Highway traffic-interference construction addition: charged by table across 8 bands of average two-way daily traffic (JTG 3830-2018 clause 3.1.6, Table 3.1.6-7)
Per clause 3.1.6 of JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects": traffic-interference addition = (quota labor + quota plant cost) of the traffic-affected works x rate; the banding index is "average two-way traffic per day-night during construction (motor plus non-motor vehicles)" in 8 bands (51-100 up to over 5000), rates by works class from Table 3.1.6-7: earthwork 1.499%-6.468%, rockwork 1.279%-5.462%, haulage 1.451%-6.285%, pavement 1.390%-5.475%, Structures I 0.924%-3.647%, Structures II 1.007%-3.943%, Structures III 0.948%-3.713%; steel and steel structures marked "—" (not applicable). New works, closed construction with traffic interruption, and rebuild/widening with bypass roads do not charge the traffic-interference addition.
Applicable Codes
- JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.6条、Table 3.1.6-7
Topic Positioning
This card explains the charging rules of the "traffic-interference construction addition" under measures costs in the highway 2018 quota system (JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects"): the banding index, the base, the rates, and the non-chargeable cases, with the full rate Table 3.1.6-7.
Core Conclusions
Definition (verbatim): "The traffic-interference construction addition means the extra costs caused by reduced labor and plant efficiency due to traffic interference while constructing under live traffic."
- Banding index: average two-way traffic per day-night during construction (motor plus non-motor vehicles), 8 bands: 51-100, 101-500, 501-1000, 1001-2000, 2001-3000, 3001-4000, 4001-5000, over 5000.
- Base: quota labor + quota plant cost of the traffic-affected works items, times the rate.
- Table 3.1.6-7 traffic-interference rates (%):
| Works class | 51-100 | 101-500 | 501-1000 | 1001-2000 | 2001-3000 | 3001-4000 | 4001-5000 | >5000 |
|---|---|---|---|---|---|---|---|---|
| Earthwork | 1.499 | 2.343 | 3.194 | 4.118 | 4.775 | 5.314 | 5.885 | 6.468 |
| Rockwork | 1.279 | 1.881 | 2.618 | 3.479 | 4.035 | 4.492 | 4.973 | 5.462 |
| Haulage | 1.451 | 2.230 | 3.041 | 4.001 | 4.641 | 5.164 | 5.719 | 6.285 |
| Pavement | 1.390 | 2.098 | 2.802 | 3.487 | 4.046 | 4.496 | 4.987 | 5.475 |
| Structures I | 0.924 | 1.386 | 1.858 | 2.320 | 2.693 | 2.988 | 3.313 | 3.647 |
| Structures II | 1.007 | 1.516 | 2.014 | 2.512 | 2.915 | 3.244 | 3.593 | 3.943 |
| Structures III | 0.948 | 1.417 | 1.896 | 2.365 | 2.745 | 3.044 | 3.373 | 3.713 |
| Steel and steel structures | — | — | — | — | — | — | — | — |
- Table note (verbatim): "New works, closed construction with traffic interruption, or rebuild/widening projects where bypass roads are built to keep traffic moving do not charge the traffic-interference construction addition." The steel and steel structures row is "—" — not applicable.
- Rates rise with the traffic band; within a band earthwork is highest and structures lower, reflecting differing efficiency losses.
Applicable Boundaries
- Applies only to the JTG 3830-2018 system (with companion JTG/T 3832-2018 budget quota); if a new edition is issued, it governs.
- Charged only on works items "constructed under live traffic and affected by it"; new works, closed construction and rebuild/widen with bypass roads do not charge.
- Traffic counts are two-way totals of motor plus non-motor vehicles; works affected on one side or direction only charge on the affected items.
- Note: some figures differ slightly across OCR/transcribed texts (e.g. pavement 4.046 vs 4.06) — verify against the official print or Ministry-issued electronic edition when compiling.
- This fee's base ("quota labor + quota plant cost") differs from the construction-auxiliary fee's base ("quota direct costs") — do not mix within the same measures-cost section.
Further Reading
- JTG 3830-2018 clause 3.1.6 (measures costs) item 4 and Table 3.1.6-7; compare the night-work addition (Table 3.1.6-3), construction-auxiliary fee (Table 3.1.6-8) and works-transfer fee (Table 3.1.6-9).
- Works-class definitions (Structures III = placing commercial cement concrete and installing concrete components of bridge works; steel and steel structures = bridge steel and steel structures); the exclusion of purchased components from measures/enterprise-management bases is clause 3.1.5.
- Comparison: the railway counterparts are "traffic-interference addition / operating-line blockage addition" (TB 10801-2024/TB 10811-2024), differently charged — see the railway cards.