Measurement and cost adjustment rules for changes to preliminary items caused by design changes (variations) under GB/T 50500-2024

Preliminaries take 'no adjustment' as the principle and 'change-induced' as the exception (GB/T 50500-2024 §7.3.1): first determine the adjustment method by the three nature classes (entity-related / competitively independent / percentage-rate composite); measurement follows the employer-approved implementation scheme and what actually occurred (§7.4.4); for substantive duration changes, preliminaries are adjusted up (down) per §8.9.4 and additional preliminary items are priced per §8.9.5; the disadvantaged party must submit its scheme for confirmation before implementation (§8.9.6), and late submission is deemed waiver of the adjustment right (§8.9.7).

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • T/ZBD 100.5-2023 建设工程结算审核作业指引
  • GB/T 51262-2017 建设工程造价鉴定规范
  • TB 10801-2024 铁路工程概预算编制办法

Topic Positioning

How preliminaries are measured and adjusted when design changes (which are variations) cause changes to preliminary items: the general principle, classification of preliminary items, the measurement and pricing paths, and the procedural red lines. Based on GB/T 50500-2024 Clauses 7.3.1, 7.4.4, 8.9.4-8.9.7, 8.10.4 and T/ZBD 100.5-2023 Clause 3.1.6.

Core Conclusions

  1. General principle (§7.3.1): preliminary items in the priced BOQ are in principle not measured or adjusted; 'changes to preliminary items caused by variations' is the explicit exception, handled per §7.4.4; BOQ errors/omissions and variations are two separate tracks — under a re-measurable (unit-rate) contract, preliminaries are not adjusted for BOQ errors/omissions (§8.2.2).
  2. First classify by nature to fix the adjustment method (T/ZBD 100.5-2023 §3.1.6): (a) entity-related preliminary items (formwork, scaffolding) — adjusted in step with the entity quantities and priced at the contract all-in unit rate; (b) competitively independent preliminary items (slope protection, dewatering, retaining works, temporary roads, hoarding) — listed per the contract agreement or the original tender price; (c) percentage-rate/scheme composite preliminary items (mandatory health, safety and environmental (HSE) provisions, vertical transport fee, super-high construction addition fee) — recalculated using the base to which percentage rates are applied and the percentage rate per state regulations and the contract.
  3. Measurement (§7.4.4): newly added management personnel, temporary works and site establishment costs, and preliminary item quantities are measured per the contractor's implementation scheme drawn up specifically for the variation and approved by the employer, or per what actually occurred; newly added machinery is measured by model, count, and shift consumption; where the variation alters the duration, link with §8.9.4 via the approved extended/shortened time. Delay-induced continued use of existing preliminary items and management personnel caused by variations on non-critical paths is not measured (deemed included in the contract price).
  4. Pricing: for substantive duration changes (critical path), the increase (decrease) in preliminaries = extended (shortened) duration × the mid-term running cost of the affected preliminary items (§8.9.4); additional preliminary items needed to complete the variation — newly added machinery at the corresponding dayworks list unit rate (absent a list, per §8.6.3), newly added temporary works and site establishment costs at a reasonable market price negotiated by both parties (§8.9.5); where the variation constitutes additional works, the preliminaries cover five items — machinery, temporary works and site establishment costs, mandatory health, safety and environmental (HSE) provisions, management personnel, and necessary measures (§8.10.4). The mandatory health, safety and environmental (HSE) provisions are non-competitive charges (§3.2.5) and are not subject to negotiated downward adjustment.
  5. Procedural red lines (§8.9.6/8.9.7): the disadvantaged party shall submit the intended implementation scheme to the other party for review and confirmation before the variation is implemented; late submission is deemed waiver of the adjustment right, and the other party's late confirmation is deemed acceptance.

Applicable Boundaries

Applies to adjustments to preliminary items under re-measurable (unit-rate) and lump-sum contracts caused by variations (including design changes); contract agreements prevail. Not applicable to: changes to preliminary items caused by BOQ errors/omissions (§8.2.2/8.2.3); preliminaries when dayworks occur (already included in the dayworks unit rate, §8.6.4); delayed use of existing preliminary items on non-critical paths; adjustment claims without an approved scheme or reported only after implementation. In railway works the 'mandatory health, safety and environmental (HSE) provisions' correspond to the 'statutory work safety levy (earmarked funds)', listed per TB 10801-2024 Clause 3.11.11.

Further Reading

GB/T 50500-2024 'China national pricing standard for BOQ (GB/T 50500)' §7.3.1, §7.4.4, §8.9.4-§8.9.7, §8.10.4, §3.2.5, §8.6.4; T/ZBD 100.5-2023 'Guidelines for final account review practice of construction works' §3.1.6 item 5; for duration extension and critical-path identification in variations see GB/T 51262-2017 'Code for construction cost expert assessment (judicial appraisal)' §5.7.5.