Difference between unit-rate preliminary items and lump-sum preliminary items, and the rules for adjusting preliminaries on a variation
GB/T 50500-2024 no longer uses the "unit-rate preliminary items / lump-sum preliminary items" dichotomy, classifying instead by three pricing methods — unit-rate pricing, lump-sum pricing and percentage-rate based pricing — and preliminary items should preferably be priced on a lump-sum basis (§2.0.10, 3.2.1); lump-sum preliminary items are price-locked and are generally not subject to measurement adjustments (§7.3.1, only five exceptions); unit-rate preliminary items follow quantities with the rate varying, adjusted per the variation all-in unit rate rules (§8.9.1); adjusting preliminaries on a variation requires submitting a scheme for confirmation before implementation (§8.9.6), and late submission is deemed waiver of the right (§8.9.7).
Applicable Codes
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. R(R.1.1 Table R.1.1 措施项目 code 011601、R.2.1、R.2.2、R.2.3)
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. E Table E.5.1 混凝土模板(code 010505)
- GB/T 50500-2024 建设工程工程量清单计价标准 §2.0.10、§2.0.12、§3.2.1、§3.3.7
- GB/T 50500-2024 §5.2.5、§6.1.5、§6.2.12、§6.2.13
- GB/T 50500-2024 §7.3.1、§7.4.4、§8.9.1、§8.9.4、§8.9.5、§8.9.6、§8.9.7
- GB/T 50500-2024 App. E Table E.3.1~Table E.3.4
- TB 10801-2024 第3.11.11条(铁路"安全生产费"对应"安全文明施工费")
- GB 50500-2013、GB 50854-2013 App. S(旧版单价措施/总价措施二分口径,已被2024版替代)
Topic Positioning
This card clarifies the distinction between "unit-rate preliminary items vs lump-sum preliminary items" (mapping the 2013 terms to the 2024 three pricing methods) and whether, how, and through what procedure preliminaries can be adjusted on a variation, for tender (priced offer) pricing, stage settlement during construction, and variation/claim practice on BOQ-priced projects.
Core Conclusions
① Term mapping: the 2024 edition drops the "unit-rate preliminary items / lump-sum preliminary items" dichotomy in favour of three pricing methods — unit-rate pricing, lump-sum pricing and percentage-rate based pricing (§2.0.10, 2.0.11) — and the pricing of the bill of preliminaries should preferably adopt lump-sum pricing (§3.2.1). The former "unit-rate preliminary items" = measurable, quantity × all-in unit rate (scaffolding, formwork supports, vertical transport, plant mobilisation/demobilisation, dewatering and drainage, etc.); "lump-sum preliminary items" = lump sums per item or on a calculation basis × percentage rate (mandatory health, safety and environmental (HSE) provisions, night work, secondary handling, winter/rainy season work, temporary works and site establishment costs, etc.). ② General adjustment principle (§7.3.1): preliminary items are in principle not subject to measurement adjustments, with only five exceptions — preliminary works itemised in the work sections of the BOQ and contract-agreed measurable items, statutory safety provisions executed per the contract, preliminary item changes caused by a variation, those caused by BOQ errors or omissions, and those caused by insufficiently foreseen works within provisional sums. ③ Measurable preliminary items follow the variation all-in unit rate rules (§8.9.1: contract rate for identical conditions, conversion for similar conditions, negotiation for different conditions); schedule changes are adjustable only where the critical path is substantively extended or shortened, calculated as the mid-term running cost of the preliminary items in the §6.2.13 breakdown table × number of days (§8.9.4); newly added preliminary items are measured and priced by actual plant shifts/quantities (§8.9.5); substantive changes (scope, schedule, quality, technical requirements) require submission of an implementation scheme for the other party's confirmation before execution (§8.9.6). ④ Procedure and time limits (§8.9.7): late submission of a scheme or of an additional-cost request by the contractor → the preliminaries are deemed unchanged and the right is waived; late review by the employer → deemed acceptance. ⑤ The mandatory health, safety and environmental (HSE) provisions (called the statutory work safety levy (earmarked funds) on railways) are executed per the contract and do not follow the other variation rules.
Applicable Boundaries
Applies to general tendering/awarding projects priced on a bill of quantities basis; GB/T 50500-2024 is a recommended standard — special contract terms prevail; regional cost data standards may divide the "unit-rate/lump-sum preliminary item" lists differently, but the pricing and variation rules are substantively identical; railway and other sector works follow sector pricing rules. This card is a rule guide; specific amounts follow the contract and the standard text.
Further Reading
See GB/T 50500-2024: §2.0.10, 2.0.11 (pricing method terms), §3.2.1 (preliminary items preferably lump-sum priced), §6.2.13 (preliminaries breakdown table), §7.3.1 (measurement adjustment exceptions), §7.4.4 (non-critical path not measured), §8.9.1, 8.9.4–8.9.7 (variation adjustment and procedure time limits); old/new comparison with GB 50500-2013; for the railway statutory work safety levy see TB 10801-2024 Clause 3.11.11.
Keywords
- 单价措施项目
- 总价措施项目
- 措施项目编码 011601
- 混凝土模板 010505
- 措施项目清单构成明细分析表
- 措施项目费用分拆表
- 单价计价 总价计价 费率计价
- 措施项目包干 计量调整
Related Cards
- →
Preliminaries bid at zero - can an increase be claimed at final account? (principle-plus-exception framework, with clarification of Clause 10.3.3)
Ordinary preliminaries bid at zero constitute a lump-sum price and are not reimbursed at final account (GB/T 50500-2024, 6.2.3, 6.1.5, 7.3.1); judicial practice treats this as a concession. 'Recalculation and determination' at final account under 10.3.3 only means recalculating all preliminaries contained in the executed works under Section 7.3 and Chapter 8 - amounts listed in interim settlement by construction stage are not a basis, and the zero bid remains effective. However, a zero bid for mandatory health, safety and environmental (HSE) provisions (railway term: statutory work safety levy (earmarked funds)) violates the non-competitive rule (3.2.5) and must be topped up at the standard rate; substantive changes caused by variations (7.4.4, implementation plan subject to employer approval) or employer-caused deferred use, dismantling/re-erection, addition or re-provision of preliminary items (3.3.7) may be adjusted through the prescribed procedure.
- →
GB/T 50500-2024: definitions of the three pricing methods (unit rate / lump sum / rate-based) and their applicability to each BOQ category
GB/T 50500-2024 provides: work-section BOQ items and day-work items should use unit-rate pricing (quantity x comprehensive rate); measures items should use lump-sum or rate-based pricing; provisional sums and specialist-work provisional amounts should use lump-sum pricing; main-contract services should use rate-based or lump-sum pricing (shared passage of Clauses 2.0.10-2.0.12). Clause 3.1.5 is the catch-all: where unit-rate or lump-sum pricing is unsuitable, rate-based or other methods may be used, with pricing requirements and price-adjustment rules stated in the tender and contract documents.
- →
Bill of preliminaries classification basis difference between GB/T 50500-2024 and GB 50500-2013: two-way split by measurability vs three pricing methods (unit-rate/lump-sum/percentage-rate)
GB 50500-2013 split preliminary items by 'whether quantities can be computed' into lump-sum items (priced per lump item, e.g., mandatory health, safety and environmental (HSE) provisions, temporary works and site establishment costs) and unit-rate items (quantity × all-in unit rate, e.g., scaffolding, dewatering), encouraging unit-rate pricing of measurable preliminary items; GB/T 50500-2024 abolishes the 'unit-rate/lump-sum preliminary items' dichotomy, replacing it with three pricing methods (clauses 2.0.10–2.0.12): unit-rate pricing, lump-sum pricing, and percentage-rate based pricing — and the recommended direction reverses: bills of preliminaries should use lump-sum pricing (3.2.1); special preliminary items genuinely requiring quantity-based pricing (and subject to expert panel review) move into the work-items list for itemization and pricing; percentage-rate based pricing gains formal terminology status (3.1.5, Appendix E Table E.3.2).
- →
Preliminaries — the "lump sum, no adjustment" principle and the full landscape of adjustable exceptions (GB/T 50500-2024 cl. 3.3.7, 7.3.1)
Under GB/T 50500-2024, the China national pricing standard for BOQ (Code of Valuation with Bill of Quantities of Construction Works), preliminaries follow a lump-sum no-adjustment principle, reflected at three levels: (1) the construction method statement reported at tendering is deemed reasonable and feasible, the cost is priced as a lump sum, and the contractor bears the risk of cost increases arising from adjusting its own method statement (cl. 3.3.7); (2) preliminary items in the priced BOQ shall not be re-measured or adjusted (cl. 7.3.1); (3) preliminaries are not adjusted for changes in costs (cl. 8.7.6 item 3). Exception channels: preliminary works listed as billed (BOQ) items and items the contract requires to be measured (cl. 7.2.1, 7.2.2); statutory safety provisions (per contract); variations (measured per cl. 7.4.4, priced per cl. 8.9); errors and omissions in the BOQ (cl. 8.2.2, 8.2.3); unforeseeable works within provisional sums (cl. 7.7.2); delayed use, removal/re-installation, increase or duplicated provision of the contractor's preliminary items due to the employer, and material changes to the time for completion (costs borne by the employer, cl. 3.3.7). Under re-measurable (unit-rate) contracts, only the statutory safety provisions and BOQ-listed formwork/temporary works etc. are adjustable for BOQ errors and omissions (cl. 8.2.2). Adjustments require "submitting the method statement for confirmation before implementation" (cl. 8.9.6); late submission is deemed waiver, and the other party's late confirmation is deemed acceptance (cl. 8.9.7).
- →
Measurement and cost adjustment rules for changes to preliminary items caused by design changes (variations) under GB/T 50500-2024
Preliminaries take 'no adjustment' as the principle and 'change-induced' as the exception (GB/T 50500-2024 §7.3.1): first determine the adjustment method by the three nature classes (entity-related / competitively independent / percentage-rate composite); measurement follows the employer-approved implementation scheme and what actually occurred (§7.4.4); for substantive duration changes, preliminaries are adjusted up (down) per §8.9.4 and additional preliminary items are priced per §8.9.5; the disadvantaged party must submit its scheme for confirmation before implementation (§8.9.6), and late submission is deemed waiver of the adjustment right (§8.9.7).
- →
Vertical transportation quantity calculation: buildings by floor area (incl. basements) x eave-height steps, structures by count/volume, rules for height-increase fees
Vertical transportation is a preliminaries (measures) item; the BOQ covers only large vertical-transport plant (tower cranes, construction hoists, material hoists etc.) — hoisting plant and manual assistance are already included in the work content of trade items and must not be double-counted. Buildings apply quota items by floor area (incl. basements) with structural type and eave-height steps; single-storey buildings with eaves <=3.6 m are excluded; structures (chimneys, water towers, silos, elevator shafts etc.) are counted per unit; foundations without basements with embedment depth >=4 m and underground water pools are measured by volume per design dimensions; the height-increase fee is computed on the floor area of the super-height portion, with eave height stepped per additional 10 m — remainders over 5 m (but under 10 m) count as 10 m, and 5 m or under is not counted.
Cited By
- ←
Content and pricing methods of preliminaries: the 2024 definition (clause 2.0.3), the listing basis (GB/T 50854-2024 annex R table R.1.1 preliminary items, code 011601), the three pricing methods of unit rate / lump sum / percentage rate and their preferred use (clauses 2.0.10 to 2.0.12, 3.2.1), the completion rules of annex E tables E.3.1 to E.3.4, and the non-competitive rule for statutory safety provisions (clause 3.2.5)
Preliminaries are 'project costs incurred in taking the relevant measures to complete the contract works, related to the cost of the works as a whole and to the performance of the contract, but unrelated to the cost of any individual divisional or sub-divisional work item' (GB/T 50500-2024 clause 2.0.3); their content is listed per annex R table R.1.1 of GB/T 50854-2024 (preliminary items, code 011601). The 2024 edition no longer splits 'lump-sum preliminaries / unit-rate preliminaries'; it prices by three methods - unit-rate pricing (quantity x all-in unit rate), lump-sum pricing (per item) and percentage-rate pricing (charging base x percentage rate) - and 'the pricing of the preliminaries BOQ should adopt the lump-sum method' (clause 3.2.1); special measures whose construction scheme the contract requires to pass expert panel review may instead be unit-rate priced and are then listed in the divisional/sub-divisional BOQ. The statutory safety provisions are a non-competitive item and must be priced per the provisions of the state and of the provincial or sector authorities (clause 3.2.5).
- ←
Definition, BOQ item (011601002) and cost composition of vertical transport: the pricing vehicle for machine-shifts of large vertical handling plant and their attending labour; a preliminaries item priced as a lump sum per item and held fixed; and its boundary against the plant costs of work items (concrete pumping, extra height for concrete placing)
Vertical transport cost is the price of BOQ item 011601002 'vertical transport' in the preliminaries bill, covering only the machine-shifts of large vertical handling plant during construction (tower cranes, builder's hoists / external hoists, material hoists and the like) plus the plant-mounted and attending labour; vertical transport done with other lifting plant or manual aids is already included in the work content of the relevant work items and must not be charged again (GB/T 50854-2024 Appendix R.2.3; GB/T 50860-2024 Appendix C.2.3). The item work content covers mobilisation and demobilisation with erection and dismantling of the plant, fabrication and installation of anchorage devices and bases, laying and removal of tracks for travelling plant, and plant operation and use; pricing follows GB/T 50500-2024 clause 3.2.1, 'the preliminaries bill is preferably priced on a lump-sum basis', priced per item, with the composition entered per Appendix E schedule E.3.2 'composition detail analysis sheet for preliminaries items', held fixed under clause 3.3.7 and not re-measured or adjusted under clause 7.3.1 (save for variations, provisional-sum works not fully foreseen, employer causes and other statutory events).
- ←
The claim path and the net-amount pricing basis for acceleration costs within preliminaries when the employer demands a shorter duration: offsetting the acceleration increment against the downward adjustment of the mid-term running costs of affected preliminaries items, the limits of the lump-sum preliminaries defence, and the approve-before-executing and claim time-limit procedures (GB/T 50500-2024 Articles 8.11.17, 2.0.32, 8.9.4, 8.9.6, 8.11.3 and 8.11.5; GF-2017-0201 clause 7.9.1)
A claim can be made, and in principle the employer bears the cost, but the claimable amount is a net amount: the actual incremental costs incurred by the contractor in the non-economical use of labour, materials and construction plant to meet the employer's demand, minus the reduction in the mid-term running costs of the affected preliminaries items caused by the shorter duration (GB/T 50500-2024 Articles 8.11.17, 2.0.32 and 8.9.4). A lump-sum preliminaries clause excludes only the increments generated by the contractor's own adjustment of its construction method or its self-initiated early completion; it does not exclude acceleration increments responding to the employer's instruction. To overcome the lump-sum defence, the method must be approved before execution (Article 8.9.6) and a Notice of Claim must be issued within the period agreed in the contract (28 days absent agreement) (Article 8.11.3).
- ←
The charging base of the winter and rainy season construction addition (norm labour, or labour plus plant), deciding the winter construction season, rate-based lump-sum charging versus special measures (warm-shed method, steam curing) priced on approved schemes and records, and the no-double-count rule against the night-work addition
Under the building and municipal basis the winter / rainy season addition is a total-price preliminaries item charged as base x rate, lump-sum: the base runs as norm labour or (norm labour + plant) by locality, and rates on different bases never compare; the rate covers only cold, insulation, rain, damp and protection plus crew and plant efficiency loss that leave the technical working process unchanged - warm-shed work, steam curing and like special measures that change the process always price separately on employer-approved winter schemes; nothing adjusts save variations, unforeseeable provisional-sum works and employer-caused preliminaries increases (GB/T 50500-2024 clause 3.3.7). The winter season starts and ends on local multi-year meteorology - 'five consecutive days of mean outdoor temperature steadily below / above 5C' (JGJ/T 104-2011 clause 1.0.3) - never on fixed calendar months.
- ←
Quota application for the erection cost of vertical storage tanks (metal oil tanks) built by the reverse jack-up method with hydraulic lifting: line-item selection by construction form and capacity class, measurement by shell metal weight in t, lifting gear and temporary stiffening to preliminaries, and NDT and the water filling test charged separately
The reverse jack-up method has no standalone line item in the erection consumption quota: the item is selected by 'tank type x shell construction form (lap-jointed / butt-jointed) x capacity class' and measured by shell metal weight in t (no deduction for the area of openings in the shell, and including bottom plates, shell plates, roof plates, curb angle, stiffening rings, wind girders, and shim and reinforcement plates); where only one tank is built on one site, labour and plant consumption is multiplied by 1.25 (materials not). Neither the plant schedule nor the work content of the items contains a lifting step, so the hydraulic lifting devices and the temporary stiffening of the reverse method are charged as preliminaries; the work content stops at 'leak testing' - shell weld NDT, the water filling test and foundation settlement monitoring are outside the items and must be listed separately.
- ←
Interim payment and final settlement of preliminaries: statutory safety provisions prepayment and recovery points (9.3.2 - at least 50% within 28 days of commencement), progress-payment methods (9.4.4 - agreed breakdown or element-works ratios), the three-stage preliminaries breakdown table (6.2.13, Appendix E Table E.3.3), interim versus final settlement (10.2.7, 10.3.3) and the three-class treatment in settlement review
Statutory safety provisions prepay at not less than 50% of the total within 28 days of commencement, the rest decomposed per the early-arrangement principle and paid with progress payments; computing progress payments never recovers the prepayment - it is recovered once at the final account (9.3.2). Preliminaries progress payments follow the parties' agreed breakdown; absent agreement, by the ratio of cumulative completed work-item list value to the work-item list total, the breakdown resting on Appendix E Table E.3.3 (initial set-up / mid-term running / late dismantling, 6.2.13, 9.4.4). Preliminaries listed in interim settlements serve only interim payment (10.2.7); the final account recomputes all preliminaries of the completed works per clause set 7.3 and chapter 8, including safety-provision adjustments - interim figures are no basis (10.3.3).
- ←
Preliminaries — the "lump sum, no adjustment" principle and the full landscape of adjustable exceptions (GB/T 50500-2024 cl. 3.3.7, 7.3.1)
Under GB/T 50500-2024, the China national pricing standard for BOQ (Code of Valuation with Bill of Quantities of Construction Works), preliminaries follow a lump-sum no-adjustment principle, reflected at three levels: (1) the construction method statement reported at tendering is deemed reasonable and feasible, the cost is priced as a lump sum, and the contractor bears the risk of cost increases arising from adjusting its own method statement (cl. 3.3.7); (2) preliminary items in the priced BOQ shall not be re-measured or adjusted (cl. 7.3.1); (3) preliminaries are not adjusted for changes in costs (cl. 8.7.6 item 3). Exception channels: preliminary works listed as billed (BOQ) items and items the contract requires to be measured (cl. 7.2.1, 7.2.2); statutory safety provisions (per contract); variations (measured per cl. 7.4.4, priced per cl. 8.9); errors and omissions in the BOQ (cl. 8.2.2, 8.2.3); unforeseeable works within provisional sums (cl. 7.7.2); delayed use, removal/re-installation, increase or duplicated provision of the contractor's preliminary items due to the employer, and material changes to the time for completion (costs borne by the employer, cl. 3.3.7). Under re-measurable (unit-rate) contracts, only the statutory safety provisions and BOQ-listed formwork/temporary works etc. are adjustable for BOQ errors and omissions (cl. 8.2.2). Adjustments require "submitting the method statement for confirmation before implementation" (cl. 8.9.6); late submission is deemed waiver, and the other party's late confirmation is deemed acceptance (cl. 8.9.7).
- ←
Whether rate-priced mandatory HSE provisions (statutory safety provisions) adjust at settlement: three adjustment doors (quantity-linked base, legal and policy change, major variation or raised standards), the rate-lump-sum principle regardless of actual spend, and the settlement base plus the 2013/2024 edition gap
Mandatory HSE provisions (railway: work safety funds; GB/T 50500-2024: statutory safety provisions) are non-competitive: settlement value = settlement base x prescribed rate, lump-sum, never rising or falling with the contractor's actual spend. Only three doors open: (1) the base (finally confirmed work-item costs) - GB 50500-2013 clause 9.6.3 adjusts rate or single-price preliminaries both ways with quantity; (2) legal and policy change after the contract base date - 2013 clause 11.2.3 and 2024 clause 8.8.1 adjust when the authorities revise the standards mid-works; (3) variation or employer-raised site standards - scheme confirmed before execution (2013 9.3.2; 2024 8.9.6), silence forfeits. Settlement review recomputes all preliminaries per 10.3.3; interim-listed figures are no basis.
- ←
Dividing preliminaries liability when site conditions change: site conditions contemplated at tender as lump-sum risk versus employer-changed sites during construction adjusting through variation and claims
GB/T 50500-2024 clause 3.3.7 draws the line: the preliminaries scheme bid 'shall be deemed reasonably practicable and meeting actual construction requirements; its cost is lump-sum, and the contractor bears the risk of increases from adjusting its own scheme'; save variations, unforeseeable provisional-sum works, and 'employer-caused extended use, reworking, addition or re-provision of preliminaries' adjusting under chapter 8, nothing adjusts. So: site conditions shown at tender and priced in the bid are the contractor's lump-sum risk; employer-changed or restricted sites, late handover and disturbed order are employer liability, adjusting upward through variation (8.9) or claims (8.11) - 8.11.10 lists profit among claimables - subject to pre-execution scheme confirmation; silence forfeits.
- ←
Recognising preliminaries costs of repeated scaffold erection and dismantling caused by the employer (instructions changing construction sequence): lump-sum exceptions, measurement anchors, pricing methods and procedural requisites (GB/T 50500-2024 clauses 3.3.7, 7.3.1, 7.4.4, 8.9.4~8.9.7, 8.11.10; GB/T 50854-2024 Appendix R, code 011601)
Preliminaries are lump-sum and unadjusted in principle, but clause 3.3.7 lists the exception: 'employer-caused extended use, reworking, addition or re-provision of preliminaries increasing their cost adjusts under chapter 8' - scaffolds re-erected after an employer instruction changing the sequence fall squarely under 'reworking' and 're-provision', with no need to prove excess over the bid scheme's assumptions, though a bid-versus-instructed scheme comparison must show the instruction caused it. Increments measure per 7.4.4 on the employer-approved scheme or actual content (extended use of existing preliminaries and management on non-critical paths never measures); material duration changes price per 8.9.4 as 'extended (shortened) duration x mid-term running costs', new plant and temporary works per 8.9.5; the scheme must be confirmed before execution (8.9.6), silence forfeiting (8.9.7). Codes: GB/T 50854-2024 Appendix R preliminaries run 011601 (scaffolds 011601001, unit 'item', no area rules at BOQ level); 011701 is the 2013 code - area / vertical-projection bases now serve only as increment pricing anchors, never to re-measure the whole scaffold list.
- ←
The unit-price / total-price preliminaries divide and its migration in the BOQ system: the 2013 'unit-price items / total-price items' split of GB 50500-2013 clauses 4.3.1-4.3.2 against the three pricing methods of GB/T 50500-2024 clauses 2.0.10~2.0.12 and 3.2.1
GB 50500-2013 clause 4.3.2 split preliminaries by 'whether quantities can be computed': those that cannot (site discipline, safety, temporary facilities) price 'per item' as total-price items; those that can (scaffolds, dewatering) price 'per quantity' as unit-price items, with clause 4.3.1 mandatory (preliminaries lists compiled per the current national measurement codes). GB/T 50500-2024 drops the split: pricing now runs by unit, total or rate (2.0.10~2.0.12); work items and dayworks suit unit pricing, preliminaries preferably total or rate (3.2.1 - total, per item); quantifiable specialist preliminaries such as concrete formwork have moved into the work-item list of GB/T 50854-2024 (Appendix E Table E.5.1, code 010505), and expert-reviewed specialist schemes may price by unit within the work-item list.
- ←
Pricing clash-detour increments of MEP services: the attribution boundary of detailing versus variation, the valuation entries (8.9.1 / 8.9.2 and 2013's 9.3.1), the material and labour increments of cable-tray extended metres, bends and supports, and the separate claim channel for stoppage and the site-record anchors
Three gates before pricing a detour: (1) difference nature - contract versus actual drawings = variation; refinement within one drawing set is no variation; (2) attribution - the employer's design errors and base-data faults are employer risk; the contractor's routine detailing avoidance is contractor risk, generally unadjusted (T/ZBD 100.4-2023 clause 4.4.6) save contracts settling on the contractor's detailing drawings; (3) the entry - variations with quantity moves within 15% price on the five bands of 8.9.1, beyond 15% on 8.9.2 with purchase-discount adjustments. Quantity magnitude fixes 'how to price', never 'whether to pay'. Stoppage, waiting and idle losses claim separately under 8.11.9 / 8.11.10 - never merged into variation rates.
- ←
Full workflow for preparing the tender bill of quantities: preparing entity and object, the seven bases of preparation, itemisation with the five elements and item description, the four-part BOQ composition, deliverables and appendix forms, error liability, and the interface with the tender price ceiling
Chapter 4 of GB/T 50500-2024 provides: the bill of quantities is prepared by a tenderer with preparation capability or by a construction cost consultant commissioned by it (4.1.1); it is itemised with the contract object or a single project or individual structure as the object and forms part of the tender documents (4.1.2); the deliverables comprise the cover, signature page, explanatory notes of the estimate, notes on measurement rules, and the BOQ and pricing forms (4.1.3), in forms B.1.1, C.1.1, D.4.1, E.1.1/E.2.1/E.2.3/E.3.1/E.4.1 to E.4.5/E.5.1 and G.1.1. The BOQ is prepared and priced in four parts -- the work-item BOQ, the preliminaries BOQ, the other items BOQ and VAT (3.1.2) -- and the current edition no longer carries a statutory levies and taxes section; the all-in unit rate and the sum are fully inclusive pre-tax prices excluding VAT, tax is entered under VAT, and the provisional sum for nominated specialist subcontract works already includes VAT and must not be taxed again (3.1.6).
- ←
GB 50500-2013 Chapter 9 'Adjustment of the Contract Price' at a glance: the 15 adjustable events, their five-category grouping and clause order, the trigger conditions and direction of price adjustment for each event, submission time limits and confirmation (deemed approval) procedures, the order of application when several events coincide, and a clause mapping to GB/T 50500-2024
Clause 9.1.1 of GB 50500-2013 lists 15 adjustable events, and the official commentary groups them into five categories: changes in laws and regulations (9.2); variations (9.3 variation, 9.4 item description mismatch, 9.5 omitted BOQ items, 9.6 quantity deviation, 9.7 dayworks); changes in costs (9.8 changes in costs, 9.9 provisional prices); claims (9.10 force majeure, 9.11 earlier completion, 9.12 delay damages, 9.13 claims); and others (9.14 site instruction records plus other adjustment events agreed by both parties). Clause numbers are easily shifted: changes in costs is 9.8 (not 9.7, which is dayworks); force majeure 9.10; earlier completion 9.11; delay damages 9.12; claims 9.13; site instruction records 9.14. Direction of adjustment: under 9.6.2, where a quantity deviation exceeds 15%, the all-in unit rate of the increased portion beyond 15% is reduced, and where the quantity decreases by more than 15% the all-in unit rate of the remaining portion is increased (reverse correction); 9.3.1 sets a four-tier pricing ladder for variations (an applicable item takes the original rate; a similar item is referenced within a reasonable range; where neither applies, the contractor proposes a rate from published price information x its quoted floating rate for the employer's confirmation; where the published price information carries no price, a lawful market price from market survey is proposed for confirmation); under 9.8.2, where no band is agreed and a unit rate changes by more than 5%, the portion beyond 5% is adjusted. Where events coincide: if a variation also causes a quantity deviation above 15%, that item's rate is adjusted under 9.6.2 (clause 9.3.1 paragraph 1), preliminaries move in linkage under 9.6.3/9.3.2, and cost fluctuation is separately adjusted under Annex A for the price differential only, without double counting.
- ←
Contract price adjustment caused by missing items in the tender bill of quantities: the clause chains of the three entries of GB 50500-2013 section 9.5 (9.5.1 to 9.3.1, 9.5.2 / 9.5.3 to 9.3.2), the four-tier valuation of all-in unit rates for new divisional and sub-divisional works items, the three-tier determination of new preliminaries, the itemisation test between unit-rate and lump-sum preliminaries, and the distinction from the quantity-deviation preliminaries linkage trigger path of clause 9.6.3
GB 50500-2013 splits 'missing BOQ items' into three mutually non-substitutable clause chains: 9.5.1 (missing divisional and sub-divisional items) fixes the rate under the four tiers of 9.3.1; 9.5.2 (new works items bringing changes to preliminaries) adjusts under 9.3.2 after the implementation plan is approved; 9.5.3 (missing preliminaries items themselves) both fixes rates under 9.3.1 and adjusts preliminaries under 9.3.2, and the plan must be submitted to the employer for approval first. The three tiers of 9.3.2: mandatory HSE provisions are calculated per 3.1.5; unit-rate preliminaries have their rates set per 9.3.1; lump-sum (or factor-based) preliminaries follow the actual adjustment amount x the contractor's quoted-price fluctuation rate. Failure to submit the plan in advance is deemed no adjustment of the preliminaries or waiver of the right to adjust. Missing items go through 9.5 / 9.3; only quantity deviations of original BOQ items over 15% (exclusive) go through 9.6.2 to adjust the all-in unit rate, with 9.6.3 adjusting factor-based or single lump-sum preliminaries up or down - the two paths must not be mixed.
- ←
Procedures for handling contract price adjustment matters under GB/T 50500-2024 section 8.1: the five steps submission - checking - re-checking - further review - confirmation, the two-way forfeiture rules under which each party's silence is deemed approval, the link between signing the output documents and concurrent payment with progress payments / stage settlement payments, and the boundaries against the prior scheme submission for preliminaries and the price review for additional works
Under GB/T 50500-2024 section 8.1, contract price adjustments are handled through 'submission - checking - re-checking - further review - confirmation': the contractor measures the quantities under chapter 7, prices the adjustment under sections 8.2 to 8.11 and submits both with the supporting documents to the employer for checking within the agreed time (8.1.2); the employer verifies within the agreed time and either notifies confirmation in writing or replies in writing with checking comments, and if it neither confirms nor comments, the contractor's report is deemed accepted (8.1.3); after receiving the checking comments the contractor re-checks within the agreed time, and if it neither confirms nor comments, the employer's comments are deemed accepted (8.1.4); the parties sign the measurement and pricing output documents, which become the payment basis under chapters 9 and 10, and the adjusted additional (reduced) price is paid concurrently with the progress payments and the interim settlement payments by construction stage (8.1.6). All periods run 'within the agreed time'; the standard sets no uniform number of days.
- ←
Characterisation, variation and site-record procedures, the variation valuation ladder, the additional-haul cost formula and the no-double-counting rule when the spoil site (spoil point / waste reception site) is changed and haul distance and disposal costs move
A spoil site changed for reasons not attributable to the contractor (a government dumping ban, expropriation of the site, a different site nominated by the employer, or insufficient capacity of the original site) is a variation under GF-2017-0201 cl. 10.1 item (4), 'changing the baselines, levels, positions and dimensions of the works'; it may proceed only after a variation instruction countersigned by the employer is received, and the unit rate is fixed by the four progressive items of GB 50500-2013 cl. 9.3.1 (an applicable rate is adopted; with no applicable but an analogous rate, reference within a reasonable range; with neither, the contractor proposes from documents, measurement and pricing methods, published price information and its price fluctuation rate for employer confirmation; where the published price information lists no price, a market price with a lawful basis applies). A haul distance change is not a quantity deviation and the 15% rule does not apply; spot site swaps and temporary double-handling instructed on site by the employer are handled as site instruction records under Section 9.14 (record report submitted within 7 days, employer verifies within 48 hours, silence past the limit means deemed approval, pricing within 7 days of completion and payment with the same-period progress payment). Note that site instruction records sit in Section 9.14 -- Section 9.10 is force majeure; the same facts may be priced through either variation or site record, never both.
- ←
Adjustment of the contract period and the attribution of delay damages and early-completion (acceleration) costs when a variation (including omissions of work by the employer) changes the works period (GF-2017-0201 clauses 10.6 and 7.9; GB/T 50500-2024 clauses 2.0.33 and 8.11.17)
When a variation (including omissions) changes the works period, the contract period is adjusted first under GF-2017-0201 clause 10.6 by agreement or determination, with the days added or reduced set by reference to the duration norms of the works location; delay damages are benchmarked against 'the contract period (including any extension approved by the employer)' (GB/T 50500-2024 clause 2.0.33), so once an omission shortens the period, delay must not be measured against the original completion date; early-completion (acceleration) costs follow 'whoever asks, pays' under GB/T 50500-2024 clause 8.11.17 and GF-2017-0201 sub-clause 7.9.1 - where the employer requires acceleration it bears the acceleration compensation and the extra cost of uneconomic use of labour, materials and plant, a contractor finishing early on its own bears its own costs, and in no case may the employer compress a reasonable period.
- ←
Determining plant and small tools cost within the all-in unit rate: consumption × plant rate per machine-shift, 7-item/4-item composition of the plant rate per machine-shift, and adjustment for price differentials
Plant and small tools cost = construction machinery usage cost + construction instrument and meter usage cost, both determined as machine-shift consumption under quota norms (prescribed resource consumption standards) × plant rate per machine-shift (GB/T 51095-2015 Clause 5.3.9; TB 10801-2024 Section 3.3). The plant rate per machine-shift for construction machinery has 7 items = depreciation + overhaul + maintenance + assembly and disassembly + labour + power + other costs; the plant rate per machine-shift for instrument and meter has 4 items = depreciation + maintenance + verification + power; both are computed on an 8-hour working shift. Where machine-shift cost quota norms exist, take the price per the quota norms (railway TB/T 10814-2024, base-period price excluding deductible input value added tax (VAT)); the difference between base period and compilation period is listed as an adjustment for price differentials of plant and small tools cost. When fuel and power prices fluctuate beyond the agreed risk band (no-adjustment tolerance, e.g. ±5%; where not agreed, 5%), price adjustment (for fluctuation) applies; the price difference carries VAT only, with no management fee or profit (GB/T 50500-2024 Clauses 8.7.2, 3.3.5).
- ←
Re-measurement and price adjustment rules after quantity changes caused by variations or BOQ errors: recalculating from the variation instruction and the actual construction drawings, the separate track for BOQ errors, the 15% banded unit-rate adjustment, and the scheme-approval precondition for pricing preliminaries and new preliminary items (GB/T 50500-2024 clauses 7.4.2-7.4.4, 8.2.1, 8.9.1-8.9.2; GB 50500-2013 clauses 9.3.1, 9.3.2, 9.6.2)
Re-measurement after a variation takes as its basis the quantities recalculated from 'the variation instruction issued or confirmed by the employer and the actual construction drawings', compared with the BOQ quantities after the BOQ errors have been corrected, to determine the added or deleted variation items and their quantities; differences between the contract drawings and the contract BOQ are BOQ errors (corrected under unit-rate contracts, not adjusted under lump-sum contracts). Where the quantity difference is within 15% (15% inclusive), the unit rate is set under GB/T 50500-2024 clause 8.9.1; beyond 15% (exclusive), clause 8.9.2 adjusts downward on increase and upward on decrease in light of labour and material purchase concessions (the 2013 edition corresponds to the four tiers of clause 9.3.1 and clause 9.6.2). Preliminaries adjustment requires prior submission of the proposed scheme confirmed by the employer and the contractor; failure to submit is deemed to cause no preliminaries adjustment or a waiver of the right to adjust. New preliminary items take the added temporary works and plant machine-shifts priced from the approved scheme; the added cost of extended use of existing preliminaries and supervisory staff from variations off the critical path need not be measured.
- ←
Whether increased pipeline quantities caused by BIM coordinated layout can adjust the work quantities: determined by attribution in the deepening design (contractor's own deepening design — no adjustment; only where it constitutes a variation is adjustment made)
Whether the quantities of pipelines increased by BIM coordinated layout can be adjusted depends on attribution: differences arising from the contractor's own deepening design are generally not adjusted (GB/T 50500-2024, Clause 3.3.9; T/ZBD 100.4-2023, Clause 4.4.6), except where the contract provides for settlement on the basis of the deepened drawings; where the employer so requires, or where it constitutes a variation confirmed upon review by the original designer, adjustment is made per Chapters 7/8/9, and where the quantity difference exceeds 15%, the unit rate is adjusted per Clause 8.9.2.
- ←
Within preliminaries: the composition, charging method and calculation bases of mandatory HSE provisions (statutory safety provisions), temporary works and site establishment costs, and the additional cost of night work, compared; plus the clause basis of the non-competitive status of mandatory HSE provisions and the item listing rules
Mandatory HSE provisions comprise four heads - environmental protection, site order, safe construction, and temporary works and site establishment (Jian Ban [2005] No. 89 article 4 citing Jian Biao [2003] No. 206); temporary works cost is thus a sub-head and must not be listed again as a separate item and double charged. GB/T 50500-2024 clause 3.2.5 makes statutory safety provisions a non-competitive item, and GB 50722-2011 clause 5.2.9 provides that mandatory HSE provisions and work injury insurance for migrant workers must not be treated as competitive costs: the tenderer may not require a discount on them and tenderers may not subject them to market competition. All three heads are lump-sum preliminaries not readily measurable, charged as calculation base x percentage rate; the base for mandatory HSE provisions is the quota base price (norm-based elemental works cost plus measurable preliminaries), the norm-based labour cost, or the norm-based labour cost plus norm-based plant cost; the additional cost of night work is charged on the base of the labour and plant costs incurred for the night work, and only where night work actually occurs under technologically required continuous construction or an approved night work plan may it be charged (statutory night runs 22:00 to 6:00 the next day).
- ←
The source definition, pricing basis and final account aggregation of the three kinds of quantities (contract BOQ quantities / variation quantities / dayworks record quantities), including the comparison baselines for BOQ errors - variation - additional works and the one-gateway-only rule against double measurement (GB/T 50500-2024 clauses 7.2, 7.3, 7.4, 7.5, 8.2, 8.6, 8.9, 8.10, 8.11, 10.3; compared with GB 50500-2013 clauses 9.3, 9.14, 11.2)
Clause 7.4.1 of GB/T 50500-2024 draws the boundary with three comparison baselines: the difference between the contract drawings and the contract BOQ = errors and omissions in the BOQ (corrected under unit-rate contracts, not adjusted under lump-sum contracts); the difference between the contract drawings and 'variation instructions + as-executed drawings' = variation; work outside the contractual scope of works completed at the employer's request = additional works (8.10.1); sundry items and events not attributable to the contractor are measured on dayworks vouchers (7.5.3 to 7.5.6). In-contract quantities are re-measured under 7.2.1 (BOQ items priced per item are not re-measured or adjusted); deviations within 15% (inclusive) go to 8.9.1 and beyond 15% to 8.9.2, the rate progressing 'contract rate -> converted similar rate -> negotiated market-reasonable all-in unit rate'; dayworks take the contract dayworks all-in unit rate under 8.6.2, or where no such BOQ item or no applicable rate exists the published price information under 8.6.3 and, failing that, the contractor's purchase price as confirmed by both parties, the rate already covering the sporadic extra costs and preliminaries of dayworks (8.6.4). Settlement aggregates in the 13-item order of 10.3.2, with preliminaries and the main contractor's attendance and coordination provisions recalculated at final account (10.3.3). No double measurement: variation quantities are determined only after comparison with 'the BOQ items and quantities as corrected for BOQ errors' (7.4.2), and what has already been adjusted under 8.2 to 8.10 may not be claimed again under the claims provisions (8.11.1).
- ←
Re-decomposition and re-pricing of cost when a design variation moves wire-in-conduit wiring to cable-tray wiring: choosing the variation valuation clause (2013 edition clause 9.3.1 four tiers / 2024 edition clauses 8.9.1~8.9.3 five tiers); the deduction basis for the original conduit and wiring quantities; itemisation and measurement of tray, supports and hangers, and wiring; attribution of demolition of work already done and material write-off, and the rework confirmation procedure
Changing wires from conduit to cable tray is a change of 'item description + construction method': the original conduit rate does not apply to the tray (under the 2013 edition, clause 9.4.2 first re-determines the all-in unit rate on the description actually built, then the four tiers of clause 9.3.1 apply - the contract rate where an applicable item exists, an analogous rate by reference where a similar one exists, and where neither exists the contractor proposes a rate built from published price information and its tender float rate for employer confirmation, or from market-enquiry prices where the published information lacks the item); conduit and wiring quantities are recalculated from the variation instruction and the drawings as actually built and set against the original BOQ for deduction (conduit deducted by length, the length occupied by junction boxes not deducted); the added tray is measured by length (m); whether supports and hangers are listed separately depends on the consumption standard applied (DB11/T 2382-2024 includes support erection, fabrication of non-finished supports being listed separately; SJG 111.3-2022 expressly excludes support fabrication and erection); wiring is recalculated as single-wire length including reservations; demolition and material write-off for rework must rest on a rework confirmation sheet or site instruction record raised within the contractually agreed time - borne by the employer where the cause is not attributable to the contractor, and serving as the basis for rework pricing under chapter 8; raised late, the work is deemed to have caused no rework and is not measured.
- ←
Determining whether vertical transport preliminaries double count the machine-shift rates of tower cranes and builder's hoists: the BOQ item coding basis, the inclusion and exclusion boundaries in provincial consumption quota chapter notes, and a method of checking whether the plant rate is included or excluded via the machine-shift content and unit of measurement of quota line items
No double counting. The machine-shift running rates of tower cranes and builder's hoists are already embedded in the pricing of the vertical transport preliminary item (GB/T 50854-2024 Table R.1.1 preliminary items, code 011601; former GB 50854-2013 Table S.3, code 011703); the vertical transport charge is the very pricing carrier of those machine-shifts, and no separate 'tower crane machine-shift charge' or 'builder's hoist machine-shift charge' may be listed. Only the parts expressly excluded by the quota chapter notes may be priced separately: off-site transport of plant, first-time erection and dismantling, subgrade bedding, track laying and removal, plus the foundations of tower cranes and hoists and the connections of cranes and hoists to the building. Determination uses a three-step check: read the inclusion and exclusion lists in the chapter notes -> check whether the labour, material and plant columns of the line item already list those machine-shifts -> check the unit of measurement and pricing basis (pricing per gross floor area is a lump-sum basis; pricing by hired machine-days must not also be charged by area).
- ←
Rate build-up basis and confirmation procedure when a BOQ omission or new item has neither an applicable nor an analogous rate: GB 50500-2013 Section 9.5 (citing the four tiers of cl. 9.3.1) mapped against GB/T 50500-2024 Sections 8.2/8.9/8.10, plus the time limits for adjustment reports
GB 50500-2013 cl. 9.5.1 provides that 'where, during performance, new divisional and sub-divisional works BOQ items arise because of omissions in the tender BOQ, the unit rates shall be determined per cl. 9.3.1 of this code and the contract price adjusted'. Tier 3 of cl. 9.3.1 reads 'where the priced BOQ contains neither an applicable nor an analogous item for the varied work, the contractor shall propose a unit rate for the varied work based on the variation documents, the measurement rules and pricing methods, the published price information issued by the government construction cost administration and the contractor's price fluctuation rate, and adjustment follows employer confirmation'; tier 4 switches, where the published price information lists no price, to a rate based on 'market prices with a lawful basis obtained through market enquiry and other means', again subject to employer confirmation -- so published price information comes first and a lawful market price only fills gaps, and tier 3 must carry the contractor's price fluctuation rate. GB/T 50500-2024 no longer has a stand-alone 'omission' section: erroneous and omitted items are folded into 'errors and omissions in the BOQ' (cl. 8.2.1 -> cl. 8.9.1/8.9.2), additional works outside the contract scope follow Section 8.10 (cl. 8.10.2 requires the contractor to submit the project execution plan or execution scheme, the programme and the priced offer to the employer for review and approval before executing the additional works), the adjustment procedure is unified as 'submission, checking, re-checking, review and confirmation' (cl. 8.1.2 to 8.1.4), and employer silence past the time limit counts as deemed approval of the contractor's report.
- ←
Boundary determination and clause routing among quantity deviation, variation and omitted BOQ items: sections 9.4/9.5/9.6 of the 2013 edition are merged into 'BOQ errors' in GB/T 50500-2024, sorted by three comparison tests (contract drawings vs contract BOQ; contract drawings vs actual construction drawings; inside vs outside the contract works scope), with an anti-double-counting rule that one matter goes through one route only
The routing test is unique: a difference between the contract drawings (including the contract specifications) and the priced BOQ equals BOQ errors; a difference between the contract drawings and the actual construction drawings (including variation instructions issued or confirmed by the employer) equals a variation; physical works outside the contract works scope and the completion delivery requirements are additional works. GB/T 50500-2024 has merged 2013 edition Section 9.4 (item description mismatch), Section 9.5 (omitted BOQ items) and Section 9.6 (quantity deviation) into 'BOQ errors' (Clause 2.0.27), with quantity differences tiered at 15%: up to and including 15% goes to Clause 8.9.1, above 15% (exclusive) goes to Clause 8.9.2. The key anti-duplication procedure: varied quantities must be determined by comparison with the BOQ items and quantities 'after the BOQ errors have been corrected' -- the same quantity difference must not be adjusted once as an error correction and again as a variation increase or decrease.
- ←
Adjusting all-in unit rates at the +/-15% quantity boundary: GB/T 50500-2024 Clauses 8.9.1-8.9.3 and the reading of the wording change from repealed GB 50500-2013 Clause 9.6.2's "tiered pricing"
Under GB/T 50500-2024 (unit-price contracts): within 15% (inclusive) per 8.9.1's five tiers (same characteristics + same conditions -> contract rate; similar -> converted; different -> negotiated market rate); beyond 15% per 8.9.2, "accounting for the purchase-price discounts gained by increased quantities (or lost when decreased), reasonably lower (or raise) the contract rate and new composite rates" - more quantity lowers the rate, less raises it. The repealed 2013 Clause 9.6.2 explicitly said "the rate of the increased portion shall be lowered; the rate of the remaining portion after decrease shall be raised" (tiered: within +/-15% unchanged); 2024 drops "portion" and does not say whether the tiered or whole-quantity repricing applies - a genuine ambiguity; being a recommended standard, contract terms govern - lock the tiered basis in the special conditions.
- ←
The dividing line between unit-rate and lump-sum preliminaries in the bill of preliminaries: the 'whether quantities can be computed' binary test of GB 50500-2013 section 4.3, and how it is landed as itemisation and coding in GB 50854-2013 Annex S and GB/T 50854-2024 Annex R
The commentary to GB 50500-2013 clause 4.3.2 takes 'whether quantities can be computed' as the only express dividing line in the code: items whose quantities cannot be computed (site amenity and safety protection, temporary works, etc.) are priced per item and called lump-sum items, while items whose quantities can be computed (scaffolding, dewatering, etc.) are priced by quantity and called unit-rate items. GB 50854-2013 clause 4.3.1 (a mandatory provision) requires preliminaries in Annex S that carry an item description, unit of measurement and measurement rule to be itemised in the measured-works manner (all five elements present), and clause 4.3.2 requires items given a code and name only to be set per the Annex S code and name (priced per item). From GB/T 50500-2024 the binary naming is dropped in favour of three pricing methods - unit-rate pricing, lump-sum pricing and percentage-rate pricing (clauses 2.0.10~2.0.12) - with the preliminaries bill preferably lump-sum priced (clause 3.2.1); GB/T 50854-2024 Annex R codes all preliminaries 011601, and concrete formwork moves into the measured works (Annex E, table E.5.1, code 010505).
- ←
Composition differences between interim settlement by construction stage and the final account: stage settlement on three elements plus a five-item payment application, the final account on 13 listed items (GB/T 50500-2024 clauses 10.2 / 10.3)
Interim settlement by stage prices at settlement nodes: its composition = the relevant contract sums within the total price for the period or node + the contract adjustments agreed by the parties, less contractor-cause liquidated damages (clause 10.2.1); the payment application follows the five items of clause 10.2.10 on 'cumulative completed price - cumulative paid - current deductions'. The final account is compiled per clause 10.3.2 as 13 items in order (contract BOQ total - BOQ errors, provisional sums, provisional prices, main contractor's attendance, dayworks, price fluctuation, law and policy changes, variations, additional works, claims, damages, others). Stage settlement files signed by both parties form part of the final account and are not re-measured or re-priced (clause 10.2.3) - only preliminaries and the main contractor's attendance provisions are recomputed per clause 10.3.3.
- ←
Whether preliminaries adjust after a construction plan (project execution plan) changes: the lump-sum boundary, adjustable situations, measurement and pricing methods, and supporting records
After a plan (project execution plan) change, preliminaries follow lump-sum-no-adjustment as the principle (GB/T 50500-2024 Article 3.3.7): the contractor's tendered measures plan is deemed reasonable and feasible, preliminaries are priced lump-sum, and the contractor bears the risk of increases caused by his own plan changes; only three exceptions - variations, works within provisional sums not fully foreseen or detailed, and employer-caused extended use, dismantling, addition or duplicated provision of measures - adjust under Chapter 8; costs of changing an unworkable plan or one beyond the contractor's capability are his own. Time effects adjust only for substantive critical-path extension or reduction (8.9.4), non-critical items unmeasured; cost fluctuation is no ground (8.7.6), while laws and policy changes are a separate channel (8.8.1); measurement adjustment is a closed list under 7.3.1; varying preliminaries requires the plan approved and confirmed before execution, silence forfeiting the right (8.9.6, 8.9.7).
- ←
Charging boundary of material price differentials (construction-period adjustment): VAT only - no overheads or profit, and no participation in the charging bases of total-price preliminaries or statutory levies (GB/T 50500-2024 Article 3.3.5 paragraph 4, Article 8.7.6)
Differentials formed by construction-period material price settlement adjustments carry VAT only - no overheads or profit, and they do not join the charging bases of total-price preliminaries or statutory levies. Basis: GB/T 50500-2024 Article 3.3.5 paragraph 4 - differentials of labour, materials and the fuel-power element of plant within all-in unit rates carry VAT but not overheads or profit; Article 8.7.6 items 3 (preliminaries) and 7 (overheads and profit) are listed among fees not adjusted for cost fluctuation; and since total-price preliminaries charge on labour plus plant, and statutory levies on quota labour, material differentials - being material in nature - fall outside both bases anyway. Express contract terms prevail.
- ←
Deducting construction water and electricity at settlement and the un-metered dispute: contract first, metered use at actual prices, the claimant bears the proof for tender-quantity deduction, local rate fallbacks
Utilities are not a single line in the contract price - they ride inside materials, machine-shift rates and temporary-facility preliminaries, so the deduction basis must mirror the pricing basis. Order: (1) contract or tender documents govern; (2) with meterable water and power meters, deduct metered use at actual prices (T/ZBD 100.4-2023 clause 4.5.8); (3) where the contractor seeks deduction on tender (quota) contents, it bears the burden of proof and the amount must be reasonably fixed; (4) failing meters and agreement, local cost-quota fallback ratios apply (Shaanxi's rules clause 8.6: 0.6% of the works cost, power 0.45% within) - never transplanted across regions. "Deduct by quota content" is no automatic default: the claimant proves.
- ←
The definition of preliminaries and its two charging bases: measurable preliminaries (priced like divisional-work costs) and comprehensively charged preliminaries (a rate on divisional-work costs plus measurable preliminaries)
Preliminaries defined (GB/T 50500-2024 clause 2.0.3): the costs of the technical, welfare, work-safety and environmental-protection items arising in construction preparation, construction and acceptance - tied to the works as a whole and to contract performance, not to any single divisional-work item. At budget stage two bases apply (GB/T 51095-2015 clause 5.3.10; DB42/T 823-2021 clause 6.3.10): measurable preliminaries price by the same method as divisional-work costs (clauses 5.3.8 / 5.3.9; 6.3.8 / 6.3.9); comprehensively charged preliminaries = (the unit work's divisional-work costs + measurable preliminaries) x the rate. At final account the preliminaries are recomputed as the full preliminaries of the completed works per GB/T 50500-2024 clause 10.3.3 - interim listings do not bind.
- ←
May quantities cut by design variation be listed as negative BOQ items: the contract BOQ itself never goes negative - increases and decreases fall to the "variation increase-and-decrease price" item at final account; under lump-sum (fixed-price) contracts BOQ defects do not adjust, only differences between as-built and contract drawings form priceable variations (GB/T 50500-2024)
Quantity cuts from design variations must never be written as negative quantities in the original contract BOQ - BOQ quantities compute on design-shown dimensions and, under lump-sum contracts, divisional BOQ quantities need no re-measurement (clause 7.2.2); the cuts land at the settlement adjustment layer, item 9 of GB/T 50500-2024 clause 10.3.2, "variation increase-and-decrease price" (which may be negative), the contract-BOQ-total line standing unchanged. Under lump-sum contracts only the difference between as-built and contract drawings constitutes a priceable variation (clause 7.4.3); contract-drawing versus contract-BOQ differences are BOQ defects and never adjust (7.4.2, 8.2.3). Variation pricing splits on whether contract rates apply: applying, adjust under 8.9.1 (quantity change within 15%, inclusive) or 8.9.2 (over 15%, exclusive - cuts reasonably raise rates); not applying, the parties negotiate the all-in rates (8.9.3).
- ←
Deciding the settlement of tower-crane base, erection-and-dismantling and off-site transport charges (including where the tower crane was never installed): three charges kept in separate accounts + the "charge as actually incurred" principle + recomputation of preliminaries at final account under BOQ pricing
The tower-crane base is a plant machine-shift "separately computed charge" - in neither the machine-shift rate nor the erection-and-dismantling charge - measured on the physical work actually completed. Erection-and-dismantling is a one-off charge per erection and dismantling (including trial running), counted per actual set-ups and not counted where none occurred. Off-site transport is counted per set-up and generally once per project location. Piling under the base, ground improvement and floor strengthening are outside the items and follow the construction method statement or actual occurrence. At final account of BOQ-priced works the preliminaries are recomputed per GB/T 50500-2024 clauses 10.3.3 and 10.2.7, charging only "the full preliminaries contained in the completed works"; amounts listed in interim (process) settlements do not bind and adjust up or down on recomputation - where the tower crane was never installed, the corresponding preliminaries are reduced.
- ←
The interface for charging superheight increment / efficiency-loss costs on separately tendered building decoration works (including door and window renewal): the trigger-height gate, the work-content gate and the tendering / pricing interface, and how to judge them
Whether separately tendered decoration (including door and window renewal) may charge superheight efficiency loss depends on passing three gates at once: (1) the trigger gate - eaves over 20 m or storeys over 6, either suffices (repair and refurbishment systems go by the work point exceeding 25 m; a building over but a work point not over the line takes nothing); (2) the work-content gate - doors and windows belong to the decoration discipline, sit within the applicable divisional items, and are charged on the decoration labour (in some regions labour plus plant) of the superheight part x the storey coefficient; the main-works "building superheight increment cost" by floor area must not double-count with decoration superheight; (3) the tendering / pricing interface - the cost enters the all-in unit rate of each bill item (SJG 77-2020 clause 5.1.4); where not allotted to the subcontract or already capped by the main contractor, the subcontractor may not claim it again.
- ←
Deciding the pricing type of a contract silent on its price form (colloquially the "fully open contract") and the corresponding scope of quantity and price review
"Fully open contract" is not a legal concept; at normative level only fixed price / adjustable price / cost-plus-fee (Order No. 107 of the Ministry of Construction, Article 12) or unit-rate contract / lump-sum contract / cost-plus-fee contract (GB/T 50500-2024 clauses 2.0.6 to 2.0.8) exist. Where the contract is silent on its price form, classify by pricing mechanism (the basis on which the contract price forms, who answers for quantities, whether drawings or the BOQ prevail in conflict) - never by the contract's name alone. Classified as a re-measurable (unit-rate) contract, quantities are re-verified as executed and all-in unit rates stay fixed within the agreed risk band; classified as a lump-sum contract, only adjustable content and out-of-band risk factors adjust on top of the lump sum and, absent special agreement, re-measurement is inappropriate.
- ←
Delay claims for design changes: critical-path determination, the time/cost double ledger, and the 28-day procedure
Delay caused by events not attributable to the contractor, such as design changes, is claimable, but duration compensation is bounded by the critical path: delays to critical-path activities extend in full; delays to non-critical activities are compensated only for the excess "delay time - total float" once beyond the total float and converted to critical; if still non-critical, no duration is compensated but cost losses remain claimable. Costs include idle labor, machinery standby, efficiency loss, shutdown/restart measures, and rework/demolition; profit may be added for employer-responsibility causes; substantive duration extension links to increased mid-term running costs of preliminary items. Procedurally: a written claim notice within 28 days of the event, then the claim report within the following 28 days — lateness is deemed waiver; on the supervision side, interim/final extension review is required.
- ←
Charging the cost of fine-decoration show flats (model rooms): classifying by nature to determine the cost-attribution path (process → measure costs / delivery → divisional works / display → other-item costs or separate award)
Show-flat costs are charged by first classifying nature, then setting the path: workmanship show flats → preliminaries or amortized into all-in unit rates; delivery-standard show flats → formally listed into divisional-works costs; marketing display show flats → other-item costs (provisional sums etc.) or separately awarded. Show flats are a mandatory pre-procedure of decoration (GB 50210-2018 Clause 3.3.8), and cost attribution follows the GB/T 50500-2024 framework + contract agreement.
- ←
Estimating and apportioning the protection-of-finished-work cost (protection cost of completed works and equipment): two paths — the percentage-rate method and the actual-cost method
The protection-of-finished-work cost belongs to preliminaries (GB/T 50500-2024 Clause 3.2.6). Two estimating paths: (1) the percentage-rate method = base to which percentage rates are applied × percentage rate — under the BOQ basis, on the base of divisional-works costs at range percentage rates from local quota norms; under the railway basis it is merged into construction preliminaries and calculated at (base-period labour cost + base-period plant and small tools cost) × percentage rate (TB 10801-2024 Section 3.6); (2) the actual-cost method = Σ(protection quantity × unit price) + guarding labour + demolition and removal, item by item per the protection scheme, with materials amortized over turnovers. Apportionment may merge into preliminaries for unified charging, be a separately billed item, or amortize into the all-in unit rates of the protected objects; the basis must be agreed in advance in the tender contract.
- ←
Costing temporary access roads (temporary bridges) during road construction: preliminary items listing and three rate build-up paths
Temporary access roads are preliminaries: municipal works list them as "item" per GB/T 50857-2024 Appendix M (041201008 access road / 041201009 temporary bridge), with rate build-up quantities per the approved project execution plan (construction methodology and site organization); three paths — applying quota items (highway JTG/T 3832-2018 7-1-1 truck access road per 1 km, maintenance per 1 km-month charged separately), quantity takeoff (earthwork + pavement + drainage + maintenance + removal and restoration), percentage rate fallback (no special scheme: charge as incurred per the project execution plan; some regional standards allow 2% of the total of the divisional and subdivisional works); temporary bridges amortized with recoverable-material credits; maintenance is the most easily missed.
- ←
GB/T 50500-2024: definitions of the three pricing methods (unit rate / lump sum / rate-based) and their applicability to each BOQ category
GB/T 50500-2024 provides: work-section BOQ items and day-work items should use unit-rate pricing (quantity x comprehensive rate); measures items should use lump-sum or rate-based pricing; provisional sums and specialist-work provisional amounts should use lump-sum pricing; main-contract services should use rate-based or lump-sum pricing (shared passage of Clauses 2.0.10-2.0.12). Clause 3.1.5 is the catch-all: where unit-rate or lump-sum pricing is unsuitable, rate-based or other methods may be used, with pricing requirements and price-adjustment rules stated in the tender and contract documents.
- ←
Fine-decoration cost collection: a spatial-dimension matrix of room → unit type → floor → building, with apportionment and reconciliation
Fine-decoration cost collection builds a two-dimensional matrix of "spatial part × cost element": the room is the smallest accounting unit (divisional items collected per GB/T 50854-2024 Appendices L/M/N/H/Q); elevator lobbies and other public areas go directly to the floor; vertical transport and super-height surcharges are apportioned to unit types by gross floor area (GFA); public areas are apportioned by the ratio of within-unit areas (the basis fixed in advance); reconciliation checks Σrooms = unit type, Σunit types + shared = floor, and floor-by-floor totals = the grand total, with cost accounting keeping the three synchronizations of physical progress, output-value statistics, and cost collection.
- ←
Cost attribution and estimation of temporary hoarding, gates, and wheel-wash facilities on site (basis of mandatory health, safety and environmental (HSE) provisions)
Hoarding, gates, and wheel-wash facilities belong respectively to the site housekeeping and appearance fee, the temporary works and site establishment costs / site monitoring fee, and the dust pollution prevention fee sub-items of mandatory health, safety and environmental (HSE) provisions (a Chinese non-competitive fee; the literal loan translation is misleading, so an institutional note is required); in regions with lump-sum percentage rates they must not be listed separately again; in regions where costs are itemised on an actual basis, estimate by "quantity × unit price" applying quota items + equipment price enquiries; on the railway basis this corresponds to the statutory work safety levy (earmarked funds) + preliminaries, with minor temporary works cost included in preliminaries and heavy temporary works priced by applying quota items on an actual basis.
- ←
Bill of preliminaries classification basis difference between GB/T 50500-2024 and GB 50500-2013: two-way split by measurability vs three pricing methods (unit-rate/lump-sum/percentage-rate)
GB 50500-2013 split preliminary items by 'whether quantities can be computed' into lump-sum items (priced per lump item, e.g., mandatory health, safety and environmental (HSE) provisions, temporary works and site establishment costs) and unit-rate items (quantity × all-in unit rate, e.g., scaffolding, dewatering), encouraging unit-rate pricing of measurable preliminary items; GB/T 50500-2024 abolishes the 'unit-rate/lump-sum preliminary items' dichotomy, replacing it with three pricing methods (clauses 2.0.10–2.0.12): unit-rate pricing, lump-sum pricing, and percentage-rate based pricing — and the recommended direction reverses: bills of preliminaries should use lump-sum pricing (3.2.1); special preliminary items genuinely requiring quantity-based pricing (and subject to expert panel review) move into the work-items list for itemization and pricing; percentage-rate based pricing gains formal terminology status (3.1.5, Appendix E Table E.3.2).
- ←
Risk allocation and adjustment rules for preliminaries (measure) costs: GB 50500-2013 vs GB/T 50500-2024 (omitted items, scheme changes, lump sum plus exceptions)
The 2024 edition restructures preliminaries as "lump sum plus exceptions": completeness/accuracy of the preliminaries list is the contractor's responsibility under both unit-price and lump-sum contracts (3.1.8); omitted items are no longer adjustable except the safety-measures cost and formwork/temporary works listed in the work-item list (8.2.2/8.2.3), whereas under 2013 list omissions were the tenderer's liability (4.1.2, mandatory) and missing preliminaries could be added via an approved scheme (9.5.3). "All preliminaries risk on the contractor" is inaccurate - exceptions like variations, unforeseen provisional-sum works, and employer causes still cost the employer (3.3.7), but only via "submit scheme before execution + mutual confirmation" (8.9.6/8.9.7), failing which the right is forfeited.
- ←
Overheads (company and site) within the all-in unit rate vs. site management fee within lump-sum preliminaries: distinction and prevention of duplicate charging
Overheads (company and site) are on-costs (indirect costs) in nature and enter the all-in unit rate (labour cost + materials cost + plant and small tools cost + overheads (company and site) + profit + agreed risk, excluding value added tax (VAT)), and are settled with the quantities; the legacy 'site management fee' belonged to preliminaries and was lump-summed per item. Since Jian Biao [2003] No. 206, the site management fee has been merged into overheads (company and site), and most provinces no longer list it separately within lump-sum preliminaries; the same management outlay can be charged only once — in preparation and audit review, check that the local quota norm percentage rate basis and the item listing are consistent with each other.
- ←
In-process settlement linked to final account: preliminaries and main-contract service fees are interim payments that must be recalculated at final settlement (GB/T 50500-2024 Clauses 10.2.3/10.2.7/10.3.3)
For projects with in-process settlement, preliminaries costs (and main-contract service fees) must be recalculated at final account - amounts listed in in-process settlements are only "interim payments", not a final-account basis, and are adjusted up or down per the recalculation (GB/T 50500-2024 10.2.3, 10.2.7, 10.3.3). But recalculation does not mean repricing: all preliminaries of the completed works (incl. safety-measures adjustments) are recalculated per Section 7.3 and Chapter 8 against the priced-list amounts, checking the five exceptions of 7.3.1 - absent exceptions, the result still equals the priced-list amount. Substantively consistent with GB 50500-2013's "lump-sum preliminaries per the priced list"; 2024 merely hard-codes the in-process-to-final linkage procedure.
- ←
Ceiling transition layers and reinforcement measures (reverse supports, over-length hangers) must be priced separately: trigger conditions and item attribution
Steel transition layers, reverse supports, and over-length hangers beyond the quota standard length are all outside the regular work content of the ceiling BOQ/quota items and must be priced separately: the transition layer is listed separately under metal-structure works (Appendix F) by theoretical mass in t; reverse supports per steel-structure bracing/reinforcement items; regular hangers are already included in the ceiling items and not priced again.
- ←
GB/T 50500-2024 Appendix E pricing cost summary: Table E.1.1 summary hierarchy (project → single project → unit work) and aggregation rules for billed items, preliminary items, other charges and VAT
GB/T 50500-2024 Appendix E contains a single general summary table — Table E.1.1 "Project summary table" — using three-level numbering (1 → 1.1 → 1.1.1) to express the project → single project → unit work hierarchy; Note 2: "This table is preferably used for the summary calculation of works where the contract subject is the object of preparation of the bill of quantities; works where a single project or unit work is the object of preparation of the bill of quantities may also be summarised using this table." Aggregation rules: billed (BOQ) item costs (the only level expanded down to unit-work detail) roll up level by level; preliminary items (with 2.1 safety-production preliminary items listed separately) and other charges (broken out into provisional sums / provisional sum for nominated specialist subcontract works / dayworks / main contractor's attendance and coordination provisions / other items agreed in the contract) are summarised at whole-project level; VAT is listed separately and its calculation base excludes the provisional sum for nominated specialist subcontract works (Note 1); total = 1+2+3+4. All-in unit rates are fully inclusive prices excluding VAT (Clause 3.1.6, term 2.0.9); statutory levies and fees are no longer listed separately in the 2024 edition, having been merged into management fee; settlement follows Table E.6.1, with amounts adjusting for errors and omissions in the BOQ entered respectively under "contract price adjustment amount" of billed items and preliminary items.
- ←
Measurement and cost adjustment rules for changes to preliminary items caused by design changes (variations) under GB/T 50500-2024
Preliminaries take 'no adjustment' as the principle and 'change-induced' as the exception (GB/T 50500-2024 §7.3.1): first determine the adjustment method by the three nature classes (entity-related / competitively independent / percentage-rate composite); measurement follows the employer-approved implementation scheme and what actually occurred (§7.4.4); for substantive duration changes, preliminaries are adjusted up (down) per §8.9.4 and additional preliminary items are priced per §8.9.5; the disadvantaged party must submit its scheme for confirmation before implementation (§8.9.6), and late submission is deemed waiver of the adjustment right (§8.9.7).
- ←
Methods and liability basis for ensuring completeness of the bill of preliminaries at construction main (general) contracting tender stage (GB/T 50500-2024)
Per GB/T 50500-2024 clause 6.1.5, whether a re-measurable (unit-rate) or lump-sum contract is used, the completeness and accuracy of the bill of preliminaries are the bidder's (contractor's) responsibility, and the bidder bears the risk of the reasonableness of its tender price; preliminary items not priced as required may be deemed included in the all-in unit rates, totals and tender total of other billed (BOQ) items, with no re-pricing or adjustment at construction payment settlement (3.5.4). The contractor should guard against omissions via the six-category 'including but not limited to' framework in 3.2.6 + three cross-checks (bill of preliminaries vs project execution plan (construction methodology and site organization)/tender documents/similar projects) + site inspection + written clarification; statutory safety provisions are non-competitive (3.2.5) and must not be omitted or priced at zero.
- ←
GB 50500-2013 -> GB/T 50500-2024: changes to the clauses on statutory levies and fees, taxes and the mandatory health, safety and environmental (HSE) provisions — mandatory provisions withdrawn, the bills restructured into four parts, and the item renamed statutory safety provisions
2013 Clause 3.1.6, “statutory levies and fees and taxes must be calculated in accordance with the provisions of the state, provincial or industry construction authorities and shall not be treated as competitive costs” (a mandatory provision), disappears entirely from GB/T 50500-2024: the 2024 edition is a recommended GB/T standard with no mandatory provisions anywhere; under Clause 3.1.2 the bills become four parts (work items / preliminaries / provisional sums and other charges / VAT), statutory levies and fees are no longer a separate billed item, and taxes are renamed VAT (Clause 3.2.11: the tax base is the total of work items + preliminaries + other items, less the provisional sum for nominated specialist subcontract works, multiplied by the tax rate). The mandatory health, safety and environmental (HSE) provisions are renamed “statutory safety provisions” (Clause 3.2.5), and their “non-competitive” character is expressly retained (“is a non-competitive item”), but the wording is softened from “must ... shall not be treated as competitive costs” to “shall be priced in accordance with the relevant provisions of the state and provincial or industry authorities”. GB/T 50500-2024 takes effect on 1 September 2025, and GB 50500-2013 is repealed at the same time.
- ←
Definition and pricing rules for preliminary items that cannot be measured precisely (Jing Jian Fa [2021] No. 11: class with issued management documents vs class without such documents)
Preliminary items that cannot be measured precisely = preliminary items whose quantities cannot be computed precisely from the dimensions shown on the construction drawings, whose cost is directly related to the construction method statement and/or the duration of input, and which are generally priced as a lump sum per item (Jing Jian Fa [2021] No. 11). Such items not covered by the "cost indicators" in the published construction cost information for Beijing fall into two classes: a) those with issued management documents (mandatory health, safety and environmental (HSE) provisions, acceleration measure increase costs, and off-site haulage and disposal of construction waste) are governed by those documents, and the cost must not fall below the floor cost standards; b) those without corresponding management documents (e.g. secondary handling, protection of completed works and equipment, night-work increase costs) should preferably be added as separately billed items with clearly defined scope of work and calculation rules, and reasonably determined by the contractor's own estimation on market-based pricing principles in accordance with the method statement. For protection of completed works: Beijing has no official percentage rate, so a percentage-rate approach has no documentary basis; the actual-cost method plus a separately billed item should be used.
- ←
Incorporating design changes (designer-issued variations) into the final account: position of the final account price item, pricing ladder, and procedural requirements
Once a design change (designer-issued variation) is confirmed and established, its price is determined by the ladder 'identical contract item -> similar item -> negotiated rate build-up' and is included in the final account documents as item 9 of the final account price, 'increase/decrease due to variations'; the variation adjustment price certified and signed off by both parties is paid concurrently with progress payments and stage settlement payments during construction, and the certified and signed-off stage settlement price serves as the basis for the final account where the contract has no special agreement.
- ←
Estimating traffic diversion (traffic relief) costs of municipal works: pricing attribution and two estimation paths
Traffic diversion cost is a preliminary item charged in the bill of preliminaries. Two estimation paths: (1) scheme-quantity method (mainstream) — item-by-item quantity take-off and pricing per the approved project execution plan/special diversion scheme (temporary roads, temporary bridges, hoarding, signs, markings, separation, signal lights, traffic wardens, efficiency loss, removal and restoration, etc.); (2) percentage-rate fallback — without a specific scheme, charge traffic management provisions as a percentage of the divisional-work BOQ total per local rules. GB/T 50903-2013 Clause 6.7.1 requires compiling traffic organization measures, which underpin the estimation.
- ←
Vertical transportation quantity calculation: buildings by floor area (incl. basements) x eave-height steps, structures by count/volume, rules for height-increase fees
Vertical transportation is a preliminaries (measures) item; the BOQ covers only large vertical-transport plant (tower cranes, construction hoists, material hoists etc.) — hoisting plant and manual assistance are already included in the work content of trade items and must not be double-counted. Buildings apply quota items by floor area (incl. basements) with structural type and eave-height steps; single-storey buildings with eaves <=3.6 m are excluded; structures (chimneys, water towers, silos, elevator shafts etc.) are counted per unit; foundations without basements with embedment depth >=4 m and underground water pools are measured by volume per design dimensions; the height-increase fee is computed on the floor area of the super-height portion, with eave height stepped per additional 10 m — remainders over 5 m (but under 10 m) count as 10 m, and 5 m or under is not counted.
- ←
Can a practice omitted from the BOQ (missing item) but mandatorily required by codes be deducted at the final account? - the judgment chain of contract type x pricing classification (GB/T 50500-2024) and the judicial approach to missing-item risk
A practice omitted from the BOQ but mandatorily required by codes is not automatically deductible: under a unit-rate contract the completeness of the divisional-item BOQ is the client's responsibility (GB/T 50500-2024 Clauses 3.1.8, 6.1.6) - a genuine omission already constructed is adjusted as a BOQ defect under 8.2.1 and repriced per 8.9.1 at up to the 15% boundary; under a lump-sum contract the priced divisional-item BOQ is the contractor's responsibility and, in principle, the contract price is not adjusted for BOQ defects (6.1.7, 8.2.3); practices that are per-item measures items, or already contained in the work content of BOQ items such as doors/windows and curtain walls, are deductible (3.1.8, 6.1.5, 8.2.2); where the contractor failed to perform a mandatory obligation, rectification comes first (at its own cost) and deduction at the final account is well-founded (10.3.13). Judicially, where missing items exceed a reasonable range and both parties are at fault, the loss may be apportioned per fault and the principle of good faith.
- ←
Design change overview: authority to propose, classification and grading, approval and implementation, three-tier pricing, settlement and disputes across six links (with variation concept cross-links and FIDIC mapping)
The design-change full chain: any of four parties may propose; only the original designer issues the document (Survey and Design Administration Regulations, art. 28); the chief supervising engineer must sign it off before construction; approve first, then construct; price on the three-tier ladder; settle on the documents. Procedural red lines: verbal instructions are no pricing voucher (unless construction per them is proven); the supervisor's emergency verbal instruction must be confirmed in writing within 24 hours (local supervision codes); emergency-rescue works proceed first with formalities completed within 10 working days. Pricing runs the ladder "identical — contract rate; analogous — converted; different — negotiated" (GB/T 50500-2024 cl. 8.9.1), with quantities beyond ±15% re-rated (down for increases, up for decreases) and the preliminaries scheme to be submitted before execution or the adjustment forfeited. Claims run the double 28-day limit, forfeited on default; the variation price takes the ninth head of the final account, disputes assessed across five tiers by instructions, drawings and confirmations.
- ←
Nature and pricing rules of statutory safety provisions (GB/T 50500-2024: non-competitive item, whole-process constraints, and the change in normative force)
GB/T 50500-2024 Clause 3.2.5 states that the statutory safety provisions in the bill of preliminaries "shall be priced per the relevant provisions of the state, provincial, and industry authorities" and "are a non-competitive item" — their standard is not formed by market competition. Clause 2.0.4 defines them as the special fee safeguarding construction production safety; Clauses 5.2.5/6.2.6/9.3.1/9.3.4 enforce "compliance with authority provisions + ring-fenced (earmarked) use of funds, no diversion" across the tender price ceiling, tenders, and interim payments. The old GB 50500-2013 Clause 4.1.5 (mandatory provisions of codes: "must... shall not be a competitive fee") lost its mandatory force when the standard changed to a recommended GB/T; current binding force rests on administrative documents of the authorities and tendering supervision practice.
- ←
FIDIC Red Book 2017 Variations vs China's variation/new-works regime (13.1 vs GB/T 50500-2024 2.0.28/2.0.30, 8.1.1 and T/ZBD 100.4-2023 4.6.1)
The two share one origin and structure: GB/T 50500-2024 term 2.0.28 "variation of works" - additions, deletions, cancellations, substitutions - maps item-by-item onto FIDIC 2017 Red Book 13.1's six variation cases (quality/characteristics, position/dimensions, omissions, necessary additional work for the Permanent Works, sequence/time); the omission safeguard "except work transferred to others" matches T/ZBD 100.4-2023 4.6.1's five appraisal situations. The biggest divergence: China lists physical works outside the contract scope separately as "new works (extra work)" (term 2.0.30), parallel to variations as two adjustment channels in 8.1.1, preventing unlimited scope expansion by variation orders; the FIDIC Red Book has no standalone "new works" - additional work necessary for the Permanent Workers folds directly into the variation procedure. Initiation and validity: FIDIC variations are Engineer-initiated and the contractor may not alter the Works; the Chinese definition makes employer approval the validity element.