Highway combined trial-run fee: charged at 0.04% of quota construction-installation costs (JTG 3830-2018 clause 3.3.6)
Per clause 3.3.6 of JTG 3830-2018, combined trial-run fee = quota construction-installation costs x 0.04% (verbatim: "The combined trial-run fee is computed on the base of quota construction-installation costs at a rate of 0.04%"). It covers all costs of full-load combined trial runs of complete M&E equipment of highway projects, excluding commissioning costs payable within equipment installation costs; it belongs to section 3.3 "other works construction costs", applies uniformly to estimates and budgets, and takes the quota-caliber construction-installation costs, not market-priced.
Applicable Codes
- JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.3.6条
Topic Positioning
The charging rules for the "combined trial-run fee" in highway estimate (budget) compilation: definition, content, base and rate, per clause 3.3.6 of JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects" (section 3.3 "other works construction costs").
Core Conclusions
- Definition (clause 3.3.6 verbatim): "The combined trial-run fee means all costs required for full-load combined trial runs of complete equipment of the project's M&E works per the relevant standards, excluding commissioning costs payable within equipment installation costs." — the fee covers only full-load combined trial runs of complete M&E equipment; commissioning already inside equipment installation costs must not be double-charged.
- Content (verbatim): "including consumption of materials, fuel and power during the runs, plant and test-equipment use, tools and consumables, wages of personnel taking part, and other costs."
- Method (verbatim): "The combined trial-run fee is computed on the base of quota construction-installation costs at a rate of 0.04%", i.e. fee = quota construction-installation costs x 0.04%, applied uniformly in estimates and budgets.
- Base caliber: the base must be the "quota" construction-installation costs (per clause 3.1.1: quota direct costs + 40% of quota equipment purchase + measures + enterprise management + statutory fees + profit + tax + special costs, at quota base-period prices), not the compilation-period market-priced total — take the right column when filling forms.
- Classification: under section 3.3 "other works construction costs", computed and listed in the other-costs table of the estimate (budget) at the above base and rate.
Applicable Boundaries
- Only for highway estimate/budget compilation (JTG 3830-2018); not for railway (TB 10801-2024) or building/municipal (GB/T 50500) systems.
- Only where the project has M&E works requiring full-load combined trial runs per the relevant standards; commissioning already paid within equipment installation costs must not re-enter this fee.
- The base is quota construction-installation costs (base-period caliber), never actual (market-priced) costs.
- Investment-estimate stage follows JTG 3820-2018 "Measures for compiling investment estimates of highway construction projects" — not covered by this card.
Further Reading
Section 3.3 "other works construction costs" of JTG 3830-2018:
- Clause 3.3.5 special appraisal (assessment) fees: environmental impact assessment, soil-water conservation assessment, seismic safety evaluation, geological hazard assessment, overlain key mineral assessment, relics survey, navigation certification, flood certification, forest-land feasibility study, land pre-review report, project risk assessment, energy assessment and social risk assessment, radiation impact assessment, planning siting opinion etc., "charged per the commissioning contract or by reference to similar projects' actual costs";
- Clause 3.3.6 combined trial-run fee (this card);
- Clause 3.3.7 production-preparation costs: tools and instruments, office and living furniture, staff training and emergency traffic-keeping equipment for new/rebuilt projects to run normally after handover. The caliber of "quota construction-installation costs" is defined in clause 3.1.1; the Form 08 and total-budget tie-outs are in the companion form notes.
Keywords
- 联合试运转费
- norm-based cost of works
- 0.04%
- JTG 3830-2018
- 工程建设其他费用
- 机电工程
- administrative compilation rules for estimates and budgets