Content and pricing methods of preliminaries: the 2024 definition (clause 2.0.3), the listing basis (GB/T 50854-2024 annex R table R.1.1 preliminary items, code 011601), the three pricing methods of unit rate / lump sum / percentage rate and their preferred use (clauses 2.0.10 to 2.0.12, 3.2.1), the completion rules of annex E tables E.3.1 to E.3.4, and the non-competitive rule for statutory safety provisions (clause 3.2.5)

Preliminaries are 'project costs incurred in taking the relevant measures to complete the contract works, related to the cost of the works as a whole and to the performance of the contract, but unrelated to the cost of any individual divisional or sub-divisional work item' (GB/T 50500-2024 clause 2.0.3); their content is listed per annex R table R.1.1 of GB/T 50854-2024 (preliminary items, code 011601). The 2024 edition no longer splits 'lump-sum preliminaries / unit-rate preliminaries'; it prices by three methods - unit-rate pricing (quantity x all-in unit rate), lump-sum pricing (per item) and percentage-rate pricing (charging base x percentage rate) - and 'the pricing of the preliminaries BOQ should adopt the lump-sum method' (clause 3.2.1); special measures whose construction scheme the contract requires to pass expert panel review may instead be unit-rate priced and are then listed in the divisional/sub-divisional BOQ. The statutory safety provisions are a non-competitive item and must be priced per the provisions of the state and of the provincial or sector authorities (clause 3.2.5).

Applicable Codes

  • GB/T 50500-2024 第 2.0.3 条(措施项目术语)
  • GB/T 50500-2024 第 2.0.10~2.0.12 条(单价计价/总价计价/费率计价)
  • GB/T 50500-2024 第 3.2.1 条(措施项目清单计价方式)
  • GB/T 50500-2024 第 3.2.5 条(安全生产措施费不可竞争)
  • GB/T 50500-2024 第 6.2.13 条(措施项目费用分拆表)
  • GB/T 50500-2024 App. E Table E.3.1、Table E.3.2、Table E.3.3、Table E.3.4
  • GB/T 50854-2024 App. R Table R.1.1(措施项目,编码 011601)、App. R.2.1
  • GB 50500-2013 第 4.3.2 条(总价项目/单价项目二分,旧版对照)

Topic Scope

Answers 'what the preliminaries comprise, how each class is priced, and which items are non-competitive': under GB/T 50500-2024, the China national pricing standard for BOQ, and GB/T 50854-2024, the national quantity take-off standard for building and decoration works, this card gives the definition of preliminaries, the listing basis (annex R table R.1.1, code 011601), the definitions and preferred use of the three pricing methods (unit rate, lump sum, percentage rate), where the amounts land in annex E tables E.3.1 to E.3.4, and the non-competitive rule for statutory safety provisions.

Core Conclusions

1. Definition of preliminaries (clause 2.0.3, original wording)

Preliminary items are 'items arising in construction preparation, construction and acceptance for completing the construction of the project, in the technical, welfare, work-safety and environmental-protection respects; the costs so incurred are the preliminaries.' The term note further defines: 'preliminaries means project costs incurred in taking the relevant measures to complete the contract works, related to the cost of the works as a whole and to the performance of the contract, but unrelated to the cost of any individual divisional or sub-divisional work item.' Three points: (1) they relate to the works as a whole and to contract performance, not to any single divisional BOQ item; (2) they are collected under four respects - technical, welfare, work safety and environmental protection; (3) they must not be charged twice over, once here and once in the measured works.

2. Listing basis of the content schedule (GB/T 50854-2024 annex R)

'The item setting, units and work content of the preliminaries BOQ shall follow the provisions of table R.1.1. Table R.1.1 Preliminary items (code: 011601).' That is, the item names, units of measurement and work content of preliminary items are fixed by table R.1.1, all collected under the 011601 coding system; annex R sets only 'item setting, units and work content', with no item description content and no quantity take-off rules - preliminary items are measured 'per item', with no physical quantities computed from the drawings. Preliminary items not covered by table R.1.1 but shown on the employer's design drawings and required to be built accordingly follow annex R.2.1: 'supplementary codes may be assigned and the item listed by reference to divisional and sub-divisional works'.

3. The three pricing methods (clauses 2.0.10 to 2.0.12, original wording)

  • Unit-rate pricing: 'the pricing method in the bill of quantities in which the amount is computed as the quantity of works multiplied by the all-in unit rate.'
  • Lump-sum pricing: 'the pricing method in the bill of quantities in which the amount is computed as a lump sum with the item as the unit.'
  • Percentage-rate pricing: 'the pricing method in the bill of quantities in which the amount is computed as the charging base multiplied by the corresponding percentage rate.'

The term notes give the preferred use (note to clause 2.0.10): 'the BOQ pricing methods mainly comprise three: unit-rate, lump-sum and percentage-rate pricing. Divisional and sub-divisional items and dayworks items should use unit-rate pricing; the preliminaries BOQ should use lump-sum or percentage-rate pricing; provisional sums and specialist provisional-price items should use lump-sum pricing; main contractor's attendance and coordination provisions should use percentage-rate or lump-sum pricing.'

Clause 3.2.1: 'For the divisional/sub-divisional BOQ and the preliminaries BOQ, items priced by the unit-rate method shall be computed as their quantity of works multiplied by the corresponding all-in unit rate; items priced by the lump-sum method shall have their BOQ item price computed per item. The divisional/sub-divisional BOQ should use unit-rate pricing, and the preliminaries BOQ should use lump-sum pricing.' The closing paragraph gives the only outlet for quantity-based pricing: 'where the tenderer stipulates in the contract a construction scheme for special-measure items that must pass expert panel review, unit-rate pricing may be adopted, with the item listed in the divisional/sub-divisional BOQ and priced as the quantity of works multiplied by the corresponding all-in unit rate.' - that is, special measures needing quantity pricing no longer stay in the preliminaries BOQ as unit-rate preliminaries.

4. Where the costs land in the annex E tables

  • Table E.3.1, preliminaries BOQ pricing table: note - 'the cost composition of the preliminaries BOQ is detailed in table E.3.2 of this standard; the composition of the delivery, removal and erection costs of large plant is in table E.3.4 of this standard.'
  • Table E.3.2, composition analysis of the preliminaries BOQ: note - 'where percentage-rate pricing is used, the values of the charging base, percentage rate and price columns shall be filled in separately; where lump-sum pricing is used, only the price column need be filled.' - in practice, whether an item is priced by percentage rate or by lump sum is seen from whether the charging base and percentage rate columns must be filled.
  • Table E.3.3, preliminaries cost break-down table (clause 6.2.13): 'the preliminaries cost break-down table submitted by the tenderer with its tender shall, per table E.3.3 of annex E.3 of this standard, state for each preliminary item the initial set-up cost, the mid-term running cost and the later dismantling cost. The preliminaries cost break-down table may be applied to the claims pricing of chapter 8 of this standard and to the interim payments of chapter 9.'
  • The pricing method directly governs later adjustment: parts priced lump sum or by percentage rate are wrapped up and generally not re-measured or adjusted; only quantity-priced special measures moved into the divisional/sub-divisional BOQ are measured and priced as quantities increase or decrease.

5. The non-competitive item: statutory safety provisions (clause 3.2.5, original wording)

'The statutory safety provisions in the preliminaries BOQ shall be priced per the relevant provisions of the state and of the provincial or sector authorities in charge.' 'The statutory safety provisions in the preliminaries BOQ are non-competitive items; their pricing shall comply with the relevant provisions of the state and of the provincial or sector authorities in charge.' In practice: the item does not compete in tender discounting, may not be self-quoted by the enterprise, may not be given away or wrapped up or quoted at zero; the percentage rate and the charging base follow the current provisions of the provincial (sector) authority at the project location. Local pricing bases commonly split the mandatory HSE provisions into temporary facilities and site establishment, site order, environmental protection and work safety, applying a percentage rate to the total of divisional/sub-divisional works costs, with excess-progressive bands by project scale, and fixing the labour-cost share within the item (the actual rate levels, the four-way split and the band amounts must be taken from the current pricing bases of the province or city of the project, and must not be borrowed across provinces).

Applicable Boundaries

  • Applies to building and decoration works priced on the BOQ basis under GB/T 50500-2024 and GB/T 50854-2024; both are recommendatory standards, and where the contract provides otherwise the contract prevails.
  • The lump-sum / unit-rate dichotomy for preliminaries is the old approach of GB 50500-2013 (split by whether quantities can be computed); the 2024 edition classifies by pricing method, and new compilations must not carry over old codes (the 011701 system) onto the new tables.
  • Railway, highway and water conservancy works follow sector pricing rules; the rate and the charging base of the statutory work safety levy there differ (for example charged on the cost of works at a sector-fixed rate) and must not be mixed with the building-sector treatment.
  • Provincial rate levels, the four-way split and the band amounts are content of local pricing bases; this card gives only the general framework of content and method of calculation.

Further Reading

GB/T 50500-2024: clause 2.0.3 (terms: preliminary items and preliminaries); clauses 2.0.10 to 2.0.12 (unit-rate / lump-sum / percentage-rate pricing); clause 3.2.1 (preliminaries pricing methods and the special-measure outlet); clause 3.2.5 (statutory safety provisions non-competitive); clause 6.2.13 (preliminaries cost break-down table); annex E tables E.3.1 / E.3.2 / E.3.3 / E.3.4. GB/T 50854-2024: annex R table R.1.1 (preliminary items, code 011601); annex R.2.1 (supplementary coding by reference to divisional/sub-divisional works). Old-new comparison: GB 50500-2013 clause 4.3.2 (the lump-sum / unit-rate item dichotomy).