Difference between unit-rate preliminary items and lump-sum preliminary items, and the rules for adjusting preliminaries on a variation

GB/T 50500-2024 no longer uses the "unit-rate preliminary items / lump-sum preliminary items" dichotomy, classifying instead by three pricing methods — unit-rate pricing, lump-sum pricing and percentage-rate based pricing — and preliminary items should preferably be priced on a lump-sum basis (§2.0.10, 3.2.1); lump-sum preliminary items are price-locked and are generally not subject to measurement adjustments (§7.3.1, only five exceptions); unit-rate preliminary items follow quantities with the rate varying, adjusted per the variation all-in unit rate rules (§8.9.1); adjusting preliminaries on a variation requires submitting a scheme for confirmation before implementation (§8.9.6), and late submission is deemed waiver of the right (§8.9.7).

Applicable Codes

  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. R(R.1.1 Table R.1.1 措施项目 code 011601、R.2.1、R.2.2、R.2.3)
  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. E Table E.5.1 混凝土模板(code 010505)
  • GB/T 50500-2024 建设工程工程量清单计价标准 §2.0.10、§2.0.12、§3.2.1、§3.3.7
  • GB/T 50500-2024 §5.2.5、§6.1.5、§6.2.12、§6.2.13
  • GB/T 50500-2024 §7.3.1、§7.4.4、§8.9.1、§8.9.4、§8.9.5、§8.9.6、§8.9.7
  • GB/T 50500-2024 App. E Table E.3.1~Table E.3.4
  • TB 10801-2024 第3.11.11条(铁路"安全生产费"对应"安全文明施工费")
  • GB 50500-2013、GB 50854-2013 App. S(旧版单价措施/总价措施二分口径,已被2024版替代)

Topic Positioning

This card clarifies the distinction between "unit-rate preliminary items vs lump-sum preliminary items" (mapping the 2013 terms to the 2024 three pricing methods) and whether, how, and through what procedure preliminaries can be adjusted on a variation, for tender (priced offer) pricing, stage settlement during construction, and variation/claim practice on BOQ-priced projects.

Core Conclusions

① Term mapping: the 2024 edition drops the "unit-rate preliminary items / lump-sum preliminary items" dichotomy in favour of three pricing methods — unit-rate pricing, lump-sum pricing and percentage-rate based pricing (§2.0.10, 2.0.11) — and the pricing of the bill of preliminaries should preferably adopt lump-sum pricing (§3.2.1). The former "unit-rate preliminary items" = measurable, quantity × all-in unit rate (scaffolding, formwork supports, vertical transport, plant mobilisation/demobilisation, dewatering and drainage, etc.); "lump-sum preliminary items" = lump sums per item or on a calculation basis × percentage rate (mandatory health, safety and environmental (HSE) provisions, night work, secondary handling, winter/rainy season work, temporary works and site establishment costs, etc.). ② General adjustment principle (§7.3.1): preliminary items are in principle not subject to measurement adjustments, with only five exceptions — preliminary works itemised in the work sections of the BOQ and contract-agreed measurable items, statutory safety provisions executed per the contract, preliminary item changes caused by a variation, those caused by BOQ errors or omissions, and those caused by insufficiently foreseen works within provisional sums. ③ Measurable preliminary items follow the variation all-in unit rate rules (§8.9.1: contract rate for identical conditions, conversion for similar conditions, negotiation for different conditions); schedule changes are adjustable only where the critical path is substantively extended or shortened, calculated as the mid-term running cost of the preliminary items in the §6.2.13 breakdown table × number of days (§8.9.4); newly added preliminary items are measured and priced by actual plant shifts/quantities (§8.9.5); substantive changes (scope, schedule, quality, technical requirements) require submission of an implementation scheme for the other party's confirmation before execution (§8.9.6). ④ Procedure and time limits (§8.9.7): late submission of a scheme or of an additional-cost request by the contractor → the preliminaries are deemed unchanged and the right is waived; late review by the employer → deemed acceptance. ⑤ The mandatory health, safety and environmental (HSE) provisions (called the statutory work safety levy (earmarked funds) on railways) are executed per the contract and do not follow the other variation rules.

Applicable Boundaries

Applies to general tendering/awarding projects priced on a bill of quantities basis; GB/T 50500-2024 is a recommended standard — special contract terms prevail; regional cost data standards may divide the "unit-rate/lump-sum preliminary item" lists differently, but the pricing and variation rules are substantively identical; railway and other sector works follow sector pricing rules. This card is a rule guide; specific amounts follow the contract and the standard text.

Further Reading

See GB/T 50500-2024: §2.0.10, 2.0.11 (pricing method terms), §3.2.1 (preliminary items preferably lump-sum priced), §6.2.13 (preliminaries breakdown table), §7.3.1 (measurement adjustment exceptions), §7.4.4 (non-critical path not measured), §8.9.1, 8.9.4–8.9.7 (variation adjustment and procedure time limits); old/new comparison with GB 50500-2013; for the railway statutory work safety levy see TB 10801-2024 Clause 3.11.11.

Keywords

  • 单价措施项目
  • 总价措施项目
  • 措施项目编码 011601
  • 混凝土模板 010505
  • 措施项目清单构成明细分析表
  • 措施项目费用分拆表
  • 单价计价 总价计价 费率计价
  • 措施项目包干 计量调整