The advance-payment recovery mechanism: two recovery modes, the start-recovery-point formula, and related rules (GB/T 50500-2024 §9.2/9.1.7/9.3.2)
Advances are recovered per the contract; if unclear, either mode: one-time recovery (fully deducted once cumulative completed value reaches the agreed share of the contract price) or installment recovery (deducted proportionally from each progress payment or interim settlement by construction stage until the agreed amount). On contract termination, unrecovered portions are fully recovered in the termination settlement. The practice start-recovery-point formula T = P - M/N (from the Cai Jian [2004] No. 369 practice). Related: absent agreement, progress payments no less than 80% of cumulative completed value; the statutory safety provisions advance is not recovered from progress payments but once at the final account; the guarantee decreases as recovery proceeds and is returned when fully recovered.
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第9.2.6条
- GB/T 50500-2024 第9.2.2条
- GB/T 50500-2024 第9.2.3条
- GB/T 50500-2024 第9.2.5条
- GB/T 50500-2024 第9.1.7条
- GB/T 50500-2024 第9.3.2条
- 财建〔2004〕369号《建设工程价款结算暂行办法》(通行做法参考)
Topic Positioning
A dedicated card on the advance (material-preparation) payment recovery mechanism: choice of recovery mode, the start-recovery-point calculation, and the linkage with progress payments, the statutory safety provisions advance, and guarantees, under GB/T 50500-2024 Chapters 9 and 10.
Core Conclusions
Recovery follows "contract agreement first" (9.2.6): the start point, ratio, and mode should be written into the contract. If unclear, either mode: (1) one-time — fully deducted once cumulative completed value reaches the agreed share of the contract price; (2) installments — deducted proportionally from each payable progress payment or interim settlement by construction stage until the agreed advance amount. On early contract termination, unrecovered portions are fully recovered in the termination settlement. The practice start-point formula T = P - M/N (T = cumulative completed value at start of recovery, P = contract price, M = advance amount, N = share of main materials and components in the total price) derives from the Cai Jian [2004] No. 369 practice — not mandated by the new national standard; the contract prevails. Related rules: absent agreement, progress payments should be no less than 80% of cumulative completed value (9.1.7); progress payments shall not recover the statutory safety provisions advance, which is recovered once at the final account (9.3.2); the advance guarantee amount decreases with recovery, remains valid until fully recovered, and is promptly returned thereafter (9.2.5); interim settlement by construction stage payment applications list "current advance recovery" as a separate deduction item (10.2.10).
Applicable Boundaries
For advances on labor-and-material contracts; multi-year major projects prepay yearly per the annual plan and recover per year (9.2.3); the advance base deducts provisional sums, dayworks amounts, and provisional sums for nominated specialist subcontract works (9.2.2). The start-point formula is an industry algorithm, not a mandatory provision — the contract prevails on conflict; employer-supplied material recovery is out of scope.
Further Reading
GB/T 50500-2024 Section 9.2 (advances: 9.2.1 nature / 9.2.2 base / 9.2.3 multi-year / 9.2.5 guarantee / 9.2.6 recovery), 9.1.7 (payment floor; safety provisions advance not recovered), 9.3.2 (safety provisions advance prepayment and one-time recovery at the final account), 10.2.10 (interim settlement by construction stage deduction listing); start-point formula per Cai Jian [2004] No. 369 "Interim measures for construction price settlement"; the term per GB/T 50875-2013 "Standard for construction cost terminology" 3.4.1.
Keywords
- 预付款扣回
- 起扣点
- T=P-M/N
- 主要材料及构件比重
- 累计产值比例法
- 分次扣回
- 一次扣回