Railway work safety fee (mandatory health, safety and environmental (HSE) provisions): calculation rate, non-competitive nature, and earmarked-fund management rules

The railway work safety fee is accrued at 3.0% of the construction and installation engineering cost (TB 10811-2024 Clause 2.11.9), with use limited to the ten categories of expenditure in TB 10801-2024 Table 3.11.11 and no duplicate accrual elsewhere in the estimate (budget); it is a non-competitive cost that must be separately accrued in tender prices and must not be used as a competitive bid item; it is managed as earmarked funds — reviewed and signed by the supervisor, disbursed on actual expenditure, strictly protected from diversion, and must not be lump-summed.

Applicable Codes

  • TB 10811-2024 铁路基本建设工程设计概(预)算费用定额
  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
  • 交通运输部令2017年第25号 公路水运工程安全生产监督管理办法
  • GB 50656-2011 施工企业安全生产管理规范

Topic Positioning

This card answers "how the mandatory health, safety and environmental (HSE) provisions are calculated, whether they may be discounted for competition, and whether they may be lump-summed": primarily the railway basis (called the "work safety fee"), also covering highway and waterway works and general contractor management requirements, for estimate/budget preparation, tender pricing compliance review, and safety fund management.

Core Conclusions

  1. Calculation: the railway work safety fee is accrued at 3.0% of the cost of works (construction and installation) (TB 10811-2024, Cost Quota for Design Estimates (Budgets) of Railway Capital Construction Works, Clause 2.11.9); use is limited to the ten expenditure categories listed in TB 10801-2024, Measures for Preparing Design Estimates (Budgets) of Railway Capital Construction Works, Table 3.11.11 (safety protection facilities and equipment, emergency rescue, major hazard source monitoring and hidden-danger rectification, safety inspection and assessment consulting, protective articles, publicity/training and hidden-danger reporting rewards, promotion of the "four new technologies", inspection/testing/verification/calibration, work safety liability insurance, etc.). Items in the table must not be accrued again elsewhere in the estimate (budget); formal protection works outside the table are listed separately in the formal works chapters per the design.
  2. Non-competitive: tender prices must include the work safety cost, accrued separately, and it must not be used as a competitive bid item; the tenderee may not demand discounts and bidders may not compete on it (Ministry of Transport Order No. 25 of 2017, Article 21). In practice, even where the lump sum is discounted, this item stays fully listed and outside the discount.
  3. Not lump-summed: the fund is implemented as "earmarked, timely and in full" (GB 50656-2011 Clause 8.0.4), disbursed on actual expenditure into the construction cost after supervisor review and sign-off and the employer's consent; diversion is strictly prohibited, and lump-sum arrangements must not be used to divert it.

Applicable Boundaries

Railway projects follow the TB 10811/TB 10801 basis; highway and waterway projects follow Ministry of Transport Order No. 25 of 2017; building, municipal and other disciplines follow the rates set by national and provincial construction authorities (generally a percentage of the cost of works), likewise not floating with contractors' own bids. For railways, Order No. 25 of 2017 is a management-principle reference only — the railway cost quota governs. Rates may change with quota revisions; verify the current effective edition when using.

Further Reading

See TB 10811-2024 Clause 2.11.9, and Clauses 2.11.7, 2.11.8 (other consulting service fees and operating-line construction cooperation fees, for cost-boundary distinction); TB 10801-2024 Clause 3.11.11 and Table 3.11.11 (details of the ten use categories); Ministry of Transport Order No. 25 of 2017, Measures for Supervision and Administration of Work Safety of Highway and Waterway Works, Article 21; GB 50656-2011, Code for Work Safety Management of Construction Enterprises, Clause 8.0.4. For the building/municipal basis see also the clauses of GB/T 50500-2024 on pricing of mandatory health, safety and environmental (HSE) provisions.