Preliminaries — the "lump sum, no adjustment" principle and the full landscape of adjustable exceptions (GB/T 50500-2024 cl. 3.3.7, 7.3.1)
Under GB/T 50500-2024, the China national pricing standard for BOQ (Code of Valuation with Bill of Quantities of Construction Works), preliminaries follow a lump-sum no-adjustment principle, reflected at three levels: (1) the construction method statement reported at tendering is deemed reasonable and feasible, the cost is priced as a lump sum, and the contractor bears the risk of cost increases arising from adjusting its own method statement (cl. 3.3.7); (2) preliminary items in the priced BOQ shall not be re-measured or adjusted (cl. 7.3.1); (3) preliminaries are not adjusted for changes in costs (cl. 8.7.6 item 3). Exception channels: preliminary works listed as billed (BOQ) items and items the contract requires to be measured (cl. 7.2.1, 7.2.2); statutory safety provisions (per contract); variations (measured per cl. 7.4.4, priced per cl. 8.9); errors and omissions in the BOQ (cl. 8.2.2, 8.2.3); unforeseeable works within provisional sums (cl. 7.7.2); delayed use, removal/re-installation, increase or duplicated provision of the contractor's preliminary items due to the employer, and material changes to the time for completion (costs borne by the employer, cl. 3.3.7). Under re-measurable (unit-rate) contracts, only the statutory safety provisions and BOQ-listed formwork/temporary works etc. are adjustable for BOQ errors and omissions (cl. 8.2.2). Adjustments require "submitting the method statement for confirmation before implementation" (cl. 8.9.6); late submission is deemed waiver, and the other party's late confirmation is deemed acceptance (cl. 8.9.7).
Applicable Codes
- GB/T 50500-2024 第3.3.7条(措施费包干与三类例外)
- GB/T 50500-2024 第7.3.1条(措施项目计量调整封闭清单)
- GB/T 50500-2024 第7.4.4、8.9.4、8.9.5、8.9.6、8.9.7条(工程变更引起措施项目计量与计价)
- GB/T 50500-2024 第8.2.1、8.2.2、8.2.3条(工程量清单缺陷)
- GB/T 50500-2024 第8.7.6条(物价变化不调费用)
- GB/T 50500-2024 第8.8.1条(法律法规及政策性变化)
- GB/T 50500-2024 第7.7.2条(暂列金额)
- GB 50500-2013 第9.6.3条(量差联动,已废止)
- GB 50500-2013 第9.3.2条(变更引起措施项目费调整,已废止)
Topic Positioning
This card maps the complete framework of the lump-sum pricing principle for preliminaries under GB/T 50500-2024, the China national pricing standard for BOQ (Code of Valuation with Bill of Quantities of Construction Works), and its adjustable exceptions: which situations lock the cost (including the three high-probability events of the contractor adjusting its own method statement, changes in costs and errors and omissions in the BOQ), which channels allow adjustment with their clause basis, and the procedural requirements any adjustment must follow. Applicable to building, municipal and other works priced on a bill of quantities basis under the 2024 standard.
Core Conclusions
I. The lump-sum no-adjustment principle (three levels)
- Method statement deemed reasonable and feasible -> lump-sum cost (cl. 3.3.7): "The preliminary items construction method statement reported by the contractor at tendering shall be deemed reasonable and feasible and to meet actual construction requirements; its preliminaries are priced as a lump sum, and the contractor shall bear the risk of increases in preliminaries caused by adjusting its own construction method statement." Where the contractor's tendered method statement is infeasible, beyond its capability, or must be adjusted at cost increase, the contractor bears it alone.
- Preliminary items in the priced BOQ are not re-measured or adjusted (cl. 7.3.1): "Except as otherwise agreed in the contract and as provided below, preliminary items in the priced BOQ shall not be re-measured or adjusted"; moreover, "regardless of whether the contractor supplemented and completed the preliminary items and pricing in the priced BOQ at tendering as required, preliminary items shall not be re-measured or adjusted for all preliminary items corresponding to the preliminaries contained in the contract price and for BOQ item changes arising from performing contractual obligations".
- No adjustment for changes in costs (cl. 8.7.6 item 3): preliminaries are among the costs that "shall not lead to adjustment of the contract price or contract unit rates due to changes in costs".
II. Adjustable exception channels (five items of cl. 7.3.1 + situations merged from cl. 3.3.7) (1) Preliminary works listed as items of the work-section BOQ and preliminary items the contract requires to be measured — per cl. 7.2.1 and cl. 7.2.2; (2) Statutory safety provisions — per the contract (non-competitive); (3) Preliminary item changes caused by variations — measured per cl. 7.4.4 (quantities of additionally invested construction management personnel, site accommodation and other construction measures computed from the employer-approved implementation method statement or actually incurred contents), priced and adjusted per section 8.9; (4) Preliminary item changes caused by errors and omissions in the BOQ — per cl. 8.2.2 and cl. 8.2.3. Narrowed under re-measurable (unit-rate) contracts (cl. 8.2.2): apart from statutory safety provisions computed per the contract, formwork works and temporary works listed in the work-section BOQ, and preliminary items the contract requires to be measured, "other preliminary items are not adjusted for errors and omissions in the BOQ", and neither the bill of preliminaries of the contract BOQ nor the contract time for completion shall be adjusted; (5) Preliminary item changes caused by works contained in provisional sums that could not be fully foreseen or specified — per cl. 7.7.2; (6) Cost increases from delayed use, removal/re-installation, increase or duplicated provision of preliminary items provided by the contractor due to the employer — adjusted per cl. 3.3.7 through the relevant provisions of Chapter 8; (7) Material changes to the time for completion caused by variations, unforeseen works within provisional sums, or employer-caused interference that affect preliminary items and prices or add preliminary items — cl. 3.3.7 expressly states "the increased costs shall be borne by the employer"; (8) Provisional sums used, at the employer's request, for works that could not be fully foreseen or specified, variations, interference, discovery of cultural relics etc. — final paragraph of cl. 7.3.1: the corresponding measures costs shall be measured and adjusted.
III. Other locking/bottom-line provisions
- The measures fee of specialist works under provisional sums for nominated specialist subcontract works is already included in the total contract price of the corresponding subcontract; it shall not be measured again (cl. 7.3.1, 7.3.3);
- The preliminaries of provisional sums are already included in the preliminary items of the priced BOQ; except for the uses in cl. 3.2.6 item 5 (variations, additional works, claims, works that could not be fully foreseen or specified), they shall not be additionally measured or adjusted (cl. 7.3.3); cl. 8.3.4 likewise states that apart from preliminary items and time changes caused by variations, unforeseen works, additional works or claims, other uses of provisional sums do not involve adjustment of preliminaries.
IV. Procedural requirements (method statement approved first, priced after)
- Cl. 8.9.6: when a variation causes a preliminary item to change, the disadvantaged party shall submit the proposed implementation method statement to the other party for review before implementation, detailing the changes compared with the original method statement's preliminary items; after confirmation by both parties, the preliminaries may be adjusted per cl. 8.9.4 and cl. 8.9.5. The contractor shall submit the implementation method statement, extension of time and additional preliminaries claims to the employer in writing for review, and compute and adjust the contract price per the employer-approved implementation method statement.
- Cl. 8.9.7: if the disadvantaged party does not request adjustment of preliminaries within the agreed time, the variation is deemed not to cause changes in preliminaries, or the right of adjustment is waived; if the other party fails to confirm or comment within the time limit, it is deemed to have accepted.
- Cl. 7.4.4: additional preliminary items are measured by the types of additional site accommodation determined in the contractor's method statement approved by the employer, actually incurred quantities and usage durations, and the models, numbers and consumed machine-shifts of additional construction machinery; increased costs from delayed use of existing preliminary items and additional management personnel caused by variations off the critical path may go unmeasured, deemed included in the preliminaries within the contract price.
Applicable Boundaries
- Precondition: works priced under GB/T 50500-2024 (building, municipal etc.); where railway, highway or other industry standards provide otherwise, those provisions prevail.
- "Except as otherwise agreed in the contract" (opening of cl. 7.3.1) — contractual agreement takes precedence; this card's principles apply only where the contract has no special agreement.
- This card gives the principle and exception-channel framework; specific measurement and pricing details (cl. 8.9.4 time-change adjustment formulas, cl. 8.9.5 pricing of additional preliminary items, cl. 8.2.3 BOQ errors and omissions adjustment) require the corresponding clauses.
- The classification of preliminary items into unit-rate, lump-sum and percentage-rate pricing and each of their adjustment rules are covered by related dedicated cards, not expanded here.
Further Reading
- Core provisions: GB/T 50500-2024, cl. 3.3.7 (lump-sum pricing principle), cl. 7.3.1 (no re-measurement/adjustment and the five exceptions), cl. 7.3.3 (provisional-sum measures fees), cl. 7.4.4 (measurement of varied preliminary items), cl. 8.2.2 (scope of preliminary item adjustment for BOQ errors and omissions under re-measurable (unit-rate) contracts), cl. 8.3.4 (provisional-sum events and measures fees), cl. 8.7.6 (list of costs not adjustable for changes in costs), cl. 8.9.6 and 8.9.7 (adjustment procedure and waiver/deemed-acceptance rules).
- Extended reading: cl. 7.2.1 and 7.2.2 (measurement methods), cl. 7.7.2 (measurement of unforeseen works), cl. 8.9.4 and 8.9.5 (pricing adjustment of preliminary items caused by variations), cl. 3.2.6 item 5 (uses of provisional sums).
- Evidence for this card comes from the standard's provisions; no official government release URL.
Keywords
- 措施项目费调整
- 包干不调
- variation
- errors and omissions in the BOQ
- 政策法规变化
- cost fluctuation
- 工期延长
- 量差联动