Highway works staple-and-supplementary food freight subsidy: composite mileage computation, rate selection and boundary rules (JTG 3830-2018 / JTG 3820-2018 clause 3.1.7)

Composite mileage = grain haul × 0.06 + fuel haul × 0.09 + vegetable haul × 0.15 + water haul × 0.70, all four hauls being whole-line averages; the subsidy is charged on the norm-based direct cost of each works class at the rates of Table 3.1.7-2; where the composite mileage falls between the listed mileages the rate may be interpolated, and works within 3 km charge this item as 3 km (JTG 3830-2018 clause 3.1.7 item 2; JTG 3820-2018 clause 3.1.7, on the same basis).

Applicable Codes

  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.7条
  • JTG 3820-2018 · Measure for Compilation of Investment Estimates of Highway Construction Projects 第3.1.7条

Topic Positioning

The composite mileage computation and rate selection rules for the "staple-and-supplementary food freight subsidy", a component of overheads (company and site), in highway works estimate/budget (and investment estimate) compilation — from clause 3.1.7 item 2 of JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects", with clause 3.1.7 of JTG 3820-2018 "Measures for compiling investment estimates of highway construction projects" on the same basis.

Core Conclusions

The staple-and-supplementary food freight subsidy is the additional cost incurred by the contractor in buying daily necessities for field construction far from towns and villages; it is charged on the norm-based direct cost of each works class at the rates in Table 3.1.7-2 (food subsidy rate table).

Composite mileage formula (verbatim): composite mileage = grain haul × 0.06 + fuel haul × 0.09 + vegetable haul × 0.15 + water haul × 0.70, where the grain, fuel, vegetable and water hauls are all whole-line averages (not distances to a single point or to individual work sites).

Boundary rules (verbatim):

  • Where the composite mileage falls between the mileages listed in the table, the rate may be interpolated;
  • For works whose composite mileage is within 3 km, this item is charged as 3 km.

Weight meaning: water carries the highest weight (0.70) — the composite mileage is driven mainly by the construction-water haul, which matches field reality where large volumes of water are used and water points are distributed along the line; grain 0.06, fuel 0.09, vegetables 0.15.

Worked example (illustrative): if the whole-line averages are grain 50 km, fuel 40 km, vegetables 20 km, water 10 km, then composite mileage = 50 × 0.06 + 40 × 0.09 + 20 × 0.15 + 10 × 0.70 = 3 + 3.6 + 3 + 7 = 16.6 km, which falls between the listed mileages, so the rate is interpolated.

Applicable Boundaries

  • Stages: estimate and budget (JTG 3830-2018) and investment estimate (JTG 3820-2018); the same basis applies at estimate stage.
  • The base is the "norm-based direct cost of each works class", with the rate selected from Table 3.1.7-2 according to works class; specific rate values are subject to the officially issued text of the Ministry of Transport (the OCR of the rate tables held in the library is poor, but the composite mileage formula and the boundary rules above are literal and can be used directly).
  • Hauls must be whole-line averages and must not be replaced by single-point distances; where the composite mileage is below 3 km, it is still charged as 3 km and must not be reduced to the actual mileage.
  • Items 3-5 of the same clause separately provide for staff home-visit travel costs (Table 3.1.7-3), staff heating subsidy (Table 3.1.7-4, with rates selected by the temperature zone of the project location: Appendix D of JTG 3830-2018, Appendix E of JTG 3820-2018) and financial costs (Table 3.1.7-5), all charged on the norm-based direct cost of each works class, under the same overheads (company and site) basis as this item.

Further Reading

  • JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects", clause 3.1.7 item 2 and Table 3.1.7-2 (food subsidy rate table).
  • JTG 3820-2018 "Measures for compiling investment estimates of highway construction projects", clause 3.1.7 and Table 3.1.7-2.
  • The interpolation and 3 km floor rules appear in the notes to those clauses; rates are divided by works class (earthwork, rockwork, haulage, pavement, tunnels, structures, technically complex bridges, steel and steel structures, etc.).
  • Extension: clause 3.1.8 statutory levies and fees and clause 3.1.11 statutory work safety levy (earmarked funds) (cost of works (construction and installation) × rate, not less than 1.5%), together with other rules for compiling cost of works items.