Bill of preliminaries classification basis difference between GB/T 50500-2024 and GB 50500-2013: two-way split by measurability vs three pricing methods (unit-rate/lump-sum/percentage-rate)
GB 50500-2013 split preliminary items by 'whether quantities can be computed' into lump-sum items (priced per lump item, e.g., mandatory health, safety and environmental (HSE) provisions, temporary works and site establishment costs) and unit-rate items (quantity × all-in unit rate, e.g., scaffolding, dewatering), encouraging unit-rate pricing of measurable preliminary items; GB/T 50500-2024 abolishes the 'unit-rate/lump-sum preliminary items' dichotomy, replacing it with three pricing methods (clauses 2.0.10–2.0.12): unit-rate pricing, lump-sum pricing, and percentage-rate based pricing — and the recommended direction reverses: bills of preliminaries should use lump-sum pricing (3.2.1); special preliminary items genuinely requiring quantity-based pricing (and subject to expert panel review) move into the work-items list for itemization and pricing; percentage-rate based pricing gains formal terminology status (3.1.5, Appendix E Table E.3.2).
Applicable Codes
- GB 50500-2013 建设工程工程量清单计价规范 第4.3.2、6.2.3、6.2.4条
- GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.10~2.0.12、3.1.5、3.2.1条及App. ETable E.3.2
Topic Positioning
Comparing the bill of preliminaries classification and pricing bases of GB 50500-2013 (mandatory GB) and GB/T 50500-2024 (recommended GB/T): 2013 used a two-way split by 'whether quantities can be computed' (lump-sum items / unit-rate items); 2024 uses a three-way split by 'price calculation method' (unit-rate / lump-sum / percentage-rate based pricing). Answers why the 'unit-rate/lump-sum preliminary items' dichotomy disappeared and how the new basis operates.
Core Conclusions
(1) 2013 basis (GB 50500-2013 4.3.2, mandatory): the classification axis is 'whether quantities can be computed'. Original: 'The measurement code divides preliminary items into two classes: items whose quantities cannot be computed, such as mandatory health, safety and environmental (HSE) provisions, and temporary works and site establishment costs, are priced per 'lump item' — lump-sum items; items whose quantities can be computed, such as scaffolding and dewatering, are priced by 'quantity', which better determines and adjusts preliminary costs — unit-rate items.' Companion pricing rules (both mandatory): unit-rate items determine all-in unit rates per tender documents and item description (work item specification), i.e., quantity × all-in unit rate (6.2.3); lump-sum item amounts are set autonomously per tender documents and the project execution plan (construction methodology and site organization) or construction method statement prepared at tender stage, with mandatory health, safety and environmental (HSE) provisions determined in accordance with state, provincial or sector construction authority regulations (6.2.4 — in practice the 'base to which percentage rates are applied × percentage rate' parameter method).
(2) 2024 basis (GB/T 50500-2024): at the terminology level the dichotomy is abolished, defining only three pricing methods — 2.0.10 'unit-rate pricing: the pricing method in a bill of quantities (BOQ) by which price is calculated as quantity × all-in unit rate'; 2.0.11 'lump-sum pricing: the pricing method in a BOQ by which price is calculated per lump item at a lump sum'; 2.0.12 'percentage-rate based pricing: the pricing method in a BOQ by which price is calculated as the base to which percentage rates are applied × the corresponding percentage rate'; and uniformly states 'bills of preliminaries should adopt lump-sum pricing or percentage-rate based pricing'.
(3) Recommended direction reversed: 3.2.1 — 'bills of work items should adopt unit-rate pricing; bills of preliminaries should adopt lump-sum pricing' — 2013 encouraged quantity-based unit-rate pricing of measurable preliminary items; 2024 shifts to lump-sum predominance.
(4) Destination of measurable special preliminary items: the second half of 3.2.1 — 'where the employer stipulates in the contract that special preliminary item construction method statements must pass expert panel review, unit-rate pricing may be used, itemized in the work-items list, priced as quantity × all-in unit rate' — special preliminary items genuinely needing quantity-based pricing no longer remain in the bill of preliminaries as 'unit-rate preliminary items' but move into the work-items list.
(5) Percentage-rate based pricing formalized: 3.1.5 permits percentage-rate based pricing or other methods where unit-rate/lump-sum pricing is unsuitable given the nature of the project, with pricing requirements and price adjustment rules to be explained in tender and contract documents; Appendix E Table E.3.2 (bill of preliminaries composition breakdown analysis) notes — 'for percentage-rate based pricing, fill in the 'base to which percentage rates are applied', 'percentage rate', and 'price' columns; for lump-sum pricing, only the 'price' column may be filled' — the parameter method used in practice for 2013 'lump-sum items' gains formal institutional status in 2024.
(6) Difference mapping: standard nature mandatory (GB) -> recommended (GB/T); classification axis 'measurability' -> 'price calculation method'; terms 'unit-rate/lump-sum preliminary items' -> no dichotomy; recommended preliminary pricing 'measurable items preferably unit-rated' -> 'preferably lump-sum or percentage-rate based pricing'; measurable special preliminary items 'kept in bill of preliminaries as unit-rate items' -> 'expert-panel-reviewed special preliminary items using unit-rate pricing go into the work-items list'; percentage-rate charging 'practical parameter method, no formal term' -> 'formally one of the three pricing methods (2.0.12, 3.1.5)'.
Applicable Boundaries
- Applies only to works executing the BOQ pricing code/standard (building & decoration, etc.); railway and other sector works follow sector pricing bases (e.g., TB 10801-2024, where 'mandatory health, safety and environmental (HSE) provisions' corresponds to 'statutory work safety levy (earmarked funds)' with different calculation bases).
- 2013 was a mandatory code (GB with mandatory provisions of codes), 2024 is recommended (GB/T); during coexistence, the applicable edition is set by the contract or tender documents.
- Completeness and accuracy of the bill of preliminaries remain the tenderer's responsibility; mandatory health, safety and environmental (HSE) provisions (railway: statutory work safety levy (earmarked funds)) are non-competitive and do not follow general adjustment rules for lump sums.
- The classification basis change directly affects adjustment rules: lump-sum-priced preliminary items lock price per lump item, generally not re-measured or adjusted (7.3.1 lists exceptions only); unit-rate-priced special preliminary items follow quantity changes with variation re-rating of unit rates rules.
Further Reading
- GB 50500-2013: 4.3.2 (preparation of the bill of preliminaries, mandatory), 6.2.3 and 6.2.4 (pricing rules for unit-rate/lump-sum items in tenders (priced offers), mandatory).
- GB/T 50500-2024: 2.0.10-2.0.12 (terms: unit-rate/lump-sum/percentage-rate based pricing), 3.1.5 (method selection), 3.2.1 (pricing methods for work-items and bill of preliminaries), Appendix E Table E.3.2 (bill of preliminaries composition breakdown analysis).
- Extension: preliminaries adjustment rules in 7.3.1 and Section 8.9; bill of preliminaries responsibility allocation in 6.1.5.
- Related standard evolution: GB/T 50854-2024 (effective 2025-09-01) restructured per-item calculation of preliminary items; GB 50854-2013 abolished.
Keywords
- bill of preliminaries
- 单价措施
- 总价措施
- 单价计价
- lump-sum pricing
- percentage-rate based pricing
- 50500-2024
- 50500-2013