Risk allocation and adjustment rules for preliminaries (measure) costs: GB 50500-2013 vs GB/T 50500-2024 (omitted items, scheme changes, lump sum plus exceptions)

The 2024 edition restructures preliminaries as "lump sum plus exceptions": completeness/accuracy of the preliminaries list is the contractor's responsibility under both unit-price and lump-sum contracts (3.1.8); omitted items are no longer adjustable except the safety-measures cost and formwork/temporary works listed in the work-item list (8.2.2/8.2.3), whereas under 2013 list omissions were the tenderer's liability (4.1.2, mandatory) and missing preliminaries could be added via an approved scheme (9.5.3). "All preliminaries risk on the contractor" is inaccurate - exceptions like variations, unforeseen provisional-sum works, and employer causes still cost the employer (3.3.7), but only via "submit scheme before execution + mutual confirmation" (8.9.6/8.9.7), failing which the right is forfeited.

Applicable Codes

  • GB 50500-2013 建设工程工程量清单计价规范(第4.1.2、9.3.1~9.3.2、9.5.3条,已废止)
  • GB/T 50500-2024 建设工程工程量清单计价标准(第3.1.8、3.3.3、3.3.7、6.1.5、7.3.1、8.2.2~8.2.3、8.9.4~8.9.7条)

Topic Positioning

Comparing GB 50500-2013 (repealed 2025-09-01) and GB/T 50500-2024 (effective 2025-09-01) on allocation and adjustment of preliminaries costs: omitted list items, extra cost from scheme changes, measurement-adjustment exceptions - answering "is all preliminaries risk on the contractor?"

Core Conclusions

The 2024 edition makes preliminaries "lump-sum priced + statutory exceptions", pushing the bulk of risk to the contractor - but not unconditionally "all on the contractor".

I. Liability for list omissions (the biggest difference)

  • 2013 4.1.2 (mandatory): "The tender BOQ must form part of the tender documents; its accuracy and completeness are the tenderer's responsibility."
  • 2024 3.1.8: work-item lists split by contract type (unit-price: employer; lump-sum: contractor), but "whether unit-price or lump-sum, the completeness of preliminaries listing and accuracy of pricing are the contractor's responsibility; bidders may add items and prices at their discretion and bear the risk of their own pricing."
  • 2024 6.1.5: bidders shall review completeness and applicability of the preliminaries list within the time allowed, may add items/prices, are responsible for accuracy and completeness, and bear pricing-reasonableness risk.

II. Can omitted preliminaries be paid?

  • 2013 9.5.3: "Where the tender BOQ omits a preliminaries item, the contractor shall submit an implementation scheme for approval and adjust the contract price per 9.3.1/9.3.2" - yes.
  • 2024 8.2.2 (unit-price): "except safety-measures items per contract, formwork and temporary works listed in the work-item list, and contractually measurable preliminaries which shall be adjusted, other preliminaries are not adjusted for BOQ defects"; lump-sum per 8.2.3 - price and duration unadjusted for list defects. Essentially no pay for omissions, except the safety cost and measurables like formwork/temporary works listed in the work-item list.

III. Scheme changes (variations) adding cost

  • 2013 9.3.2: when a variation changes the scheme and preliminaries, the contractor shall submit the intended scheme to the employer beforehand with detailed changes; safety costs recalculated per 3.1.5; unit-priced preliminaries per 9.3.1; lump-sum (or coefficient) preliminaries adjusted by actual amount times the contractor's bid fluctuation rate per 9.3.1; failure to submit beforehand is deemed no adjustment or waiver.
  • 2024 8.9.6: when a variation substantively changes scope, duration, quality, or specifications and alters preliminaries, the disadvantaged party shall submit the intended scheme to the other before execution with a detailed comparison; upon mutual confirmation, adjust per 8.9.4/8.9.5.
  • 2024 8.9.7: if the disadvantaged party does not claim within the agreed time, no change or waiver is presumed; if the other party does not confirm or comment in time, approval is presumed.

IV. Lump-sum pricing and employer-paid exceptions (2024 3.3.7) The contractor's bid scheme is deemed reasonable and feasible; preliminaries are lump-sum, and the contractor bears increases from its own scheme adjustments; if its scheme proves unfeasible or beyond its capacity, increases are its own. Only these are adjustable per Chapter 8 at the employer's cost: (1) variations; (2) provisional-sum works not fully foreseen or specified; (3) employer-caused delayed use, removal/re-installation, addition, or duplicate provision of preliminaries; (4) substantive duration changes from variations, provisional sums, or employer causes affecting or adding preliminaries.

V. Contractor's self-borne risk list (2024 3.3.3) Item 1 is "accuracy and completeness of the preliminaries list"; also lump-sum BOQ defects, self-caused scheme changes, cost increases from own machinery/technology/management, self-caused acceleration/suspension, and movements within agreed price bands. The contractor bears its own technical/management risks (e.g., management fee) and agreed market risks, but not legal/regulatory changes.

VI. Measurement-adjustment exceptions narrowed to five (2024 7.3.1) Absent contrary agreement, priced preliminaries are not re-measured, except: (1) preliminaries works listed in the work-item list and contractually measurable items (7.2.1/7.2.2); (2) safety-measures costs per contract; (3) variation-induced changes (7.4.4); (4) BOQ-defect changes (8.2.2/8.2.3); (5) provisional-sum works not fully foreseen or specified (7.7.2). Preliminaries within specialist prime-sum subcontracts are included in the subcontract lump sum - no double measurement.

Applicable Boundaries

  • Compares the two national standards: GB 50500-2013 repealed 2025-09-01; GB/T 50500-2024 effective the same day; signed contracts follow their terms and the standard in force at signing.
  • 2024 is recommended (GB/T), 2013 was mandatory (with bold clauses); execution follows tender documents and contracts; the MOHURD announcement requires implementation per the new standard.
  • "All preliminaries on the contractor" is inaccurate: variations, unforeseen provisional-sum works, and employer causes (delayed use/removal/addition/duplicate provision, substantive duration changes) still cost the employer - but the contractor must follow "scheme before execution + mutual confirmation", failing which it forfeits.
  • Excludes the 15% work-quantity adjustment boundary, material price adjustment, and zero-priced preliminaries - see related cards.

Further Reading

  • GB 50500-2013: 4.1.2 (mandatory), 9.3.1-9.3.2, 9.5.3 (repealed; comparison only).
  • GB/T 50500-2024: 3.1.8, 3.3.3, 3.3.7, 6.1.5, 7.3.1, 8.2.2-8.2.3, 8.9.4-8.9.7.
  • Companion reading: tender-BOQ liability comparison, the 2024 three-mode preliminaries pricing classification, bid-stage completeness responsibility.