Work safety levy for non-railway works (building / municipal / highway / water conservancy): accrual basis, non-competitive nature, and ring-fenced use rules
Building/municipal: the mandatory health, safety and environmental (HSE) provisions are a non-competitive preliminary item priced at percentage rates set by national and provincial provisions (GB/T 50500-2024 Clause 3.2.5; GB 50722-2011 Clause 5.2.9); highway: accrued as the cost of works (construction and installation) (excluding the work safety levy itself) × percentage rate, with the rate not less than 1.5% (JTG 3830-2018 Clause 3.1.11); in all industries, tender (priced offers) must list it separately, it must not be a competitive bid item, and after the supervising engineer's certification and sign-off it is disbursed on actual expenditure — diversion strictly prohibited, no lump-summing (Ministry of Transport Order No. 25 of 2017, Article 21).
Applicable Codes
- JTG 3830-2018 公路工程建设项目概算预算编制办法
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB 50722-2011 城市轨道交通建设项目管理规范
- 交通运输部令2017年第25号 公路水运工程安全生产监督管理办法
- GB 50656-2011 施工企业安全生产管理规范
- 财资〔2022〕136号 企业安全生产费用提取和使用管理办法
Topic Positioning
This card answers "how the statutory work safety levy (earmarked funds) — the mandatory health, safety and environmental (HSE) provisions — for non-railway works (building/municipal/highway/water conservancy, etc.) is accrued, whether it may be discounted for competition, and whether it may be lump-summed" — the discipline-by-discipline complement to the railway basis (3.0% of the cost of works (construction and installation), see the railway work safety levy card), for preliminary estimate/budget preparation, tender pricing compliance review, and safety fund management across industries.
Core Conclusions
- Building/municipal (BOQ-based pricing system): the mandatory health, safety and environmental (HSE) provisions are a preliminary item priced at percentage rates set by national and provincial construction authorities and are non-competitive (GB/T 50500-2024 Clause 3.2.5); GB 50722-2011 Clause 5.2.9 further makes the mandatory health, safety and environmental (HSE) provisions and work-injury insurance for migrant workers non-competitive — the employer may not demand discounts, and bidders may not compete on them.
- Highway works: per the administrative compilation rules for estimates and budgets, accrued as the cost of works (construction and installation) (excluding the work safety levy itself) multiplied by a percentage rate not less than 1.5% (JTG 3830-2018 Clause 3.1.11).
- General management rules (Ministry of Transport Order No. 25 of 2017, Article 21): the work safety cost determined by the employer must not be below the national standard; contractors accrue it separately in tender (priced offers) and it must not be a competitive bid item; the cost is disbursed on actual expenditure after the supervising engineer's certification and sign-off and the employer's consent, with diversion strictly prohibited — i.e., no discounting and no lump-summing.
- Enterprise financial accrual basis: based on the cost of works (construction and installation); the old accrual ratios of Cai Qi [2006] No. 478 cited by GB 50656-2011 Clause 3.0.6 have been replaced by Cai Zi [2022] No. 136, Administrative Measures for the Accrual and Use of Enterprise Work Safety Costs — the current ratios follow that document.
Applicable Boundaries
This card covers building/municipal/highway/water conservancy and other non-railway industries; railway projects follow TB 10811-2024 Clause 2.11.9 (3.0% of the cost of works (construction and installation)), see the railway work safety levy card. Building/municipal percentage rates are set by provincial norms for on-costs and expenses and differ by province — budget per the current rules of the project location; industry rates and measures change with revisions, so verify the current effective edition before use.
Further Reading
See Administrative Compilation Rules for Estimates and Budgets of Highway Construction Projects JTG 3830-2018 Clause 3.1.11; GB/T 50500-2024 Clause 3.2.5; GB 50722-2011, Code for Management of Urban Rail Transit Construction Projects, Clause 5.2.9; Ministry of Transport Order No. 25 of 2017, Measures for Supervision and Administration of Work Safety of Highway and Waterway Works, Article 21; GB 50656-2011, Code for Work Safety Management of Construction Enterprises, Clauses 3.0.6 and 8.0.4; for accrual and payment management see also Cai Zi [2022] No. 136, Administrative Measures for the Accrual and Use of Enterprise Work Safety Costs.
Keywords
Cited By
- ←
Comparing mandatory HSE provisions (statutory work safety levy) rates with the statutory work safety funding standard correctly: the three-step method - align the base, align the scope, separate the levels - and why a single-item rate converted below 3% is method failure, not non-compliance
A safe-construction rate sitting on a labour-plus-machine base, multiplied by the labour-and-machine share and converted to a cost-of-works denominator, falling below the statutory 3% does not show the rate deficient: first, the bases differ (labour plus machine costs versus the construction and installation cost of works) - for the single 5.19% item the conversion reaches 3% only at a labour-and-machine share of 57.8% or more, forever out of reach for building works at 20% to 30%: method failure; second, the scopes differ (safe-construction provisions carry only two classes of spending - safety protection facilities and equipment, and site workers' protective gear - while training, emergency preparedness, testing and examination, work safety liability insurance and hazard rectification sit elsewhere, in overheads or statutory levies or outside construction cost entirely); third, the levels differ (the 3% of Cai Zi [2022] No. 136 is an enterprise accrual on output progress, not the same level as the HSE provisions singled out in the contract price). Correct method: unify the base, align the spending scope, and judge on three levels - priced into the works, accrued by the enterprise, actually spent.
- ←
Why the 'statutory withdrawal coefficient' of the work safety levy and the fee rates of pricing bases differ: the hierarchy of Work Safety Law article 23, the withdrawal standards of Cai Zi [2022] No. 136, and the differences of base, content and function across sector fee schedules
Work Safety Law (2021 revision) article 23 itself sets no percentage - only three duties, to withdraw, to use exclusively and to charge to cost as actually incurred, delegating the rates to the finance and emergency-management departments; the so-called statutory coefficient is in fact article 17 of the Measures for the Administration of Withdrawal and Use of Enterprise Work Safety Expenses (Cai Zi [2022] No. 136): withdrawal on the construction and installation cost of works - mining 3.5%; railway, building and urban rail transit 3%; water conservancy and hydropower, and power 2.5%; smelting, mechanical and electrical installation, chemical and petroleum, and communications 2%; municipal utilities, ports and waterways, and highway 1.5%. The rates in the BOQ pricing standard and sector fee schedules are price standards - how the money enters the contract price and who pays (GB/T 50500-2024 clauses 2.0.4 and 3.2.5; statutory safety provisions are non-competitive) - and differ in base and content (cost of works versus labour plus machine costs; work safety expenses versus the wider mandatory HSE provisions including civilised construction, environmental protection and temporary facilities); the two are not on one yardstick and their figures cannot be compared directly; within one sector they mostly agree (TB 10811-2024 clause 2.11.9: 3.0%; JTG 3830-2018: not less than 1.5%).
- ←
Content and pricing methods of preliminaries: the 2024 definition (clause 2.0.3), the listing basis (GB/T 50854-2024 annex R table R.1.1 preliminary items, code 011601), the three pricing methods of unit rate / lump sum / percentage rate and their preferred use (clauses 2.0.10 to 2.0.12, 3.2.1), the completion rules of annex E tables E.3.1 to E.3.4, and the non-competitive rule for statutory safety provisions (clause 3.2.5)
Preliminaries are 'project costs incurred in taking the relevant measures to complete the contract works, related to the cost of the works as a whole and to the performance of the contract, but unrelated to the cost of any individual divisional or sub-divisional work item' (GB/T 50500-2024 clause 2.0.3); their content is listed per annex R table R.1.1 of GB/T 50854-2024 (preliminary items, code 011601). The 2024 edition no longer splits 'lump-sum preliminaries / unit-rate preliminaries'; it prices by three methods - unit-rate pricing (quantity x all-in unit rate), lump-sum pricing (per item) and percentage-rate pricing (charging base x percentage rate) - and 'the pricing of the preliminaries BOQ should adopt the lump-sum method' (clause 3.2.1); special measures whose construction scheme the contract requires to pass expert panel review may instead be unit-rate priced and are then listed in the divisional/sub-divisional BOQ. The statutory safety provisions are a non-competitive item and must be priced per the provisions of the state and of the provincial or sector authorities (clause 3.2.5).
- ←
Interim payment and final settlement of preliminaries: statutory safety provisions prepayment and recovery points (9.3.2 - at least 50% within 28 days of commencement), progress-payment methods (9.4.4 - agreed breakdown or element-works ratios), the three-stage preliminaries breakdown table (6.2.13, Appendix E Table E.3.3), interim versus final settlement (10.2.7, 10.3.3) and the three-class treatment in settlement review
Statutory safety provisions prepay at not less than 50% of the total within 28 days of commencement, the rest decomposed per the early-arrangement principle and paid with progress payments; computing progress payments never recovers the prepayment - it is recovered once at the final account (9.3.2). Preliminaries progress payments follow the parties' agreed breakdown; absent agreement, by the ratio of cumulative completed work-item list value to the work-item list total, the breakdown resting on Appendix E Table E.3.3 (initial set-up / mid-term running / late dismantling, 6.2.13, 9.4.4). Preliminaries listed in interim settlements serve only interim payment (10.2.7); the final account recomputes all preliminaries of the completed works per clause set 7.3 and chapter 8, including safety-provision adjustments - interim figures are no basis (10.3.3).
- ←
Whether rate-priced mandatory HSE provisions (statutory safety provisions) adjust at settlement: three adjustment doors (quantity-linked base, legal and policy change, major variation or raised standards), the rate-lump-sum principle regardless of actual spend, and the settlement base plus the 2013/2024 edition gap
Mandatory HSE provisions (railway: work safety funds; GB/T 50500-2024: statutory safety provisions) are non-competitive: settlement value = settlement base x prescribed rate, lump-sum, never rising or falling with the contractor's actual spend. Only three doors open: (1) the base (finally confirmed work-item costs) - GB 50500-2013 clause 9.6.3 adjusts rate or single-price preliminaries both ways with quantity; (2) legal and policy change after the contract base date - 2013 clause 11.2.3 and 2024 clause 8.8.1 adjust when the authorities revise the standards mid-works; (3) variation or employer-raised site standards - scheme confirmed before execution (2013 9.3.2; 2024 8.9.6), silence forfeits. Settlement review recomputes all preliminaries per 10.3.3; interim-listed figures are no basis.
- ←
Within preliminaries: the composition, charging method and calculation bases of mandatory HSE provisions (statutory safety provisions), temporary works and site establishment costs, and the additional cost of night work, compared; plus the clause basis of the non-competitive status of mandatory HSE provisions and the item listing rules
Mandatory HSE provisions comprise four heads - environmental protection, site order, safe construction, and temporary works and site establishment (Jian Ban [2005] No. 89 article 4 citing Jian Biao [2003] No. 206); temporary works cost is thus a sub-head and must not be listed again as a separate item and double charged. GB/T 50500-2024 clause 3.2.5 makes statutory safety provisions a non-competitive item, and GB 50722-2011 clause 5.2.9 provides that mandatory HSE provisions and work injury insurance for migrant workers must not be treated as competitive costs: the tenderer may not require a discount on them and tenderers may not subject them to market competition. All three heads are lump-sum preliminaries not readily measurable, charged as calculation base x percentage rate; the base for mandatory HSE provisions is the quota base price (norm-based elemental works cost plus measurable preliminaries), the norm-based labour cost, or the norm-based labour cost plus norm-based plant cost; the additional cost of night work is charged on the base of the labour and plant costs incurred for the night work, and only where night work actually occurs under technologically required continuous construction or an approved night work plan may it be charged (statutory night runs 22:00 to 6:00 the next day).
- ←
Where the work safety liability insurance (Anze Xian), employer's liability insurance and work injury insurance for migrant workers belong in pricing: inclusion in the mandatory HSE provisions (the statutory work safety levy under railway rules), how they are taken at tender and settlement, and how the three relate
The work safety liability insurance is in principle disbursed within the mandatory HSE provisions / statutory work safety levy without a separate heading: railway TB 10801-2024 Table 3.11.11 category 9 is 'work safety liability insurance expenditure'; the highway guide says it 'may be disbursed from the work safety costs'; some provincial fee norms for building and municipal works list it within the mandatory HSE provisions. Taking basis: at tender / tender price ceiling it is taken at the non-competitive percentage rate, at settlement adjusted to the amount actually paid (policy and contract plus premium receipts / technical service deliverables). Employer's liability insurance is the contractor's commercial cover carried in overheads, not disbursed from the work safety levy. Work injury insurance for migrant workers is social insurance - carried separately, non-competitive, paid in one lump sum by the main contractor before commencement - running parallel to, not replacing, the work safety liability insurance.
- ←
Whether preliminaries adjust after a construction plan (project execution plan) changes: the lump-sum boundary, adjustable situations, measurement and pricing methods, and supporting records
After a plan (project execution plan) change, preliminaries follow lump-sum-no-adjustment as the principle (GB/T 50500-2024 Article 3.3.7): the contractor's tendered measures plan is deemed reasonable and feasible, preliminaries are priced lump-sum, and the contractor bears the risk of increases caused by his own plan changes; only three exceptions - variations, works within provisional sums not fully foreseen or detailed, and employer-caused extended use, dismantling, addition or duplicated provision of measures - adjust under Chapter 8; costs of changing an unworkable plan or one beyond the contractor's capability are his own. Time effects adjust only for substantive critical-path extension or reduction (8.9.4), non-critical items unmeasured; cost fluctuation is no ground (8.7.6), while laws and policy changes are a separate channel (8.8.1); measurement adjustment is a closed list under 7.3.1; varying preliminaries requires the plan approved and confirmed before execution, silence forfeiting the right (8.9.6, 8.9.7).
- ←
Highway works staple-and-supplementary food freight subsidy: composite mileage computation, rate selection and boundary rules (JTG 3830-2018 / JTG 3820-2018 clause 3.1.7)
Composite mileage = grain haul × 0.06 + fuel haul × 0.09 + vegetable haul × 0.15 + water haul × 0.70, all four hauls being whole-line averages; the subsidy is charged on the norm-based direct cost of each works class at the rates of Table 3.1.7-2; where the composite mileage falls between the listed mileages the rate may be interpolated, and works within 3 km charge this item as 3 km (JTG 3830-2018 clause 3.1.7 item 2; JTG 3820-2018 clause 3.1.7, on the same basis).
- ←
Advance payment rules for the statutory safety provisions (mandatory health, safety and environmental (HSE) provisions) compared: GB 50500-2013 Clause 10.2.2's 60% vs GB/T 50500-2024 Clause 9.3.2's 50%, no recovery from progress payments, one-time recovery at final account
The advance percentage for the mandatory health, safety and environmental (HSE) provisions (renamed "statutory safety provisions" in the 2024 standard) has dropped from 60% to 50%: GB 50500-2013 (repealed) Clause 10.2.2 required an advance of not less than 60% of the current year's planned total within 28 days of commencement; GB/T 50500-2024 (current) Clause 9.3.2 changes this to not less than 50% of the total and adds the explicit recovery rule that "the advance for the statutory safety provisions shall not be recovered when computing progress payments due and shall be recovered in one lump sum at final account". The advance window (within 28 days of commencement) is unchanged.
- ←
Prepayment and payment rules for statutory safety provisions (GB/T 50500-2024 Clauses 9.3.2, 9.3.3): not less than 50% prepaid within 28 days of commencement, paid alongside progress payments, recovered in one lump sum at final account
Under Clause 9.3.2 of GB/T 50500-2024, the China national pricing standard for BOQ, the employer shall, within 28 days after commencement, prepay to the contractor not less than 50% of the total statutory safety provisions; the remainder shall be broken down on the "arrange in advance" principle and paid alongside progress payments; for multi-year major works the prepaid total may be broken down by reference to the annual programme of works. When computing progress payments due, the prepaid safety provisions shall not be recovered; they are recovered in one lump sum at final account. Clause 9.3.3: where the employer fails to pay by the agreed time, the contractor may give notice; if payment is still not made within the agreed period after such notice, the contractor is entitled to suspend the works and the employer bears liability for breach of contract; where a safety accident occurs because the employer failed to pay the statutory safety provisions on time, the employer bears the corresponding responsibility.
- ←
Checking tender prices for omitted taxes and duties, statutory levies and fees, and preliminaries (edition basis → tax back-calculation → levy rates → preliminaries comparison)
Four-step check for omitted taxes and duties / statutory levies and fees / preliminaries: ① confirm the pricing edition basis first (2013: five costs listed separately vs 2024: statutory levies and fees embedded in all-in unit rates, only VAT listed separately); ② taxes and duties — check the rate and the base (work items + preliminaries + bill of provisional sums and other charges, net of provisional sums for nominated specialist subcontract works), and verify by back-calculation: total price ÷ 1.09; ③ statutory levies and fees — check completeness of the listed items and consistency of percentage rates (non-competitive; must exactly match the tender documents / provincial rates); ④ preliminaries — compare item by item against the project execution plan (construction methodology and site organization), with a dedicated check on the non-competitive mandatory health, safety and environmental (HSE) provisions; under the 2024 edition a cost-breakdown table must be submitted with the tender.
- ←
Highway estimate/budget "other works construction costs": nine items and the project management fee rules (JTG 3830-2018 section 3.3)
Per clause 3.3.1 of JTG 3830-2018, the nine items of "other works construction costs" are: project management fee, research and test fees, project preliminary-stage fees, special appraisal (assessment) fees, combined trial-run fees, production-preparation costs, works traffic-maintenance management fees, works insurance, and other related costs. Project management fee (clause 3.3.2) has 5 sub-items: owner management fee, project informatization fee, supervision fee, design-document review fee, completion/acceptance testing fee; the owner management fee is computed progressively on quota construction-installation costs at Table 3.3.2-1 rates. Note: "land-use and demolition compensation costs" is a separate item in the 2018 edition (section 3.2), not among the nine.
- ←
Highway estimate/budget statutory fees (规费) base: charged on the sum of labor costs of each works class (JTG 3830-2018 clause 3.1.8) and the distinction from quota labor
Per JTG 3830-2018 clause 3.1.8, highway statutory fees comprise five items — pension, unemployment, medical (including maternity), work-injury insurance and housing fund; "each statutory fee is charged on the base of the sum of labor costs of each works class, at standards set by state or local laws, regulations, rules and provisions." That base is the compilation-period labor cost at the works location's composite day rate, not the "quota labor" priced at Appendix IV base prices of JTG/T 3832-2018 (the latter serving only quota direct costs and the bases of measures/enterprise-management/profit fees); the composite day rate already includes the employee-paid pension, unemployment, medical (excluding maternity) and housing fund, while the statutory fee charges the enterprise-paid portion.
- ←
Highway 2018 quota-norm system — taxes and duties: VAT output tax listed separately; taxes and duties = (direct cost + permanent equipment procurement cost + preliminaries + overheads (company and site) + statutory levies and fees + profit) × construction VAT rate (JTG 3830-2018 clause 3.1.10)
Per clause 3.1.10 of JTG 3830-2018 "Administrative Compilation Rules for Estimates and Budgets of Highway Construction Projects": taxes and duties mean the VAT output tax that state tax law requires to be included in the cost of works (construction and installation), and the formula is: taxes and duties = (direct cost + permanent equipment procurement cost + preliminaries + overheads (company and site) + statutory levies and fees + profit) × construction VAT rate. Together with the clause 3.1.1 rule of separation of net price and VAT, all six bracketed items are computed at prices (rates) exclusive of deductible input VAT — input VAT enters no cost item and taxes and duties are listed separately in the project cost. The compilation rules do not lock the rate value; follow the finance and tax authorities — since 1 April 2019 the construction VAT rate under the general taxation method is 9% (MOF/STA/GAC Announcement No. 39 of 2019). Special costs (site construction fee, statutory work safety levy) do not enter the tax base.
- ←
Highway permanent land-occupation fee composition and the five classes of land-use and demolition compensation costs (JTG 3830-2018 section 3.2)
Per clause 3.2.2 of JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects", the permanent land-occupation fee has 5 items: land compensation, resettlement subsidy for requisitioned arable land, arable-land reclamation fee, forest-vegetation restoration fee, and pension insurance for land-lost farmers; clause 3.2.1 defines land-use and demolition compensation costs as 5 classes: permanent land-occupation fee, temporary land-occupation fee, demolition compensation, soil-and-water conservation compensation, and other costs. Each is computed per state and provincial (works-location) government provisions.
- ←
Highway 2018 quota norms system: composition of the cost of works (construction and installation) — 8 cost items, separation of net price and VAT, and bases to which percentage rates are applied (JTG 3830-2018 section 3.1)
Per JTG 3830-2018 clause 3.1.1, highway cost of works (construction and installation) = direct costs + permanent equipment procurement cost + preliminaries + overheads (company and site) + statutory levies and fees + profit + taxes and duties (VAT under the current standard) + special costs (8 items); except special costs, all follow the separation of net price and VAT rule, computed at prices (percentage rates) excluding deductible input VAT. Norm-based cost of works = norm-based direct cost + 40% of norm-based permanent equipment procurement cost + preliminaries + overheads (company and site) + statutory levies and fees + profit + taxes and duties + special costs. Bases to which percentage rates are applied (Form 08): preliminaries and overheads (company and site) on the sum of norm-based labour cost and norm-based plant cost, or norm-based direct cost; statutory levies and fees on labour cost; profit on (norm-based direct cost + preliminaries + overheads (company and site)); taxes and duties on (direct costs + preliminaries + overheads (company and site) + statutory levies and fees + profit).
- ←
Cost attribution and estimation of temporary hoarding, gates, and wheel-wash facilities on site (basis of mandatory health, safety and environmental (HSE) provisions)
Hoarding, gates, and wheel-wash facilities belong respectively to the site housekeeping and appearance fee, the temporary works and site establishment costs / site monitoring fee, and the dust pollution prevention fee sub-items of mandatory health, safety and environmental (HSE) provisions (a Chinese non-competitive fee; the literal loan translation is misleading, so an institutional note is required); in regions with lump-sum percentage rates they must not be listed separately again; in regions where costs are itemised on an actual basis, estimate by "quantity × unit price" applying quota items + equipment price enquiries; on the railway basis this corresponds to the statutory work safety levy (earmarked funds) + preliminaries, with minor temporary works cost included in preliminaries and heavy temporary works priced by applying quota items on an actual basis.
- ←
Highway combined trial-run fee: charged at 0.04% of quota construction-installation costs (JTG 3830-2018 clause 3.3.6)
Per clause 3.3.6 of JTG 3830-2018, combined trial-run fee = quota construction-installation costs x 0.04% (verbatim: "The combined trial-run fee is computed on the base of quota construction-installation costs at a rate of 0.04%"). It covers all costs of full-load combined trial runs of complete M&E equipment of highway projects, excluding commissioning costs payable within equipment installation costs; it belongs to section 3.3 "other works construction costs", applies uniformly to estimates and budgets, and takes the quota-caliber construction-installation costs, not market-priced.
- ←
Highway works preliminary estimate (budget) site construction fee: base to which percentage rates are applied = norm-based cost of works − special costs, progressive percentage rates per Table 3.1.11 (JTG 3830-2018 clause 3.1.11)
Per clause 3.1.11 of JTG 3830-2018 'Administrative Compilation Rules for Estimates and Budgets of Highway Works Construction Projects': the site construction fee is calculated on the 'site construction base to which percentage rates are applied = norm-based cost of works − special costs' at the percentage rates in Table 3.1.11 using the progressive bracket-excess method (5.338% for 5 million yuan and below, stepping down band by band to 1.118% above 10,000 million yuan, 15 bands); special costs = site construction fee + statutory work safety levy (earmarked funds). Distinguish it from the statutory work safety levy (earmarked funds) in the same clause: statutory work safety levy (earmarked funds) = cost of works (construction and installation) (excluding the levy itself) × percentage rate (not less than 1.5%) — the base is different and the two must not be mixed.
- ←
Full workflow of agreeing and paying construction advance payments (GB/T 50500-2024 Section 9.2): nature, proportion, procedure, guarantee, and recovery
The construction advance payment (materials advance) is paid by the Employer before commencement for the Contractor's materials preparation - earmarked and interest-free. For labour-and-material contracts, the payment proportion should not be less than 10% of the signed contract price (net of provisional sums, dayworks and provisional sums for nominated specialist subcontract works) and should not exceed 30% of the signed contract price (for major multi-year projects, prepaid annually at the same proportion in accordance with the annual plan). The Contractor applies -> the Employer reviews and pays (an equal-value guarantee may be agreed); recovery is made as agreed in the contract, or, if not agreed, in one or more instalments; on termination of the contract, any unrecovered portion is recovered in full.
- ←
GB 50500-2013 -> GB/T 50500-2024: changes to the clauses on statutory levies and fees, taxes and the mandatory health, safety and environmental (HSE) provisions — mandatory provisions withdrawn, the bills restructured into four parts, and the item renamed statutory safety provisions
2013 Clause 3.1.6, “statutory levies and fees and taxes must be calculated in accordance with the provisions of the state, provincial or industry construction authorities and shall not be treated as competitive costs” (a mandatory provision), disappears entirely from GB/T 50500-2024: the 2024 edition is a recommended GB/T standard with no mandatory provisions anywhere; under Clause 3.1.2 the bills become four parts (work items / preliminaries / provisional sums and other charges / VAT), statutory levies and fees are no longer a separate billed item, and taxes are renamed VAT (Clause 3.2.11: the tax base is the total of work items + preliminaries + other items, less the provisional sum for nominated specialist subcontract works, multiplied by the tax rate). The mandatory health, safety and environmental (HSE) provisions are renamed “statutory safety provisions” (Clause 3.2.5), and their “non-competitive” character is expressly retained (“is a non-competitive item”), but the wording is softened from “must ... shall not be treated as competitive costs” to “shall be priced in accordance with the relevant provisions of the state and provincial or industry authorities”. GB/T 50500-2024 takes effect on 1 September 2025, and GB 50500-2013 is repealed at the same time.
- ←
Highway JTG 3830-2018 site construction fee: 5.338% on the first 5 million yuan, progressive computation per Table 3.1.11, and the base to which percentage rates are applied (special costs)
Per clause 3.1.11 and Table 3.1.11 "site construction fee rate table" of the Administrative Compilation Rules for Estimates and Budgets of Highway Works (JTG 3830-2018), the site construction fee is a special cost within the cost of works (construction and installation), alongside the statutory work safety levy (earmarked funds), with the base to which percentage rates are applied for site construction = norm-based cost of works − special costs, charged progressively rather than as the full amount × one percentage rate. First band: base up to 5 million yuan at 5.338% (example 500 × 5.338% = 26.69, i.e. 266,900 yuan); later bands decrease with the base (5-10 million 4.228%, 10-50 million 2.665%, ... above 10,000 million 1.118%).
- ←
Highway estimate (budget) work-safety fee: base = construction-installation costs excluding the fee itself, rate >=1.5% (JTG 3830-2018 clause 3.1.11), fee content and management requirements
Highway work-safety fee = construction-installation works costs (excluding the work-safety fee itself) x work-safety rate, the rate at not less than 1.5% (JTG 3830-2018 clause 3.1.11); it is one of the 'special costs' in the 8-item composition, covering eight categories of safety expenditure; per Article 21 of Ministry of Transport Order No. 25 of 2017, it must be separately accrued in bid prices and not treated as a competitive price item, reviewed and signed off by the supervising engineer, and, with the employer's consent, disbursed against actual costs within the project construction cost — diversion strictly prohibited. Comparison: railway (TB 10811-2024) books 3.0% of construction-installation costs — the two bases differ, so do not mix them.
- ←
Nature and pricing rules of statutory safety provisions (GB/T 50500-2024: non-competitive item, whole-process constraints, and the change in normative force)
GB/T 50500-2024 Clause 3.2.5 states that the statutory safety provisions in the bill of preliminaries "shall be priced per the relevant provisions of the state, provincial, and industry authorities" and "are a non-competitive item" — their standard is not formed by market competition. Clause 2.0.4 defines them as the special fee safeguarding construction production safety; Clauses 5.2.5/6.2.6/9.3.1/9.3.4 enforce "compliance with authority provisions + ring-fenced (earmarked) use of funds, no diversion" across the tender price ceiling, tenders, and interim payments. The old GB 50500-2013 Clause 4.1.5 (mandatory provisions of codes: "must... shall not be a competitive fee") lost its mandatory force when the standard changed to a recommended GB/T; current binding force rests on administrative documents of the authorities and tendering supervision practice.