compilation rules for highway estimates and budgets (JTG 3830)
- 01
Highway works staple-and-supplementary food freight subsidy: composite mileage computation, rate selection and boundary rules (JTG 3830-2018 / JTG 3820-2018 clause 3.1.7)
Composite mileage = grain haul × 0.06 + fuel haul × 0.09 + vegetable hau…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.7条JTG 3820-2018 · Measure for Compilation of Investment Estimates of Highway Construction Projects 第3.1.7条2026-09-25 - 02
Highway estimate/budget project-table compilation rules: ten items of Part 1 cost of works (temporary works through special fees) and the part-item-sub-item-section-detail five-level coding (JTG 3830-2018 Section 2.4, Appendix B)
Per Clause 2.4.2 Figure 2.4.2 of JTG 3830-2018 (see Appendix B Table B.0…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第2.4节、App. B2026-09-25 - 03
Highway works JTG 3830-2018 composition of overheads (company and site): the five items — basic fee, staple and non-staple food freight subsidy, staff home-visit travel expenses, staff heating subsidy and financial costs — and the bases to which percentage rates are applied (clause 3.1.7)
JTG 3830-2018 clause 3.1.7: highway overheads (company and site) compris…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.7条、第3.1.6条、App. D2026-09-25 - 04
Highway 2018 system item-numbering rule for estimates and budgets: five levels - part (1 digit), item (2), sub-item (2), section (2), detail (2) (JTG 3830-2018 Clause 2.4.3; see Appendix B)
Per Clause 2.4.3 of JTG 3830-2018 "Measures for compiling estimates and…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第2.4节(第2.4.1~2.4.3条)及App. B2026-09-25 - 05
Highway estimate/budget "other works construction costs": nine items and the project management fee rules (JTG 3830-2018 section 3.3)
Per clause 3.3.1 of JTG 3830-2018, the nine items of "other works constr…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.3.1 条、第 3.3.2 条及Table 3.3.2-1JTG 3830-2018 第 3.2 节(土地使用及拆迁补偿费单独成项)2026-09-25 - 06
Highway completion (handover) acceptance test-and-inspection fee rates and rules: expressway 23,500 yuan/km etc. per table 3.3.2-5, chargeable length and lane corrections (JTG 3830-2018 clause 3.3.2 item 5; same caliber in JTG 3820-2018)
Per clause 3.3.2 item 5 and table 3.3.2-5 of JTG 3830-2018: completion (…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.3.2 条第 5 款、Table 3.3.2-5JTG 3820-2018 · Measure for Compilation of Investment Estimates of Highway Construction Projects 第 3.3.2 条2026-09-25 - 07
Highway 2018 quota-norm system — taxes and duties: VAT output tax listed separately; taxes and duties = (direct cost + permanent equipment procurement cost + preliminaries + overheads (company and site) + statutory levies and fees + profit) × construction VAT rate (JTG 3830-2018 clause 3.1.10)
Per clause 3.1.10 of JTG 3830-2018 "Administrative Compilation Rules for…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.10条(税金定义与公式)、第3.1.1条(价税分离)财政部 税务总局 海关总署公告2019年第39号(建筑业增值税税率9%)2026-09-25 - 08
Highway works preliminary estimate (budget) employer's (owner's) management fee: computed progressively on the norm-based cost of works per JTG 3830-2018 table 3.3.2-1 rates (with full rate table and worked example)
Per clause 3.3.2 of JTG 3830-2018, the employer's (owner's) management f…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.3.2 条、Table 3.3.2-1JTG 3830-2018 第 3.1.1 条(定额建筑安装工程费构成口径)2026-09-25 - 09
Highway permanent land-occupation fee composition and the five classes of land-use and demolition compensation costs (JTG 3830-2018 section 3.2)
Per clause 3.2.2 of JTG 3830-2018 "Measures for compiling estimates and…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.2节国办发〔2018〕16号《跨省域补充耕地国家统筹管理办法》2026-09-25 - 10
Publication and dynamic adjustment of the labour workday rate (all-in daily labour rate) under the 2018 highway quota system: set and published by the provincial transport authority (JTG 3830-2018, Clause 3.1.2)
Per Clause 3.1.2, item 1 of JTG 3830-2018, labour cost in highway estima…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.2条、第2.1.1条、第3.1.1条、第3.1.8条JTG/T 3832—2018 · Budget Quota of Highway Engineering 附录四'定额人工、材料、设备单价表'JTG/T 3833 · Quota for Shift Costs of Highway Engineering Machinery2026-09-25 - 11
Highway 2018 quota norms system: composition of the cost of works (construction and installation) — 8 cost items, separation of net price and VAT, and bases to which percentage rates are applied (JTG 3830-2018 section 3.1)
Per JTG 3830-2018 clause 3.1.1, highway cost of works (construction and…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1节JTG/T 3832-2018 · Budget Quota of Highway Engineering 附录四JTG/T 3833 · Quota for Shift Costs of Highway Engineering Machinery2026-09-25 - 12
Highway JTG 3830-2018 purchasing and custody charge rates for materials: steel 0.75%, fuel and explosives 3.26%, other materials 2.06%, purchased components 0.42%, commercial mixes exempt — and the basis for the norm-based material price for estimating
Per clause 3.1.2 of JTG 3830-2018 "Administrative compilation rules for…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.1.2 条JTG/T 3833 · Quota for Shift Costs of Highway Engineering Machinery2026-09-25 - 13
Highway estimate (budget) contingency rules: basic contingency rates by stage (design estimate 5% / revised estimate 4% / construction-drawing budget 3%), price-difference contingency formula, values of n and i, and the exemption clause (JTG 3830-2018 section 3.4)
Per section 3.4 of JTG 3830-2018: contingency = basic contingency + pric…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.4节2026-09-25 - 14
Highway traffic-interference construction addition: charged by table across 8 bands of average two-way daily traffic (JTG 3830-2018 clause 3.1.6, Table 3.1.6-7)
Per clause 3.1.6 of JTG 3830-2018 "Measures for compiling estimates and…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.6条、Table 3.1.6-72026-09-25 - 15
Highway estimate/budget works sub-table codes (JTG 3830-2018 Appendix B): culverts HD, greening and environmental protection LH, the nine two-letter codes, and item numbering within the sub-tables
Per Appendix B of JTG 3830-2018, there are nine works sub-tables, all tw…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects App. B(Table B.0.1-1~B.0.1-9)2026-09-25 - 16
Highway JTG 3830-2018 plateau-region construction addition: from 2000 m elevation, base quota labor + quota plant cost, stepped rates in Table 3.1.6-4
Per clause 3.1.6 item 4 of JTG 3830-2018 "Measures for compiling estimat…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.1.6 条第 4 款、Table 3.1.6-42026-09-25 - 17
Highway works preliminary estimate (budget) site construction fee: base to which percentage rates are applied = norm-based cost of works − special costs, progressive percentage rates per Table 3.1.11 (JTG 3830-2018 clause 3.1.11)
Per clause 3.1.11 of JTG 3830-2018 'Administrative Compilation Rules for…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.11条及Table 3.1.11JTG/T 3832-2018 · Budget Quota of Highway EngineeringJTG/T 3831-2018 · Estimate Quota of Highway Engineering2026-09-25 - 18
Highway 2018 quota system works classification: the 10 classes of JTG 3830-2018 clause 3.1.4 (Structures II = minor, medium, major and super-major bridges) and their use as fee-band selectors
Per clause 3.1.4 of JTG 3830-2018 "Measures for compiling estimates and…
JTG 3830—2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.1.4~3.1.6 条JTG/T 3831—2018 · Estimate Quota of Highway EngineeringJTG/T 3832—2018 · Budget Quota of Highway Engineering2026-09-25 - 19
Composition of labor cost (quota labor cost) in the highway 2018 system: three classes of wage-type costs and the comprehensive shift-price caliber (JTG 3830-2018 Clause 3.1.2)
Per Clause 3.1.2 of JTG 3830-2018, highway estimate (budget) labor cost…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.2条JTG 3820-2018 · Measure for Compilation of Investment Estimates of Highway Construction ProjectsJTG/T 3832-2018 · Budget Quota of Highway Engineering 附录四2026-09-25 - 20
Quota basis of labor/material/plant consumption in highway estimate (budget) compilation: JTG 3830-2018 clause 2.1.1 adopts JTG/T 3831-2018 estimate quota and JTG/T 3832-2018 budget quota
Clause 2.1.1 of JTG 3830-2018 provides: when compiling estimates and bud…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第2.1.1条JTG/T 3831-2018 · Estimate Quota of Highway EngineeringJTG/T 3832-2018 · Budget Quota of Highway Engineering2026-09-25 - 21
Highway JTG 3830-2018 site construction fee: 5.338% on the first 5 million yuan, progressive computation per Table 3.1.11, and the base to which percentage rates are applied (special costs)
Per clause 3.1.11 and Table 3.1.11 "site construction fee rate table" of…
JTG 3830—2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.11条、Table 3.1.112026-09-25 - 22
Highway estimate/budget construction-auxiliary fee base: quota direct costs x Table 3.1.6-8 rates (JTG 3830-2018 clause 3.1.6 item 6)
The highway construction-auxiliary fee is charged on the base "quota dir…
JTG 3830—2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.1条、第3.1.6条第6款、Table 3.1.6-8JTG/T 3832—2018 · Budget Quota of Highway Engineering 附录四JTG/T 3833 · Quota for Shift Costs of Highway Engineering Machinery2026-09-25