Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-25

The dividing line between unit-rate and lump-sum preliminaries in the bill of preliminaries: the 'whether quantities can be computed' binary test of GB 50500-2013 section 4.3, and how it is landed as itemisation and coding in GB 50854-2013 Annex S and GB/T 50854-2024 Annex R

The commentary to GB 50500-2013 clause 4.3.2 takes 'whether quantities can be computed' as the only express dividing line in the code: items whose quantities cannot be computed (site amenity and safety protection, temporary works, etc.) are priced per item and called lump-sum items, while items whose quantities can be computed (scaffolding, dewatering, etc.) are priced by quantity and called unit-rate items. GB 50854-2013 clause 4.3.1 (a mandatory provision) requires preliminaries in Annex S that carry an item description, unit of measurement and measurement rule to be itemised in the measured-works manner (all five elements present), and clause 4.3.2 requires items given a code and name only to be set per the Annex S code and name (priced per item). From GB/T 50500-2024 the binary naming is dropped in favour of three pricing methods - unit-rate pricing, lump-sum pricing and percentage-rate pricing (clauses 2.0.10~2.0.12) - with the preliminaries bill preferably lump-sum priced (clause 3.2.1); GB/T 50854-2024 Annex R codes all preliminaries 011601, and concrete formwork moves into the measured works (Annex E, table E.5.1, code 010505).

Applicable Codes

  • GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第 4.3.1 条(强制性条文)、第 4.3.2 条及条文说明
  • GB 50854-2013 · Code for Measurement of Quantities of Building and Decoration Works 第 4.2.7 条、第 4.3.1 条(强制性条文)、第 4.3.2 条、App. S Table S.1/S.2/S.3/S.5/S.6/S.7
  • GB/T 50854-2024 · Standard for measurement of building construction and fitting out works 第 4.3.1 条、App. R Table R.1.1(011601)、R.2.2、R.2.3、App. E Table E.5.1(010505)
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 2.0.10~2.0.12 条、第 3.2.1 条、第 4.2.5 条
  • TB 10801-2024 第 3.11.11 条(铁路口径:安全文明施工费对应安全生产费)

Positioning

Answers 'by what line the bill of preliminaries splits into unit-rate and lump-sum preliminaries', and shows how that line lands, in the pricing code (GB 50500-2013 section 4.3) and the measurement code and standard (GB 50854-2013 Annex S; GB/T 50854-2024 Annex R), as operable itemisation rules and codes - for use when compiling the tender BOQ, pricing a bid or reconciling quantities, to judge whether a preliminary is listed under 'quantity' or under 'item'.

Core conclusions

1. The line itself: the only express test is 'whether quantities can be computed' (GB 50500-2013 section 4.3)

Clause 4.3.1 (a mandatory provision), verbatim: 'the bill of preliminaries must be compiled in accordance with the provisions of the current national measurement code for the relevant works.' Commentary: 'as the current national measurement codes have taken the preliminaries into the codes, this clause requires the bill of preliminaries to be compiled per the provisions of the current national measurement code for the relevant works. This is a mandatory provision and must be strictly executed.'

Clause 4.3.2, verbatim: 'the bill of preliminaries shall list its items according to the actual circumstances of the proposed works.' Its commentary is the code-level source of the unit-rate / lump-sum binary, verbatim: 'compiling the bill of preliminaries calls many factors into account - beyond the works themselves, hydrology, weather, environment, safety and so on. As too many factors govern what preliminaries are set, the measurement codes cannot list one by one every preliminary that may arise during construction. When compiling the bill, should preliminaries appear that the annex of the measurement code does not list, the bill may be supplemented according to the circumstances of the works. The measurement codes divide preliminaries into two classes: those whose quantities cannot be computed, such as site amenity and safety protection and temporary works, are priced per item and called lump-sum items; those whose quantities can be computed, such as scaffolding and dewatering works, are priced by quantity - which serves better to determine and adjust the preliminaries - and are called unit-rate items.'

2. Landing the line: judge by 'whether the measurement code gives all five elements' (GB 50854-2013 section 4.3)

Clause 4.3.1 (a mandatory provision), verbatim: 'for preliminaries for which the item code, item name, item description, unit of measurement and measurement rule are listed, the bill of quantities shall be compiled under clause 4.2 of this code for the measured works.' The commentary makes clear that preliminaries are compiled for the BOQ just like measured works - the item code, item name, item description and unit of measurement must all be listed, with measurement, coding, description, unit and measurement rule per section 4.2. -> Annex S items carrying the full set of code + name + description + unit + measurement rule are unit-rate preliminaries, itemised in the measured-works manner.

Clause 4.3.2, verbatim: 'for preliminaries for which only the item code and item name are listed, without item description, unit of measurement or measurement rule, the bill of quantities shall be compiled by the item codes and item names prescribed in Annex S, preliminaries, of this code.' -> Items given a code and a name only - no description, no unit, no measurement rule - are lump-sum preliminaries, listed per item.

3. Three-axis classification table (2013 edition basis)

Annex S code Preliminary Measurable (description / unit / rule given)? Varies with the physical quantity? Listing and pricing
011701 Scaffolding works (table S.1) Measurable Varies with physical scale, erected area / length Unit-rate preliminary: five elements complete; quantity x all-in unit rate
011702 Concrete formwork and supports (table S.2) Measurable (in m2) Varies with the physical concrete quantity Unit-rate preliminary; but either/or against the measured works, see the next item
011703 Vertical transport (table S.3) Measurable Varies with physical quantity and duration Unit-rate preliminary
011705 Mobilisation and erection / dismantling of large plant (table S.5) Measurable (per machine-trip / per item per the table rules) Varies with the execution plan and plant configuration Unit-rate preliminary
011706 Construction drainage and dewatering (table S.6) Measurable Varies with hydrology and quantities Unit-rate preliminary
011707 Mandatory HSE and other preliminaries (table S.7) Not measurable (code and name only; scope as listed in the table) Taken by works scale / percentage rate, not item by item with physical quantity Lump-sum preliminary: priced per item; the mandatory HSE provisions taken per the rules of the State or of the provincial or industry authorities

4. The special rule for concrete formwork (GB 50854-2013 clause 4.2.7, a trap)

Key points, verbatim: the 'work content' of cast-in-place concrete items includes formwork work, while a cast-in-place concrete formwork item is also listed separately under preliminaries - 'the tenderer shall choose according to the actual circumstances of the works. If the tenderer does not list a cast-in-place concrete formwork item in the bill of preliminaries, formwork is not listed separately, and the all-in unit rate of the cast-in-place concrete item shall include the formwork cost.' The commentary sums up three layers: first, within one tender section (or contract section) the tenderer must choose one of the two ways; second, if formwork is listed separately, it must carry the unit of measurement, item code and item description prescribed by the code, and the cast-in-place concrete item carries no formwork cost; third, if it is not listed separately, no formwork bill is compiled, which means the all-in unit rate of the concrete item already contains the formwork cost.

5. The change of basis in the 2024 edition (the two code systems must not be mixed)

  • Pricing standard: GB/T 50500-2024 clauses 2.0.10~2.0.12 define only three pricing methods - 'unit-rate pricing: the pricing method under which, in the bill of quantities, the price is computed as quantity x all-in unit rate'; 'lump-sum pricing: the pricing method under which, in the bill of quantities, the price is computed as a total price per item'; 'percentage-rate pricing: the pricing method under which, in the bill of quantities, the price is computed as charging base x the matching percentage rate'; and all three state uniformly that 'the bill of preliminaries should adopt lump-sum pricing or percentage-rate pricing'. Clause 3.2.1: 'the measured-works item list should adopt unit-rate pricing, and the bill of preliminaries should adopt lump-sum pricing.' The same clause also provides: 'where the tenderer agrees in the contract that the execution plan of dedicated preliminaries must pass expert panel review, unit-rate pricing may be adopted, with the items listed in the measured-works item list and priced as quantity x the matching all-in unit rate.' -> the 2024 edition no longer draws the line at 'measurable or not'; measurable dedicated preliminaries move into the measured-works list.
  • Measurement standard: GB/T 50854-2024 Annex R table R.1.1, preliminaries (code 011601); clause 4.3.1: 'when compiling the bill of quantities, the preliminaries of Annex R of this standard shall be set by the prescribed item code, item name and work content.' The commentary notes that 'this clause provides that preliminaries are listed by the prescribed item code, item name and work content' - that is, listed by code, name and work content only, with item description, unit of measurement and measurement rule no longer mentioned.
  • Scope: the notes to Annex R state that 'scaffolding' covers all scaffolds erected during construction as required by the relevant codes and to meet the work needs; 'vertical transport' covers only the large vertical hauling plant used during construction - vertical transport performed with other lifting plant and manual aids is included in the work content of the related measured-work items.
  • Where the formwork went: GB/T 50854-2024 Annex E table E.5.1, concrete formwork (code 010505), is now an item of the concrete and reinforced-concrete works, no longer in the preliminaries annex.
  • Compilation requirements: GB/T 50500-2024 clause 4.2.5 requires the bill of preliminaries to be compiled 'in the light of the actual circumstances of the tendered works and the relevant provisions of the authorities, on the basis of the conventional construction process and sequence and the requirements of a non-physical nature - welfare, safety, environmental protection, temporary works and site amenity - and per the classification rules for preliminaries of the national and industry measurement standards for the relevant works and any supplementary measurement rules, together with the tender documents and the contract clauses. Statutory work safety provision items shall be listed per the management requirements of the State and of the provincial and industry authorities and the actual circumstances of the tendered works'; bidders may re-check the completeness and suitability of the listing on a site visit and decide for themselves whether to add items and prices.

6. The classification workflow (reusable)

(1) Check the annex of the measurement code or standard on which the compilation is based - item description + unit of measurement + measurement rule given -> a unit-rate preliminary, itemised in the measured-works manner with all five elements; code + name only -> a lump-sum preliminary, listed per item. (2) Check whether the item rises and falls with the physical quantity - what varies with quantity suits pricing by quantity; what does not suits pricing per item or by percentage rate. (3) Check which edition applies - under the 2024 edition everything is lump-sum or percentage-rate pricing, and measurable dedicated preliminaries that pass expert panel review move into the measured-works list; the code systems (011701~011707 versus 011601 and 010505) switch with the edition and must not be mixed. (4) Safety (site amenity) preliminaries are non-competitively priced under every edition, listed and taken per the requirements of the State and of the provincial and industry authorities - the quantity-variation adjustment logic of measurable preliminaries does not apply.

Application boundaries

  • Applies to building, decoration and like BOQ-priced works governed by the China BOQ pricing code and standard; other sectors follow their own measurement and pricing bases (in railway works the 'mandatory HSE provisions' correspond to the 'statutory work safety levy', see TB 10801-2024 clause 3.11.11, under a different charging basis).
  • Edition boundary: GB 50500-2013 and GB 50854-2013 are mandatory codes (with mandatory provisions); GB/T 50500-2024 and GB/T 50854-2024 are recommended standards - during the transition the applicable edition follows the contract or the tender documents, and the codes and itemisation elements of the two editions must not be crossed.
  • 'Whether quantities can be computed' is the only express line of the 2013 edition; the 2024 edition no longer uses it, nor the names 'unit-rate preliminaries' and 'lump-sum preliminaries' - state the edition relied on before citing, or the pricing basis and the codes will not match.
  • Whether concrete formwork sits 'inside the measured-works rate' or is 'listed separately under preliminaries' must be one-or-the-other within one tender section (or contract section); it must not differ from section to section of the same project, nor may formwork be listed again beside a concrete all-in unit rate that already includes it.
  • The split of responsibility for the completeness and suitability of the preliminaries listing, and whether preliminaries may be adjusted on variation, follow separate rules, unchanged by this classification.

Further reading

  • GB 50500-2013, the China BOQ pricing code: section 4.3 - clause 4.3.1 (mandatory; the bill of preliminaries must be compiled per the measurement code) and clause 4.3.2 with its commentary (the original source of the 'measurable or not' binary); companion pricing clauses 6.2.3 and 6.2.4.
  • GB 50854-2013, the measurement code for building and decoration works: clause 4.2.7 (the cast-in-place formwork either/or); clause 4.3.1 (mandatory; items carrying a measurement rule listed per section 4.2); clause 4.3.2 (items given code and name only set per Annex S); the Annex S tables - S.1 scaffolding works (011701); S.2 concrete formwork and supports (011702); S.3 vertical transport (011703); S.5 mobilisation and erection / dismantling of large plant (011705); S.6 construction drainage and dewatering (011706); S.7 mandatory HSE and other preliminaries (011707).
  • GB/T 50854-2024, the measurement standard for building and decoration works: clause 4.3.1; Annex R table R.1.1 (011601), R.2.2 (scaffolding scope) and R.2.3 (vertical transport scope); Annex E table E.5.1 concrete formwork (010505).
  • GB/T 50500-2024: clauses 2.0.10~2.0.12 (the three pricing methods); clause 3.2.1 (preliminaries suit lump-sum pricing; expert-reviewed dedicated preliminaries listed in the measured works); clause 4.2.5 (compilation basis for the bill of preliminaries; listing of statutory work safety provision items).
  • Directions for further reading: the measurement and adjustment of preliminaries (the exceptions to no-adjustment; the rules for setting all-in unit rates on variation); the non-competitive character of the mandatory HSE provisions and the statutory work safety levy.