Prepayment and payment rules for statutory safety provisions (GB/T 50500-2024 Clauses 9.3.2, 9.3.3): not less than 50% prepaid within 28 days of commencement, paid alongside progress payments, recovered in one lump sum at final account

Under Clause 9.3.2 of GB/T 50500-2024, the China national pricing standard for BOQ, the employer shall, within 28 days after commencement, prepay to the contractor not less than 50% of the total statutory safety provisions; the remainder shall be broken down on the "arrange in advance" principle and paid alongside progress payments; for multi-year major works the prepaid total may be broken down by reference to the annual programme of works. When computing progress payments due, the prepaid safety provisions shall not be recovered; they are recovered in one lump sum at final account. Clause 9.3.3: where the employer fails to pay by the agreed time, the contractor may give notice; if payment is still not made within the agreed period after such notice, the contractor is entitled to suspend the works and the employer bears liability for breach of contract; where a safety accident occurs because the employer failed to pay the statutory safety provisions on time, the employer bears the corresponding responsibility.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 9.3.2 条、第 9.3.3 条

Topic Positioning

This card covers the prepayment and payment mechanism for statutory safety provisions (mandatory health, safety and environmental (HSE) provisions) under Clauses 9.3.2 and 9.3.3 of GB/T 50500-2024, the China national pricing standard for BOQ: prepayment timing and percentage, the principle for breaking down the balance, the relationship with progress payments, the point of recovery, and the legal consequences of late payment by the employer. It applies to interim payment management under construction contracts concluded on the basis of this standard.

Core Conclusions

Clause 9.3.2 (as worded, in the interim payment chapter):

  • The employer shall, within 28 days after commencement, prepay to the contractor not less than 50% of the total statutory safety provisions; the remainder shall be broken down on the "arrange in advance" principle and paid alongside progress payments.
  • For multi-year major works, the prepaid total of statutory safety provisions may be broken down by reference to the annual programme of works.
  • When computing progress payments due, the parties shall not recover the prepaid statutory safety provisions.
  • The statutory safety provisions shall be broken down on the "arrange in advance" principle and recovered in one lump sum at final account.

Clause 9.3.3 (consequential provision): where the employer fails to pay by the agreed time, the contractor may give notice; if payment is still not made within the agreed period after such notice, the contractor is entitled to suspend the works and the employer bears liability for breach of contract; where a safety accident occurs because the employer failed to pay the statutory safety provisions on time, the employer shall bear the corresponding responsibility.

Key points:

  • Prepayment floor: within 28 days of commencement, not less than 50% of the total statutory safety provisions — a mandatory timing and percentage requirement on the employer;
  • Distinct from the advance payment (materials advance, 10%–30% of the contract price under §9.2): the safety-provisions prepayment is not recovered in progress payments but in one lump sum at final account;
  • For multi-year major works, the prepaid total may be broken down by reference to the annual programme of works;
  • Late payment triggers notice → suspension of the works → liability for breach of contract, and is linked to liability for safety accidents.

Applicable Boundaries

  • Applies to payment of statutory safety provisions under construction contracts concluded on the basis of GB/T 50500-2024; railway and other sectors book their work safety levies under their own standards (e.g. TB 10811-2024: 3.0% of the cost of works (construction and installation)), but all such sums are non-competitive, must be listed separately in tenders, and are subject to ring-fenced (earmarked) use of funds — their payment rules may refer to this standard.
  • This card covers payment timing, breakdown and recovery only — not the calculation base, percentage rate, or scope of use of the safety provisions (see related cards).
  • "Within 28 days, not less than 50%" is a floor; where the contract provides better terms (higher percentage / earlier payment), those terms prevail.

Further Reading

  • See GB/T 50500-2024 Clauses 9.3.2 and 9.3.3 (Chapter 9, interim payment of contract price); related clauses: 9.1.7 (progress payment percentage should not be less than 80% of the cumulative value of works completed), 9.2.2 (advance payment should not be less than 10% and not more than 30% of the contract price).
  • For the calculation basis of safety provisions, see the cards on "calculation basis for work safety levies in non-railway works" and "railway work safety levy percentage rate"; for the relationship between recovery and progress payments, see the cards on "advance payment recovery mechanism" and "computation of progress payments".