit rate;
  • Taxes and duties: on (direct costs + preliminaries + overheads (company and site) + statutory levies and fees + profit) x tax rate.

Applicable Boundaries

  • Applies to highway preliminary estimate and budget compilation (JTG 3830-2018); not to railway (TB 10801-2024's sixteen-step procedure) or building/municipal (GB/T 50500 BOQ-based pricing) — each industry's composition and bases differ, no mixing.
  • This is the 2018 new framework (8 items); 2018-system budgets must use it, not the old cost items of earlier highway administrative compilation rules for estimates and budgets.
  • The daily labour rate serves only preliminary estimate/budget compilation, not wage payment; no double-counting of on-site haul or double handling for materials.
  • Special costs (site construction fees etc.) do not participate in the separation of net price and VAT and are listed in full; statutory work safety levy (earmarked funds) per clause 3.1.11 (the calculation base is the cost of works excluding the levy itself x percentage rate, not less than 1.5%).

Further Reading

  • JTG 3830-2018: clause 3.1.1 (composition, separation of net price and VAT, norm-based cost of works basis), clause 3.1.2 (direct costs: labour cost, material cost, with Tables 3.1.2-1 gross-mass coefficients/unit gross mass and 3.1.2-2 off-site transport wastage rates), clause 3.1.3 onward (permanent equipment procurement cost, preliminaries, overheads (company and site), statutory levies and fees, profit, taxes and duties, special costs).
  • Companion quota norms: Highway Works Budget Quota Manual (JTG/T 3832-2018) Appendix IV norm-based labour, material and equipment unit-price table; Highway Works Plant Rate Norms per Machine-Shift (JTG/T 3833).
  • Form 08 (comprehensive cost calculation) notes and the summary table (comprehensive Table 36.1): the tie-out norm-based cost of works = norm-based direct cost + norm-based permanent equipment procurement cost x 40% + preliminaries + overheads (company and site) + statutory levies and fees + profit + taxes and duties + special costs.