Appendix F Table F.3.1 progress-payment application (approval) form of GB/T 50500-2024: structure, six reporting items, and prepayment deduction entries
Table F.3.1 is a six-row form (each row with application/verification amount columns) matching the six items of 9.4.9: (1) cumulative completed gross value (11 sub-items), (2) cumulative recovered prepayments (incl. current), (3) cumulative payable progress payment, (4) prior cumulative paid progress payments, (5) amounts the employer should deduct, (6) current payable progress payment. Prepayment deduction goes in row 2 "cumulative recovered prepayment" (cumulative figure); current deduction = current cumulative minus prior cumulative, also part of row 5; progress payments shall not recover safety-production measure prepayments (9.1.7). Four copies; preparer and Grade-1 registered cost engineer sign and seal; contractor representative, supervising engineer, and employer representative sign or seal.
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第9.1.7条、第9.2.6条、第9.4.9条、App. FTable F.3.1
Topic Positioning
The structure, reporting content, and correspondence with the six items of clause 9.4.9 of Appendix F Table F.3.1 "Progress payment application (approval) form" in GB/T 50500-2024, focusing on the practical question "how prepayment deduction is reflected on the form".
Core Conclusions
1. Payment application contents (9.4.9 original): the contractor shall submit, by each agreed measurement cycle and payment verification date, an application for completed-work progress payments stating amounts considered due — including application amounts for construction workers' wages and progress payments of specialized subcontractors for completed works — with calculation bases. Six items:
- Cumulative completed gross value, with 11 sub-items: (1) cumulative price of contract list items completed; (2) cumulative BOQ-defect adjustments (unit-price re-measurement adjustments; lump-sum provisional-quantity adjustments); (3) cumulative provisional-sum amounts; (4) cumulative provisional-sum adjustments (materials; contractor-executed specialized works); (5) cumulative general-contractor service fee adjustments; (6) cumulative dayworks; (7) cumulative price-fluctuation adjustments; (8) cumulative law/regulation/policy adjustments; (9) cumulative variation amounts; (10) cumulative new-works amounts; (11) cumulative claims.
- Cumulative recovered prepayments (incl. current recovery); 3. cumulative payable progress payment; 4. prior cumulative paid progress payments; 5. amounts the employer should deduct; 6. current payable progress payment.
2. Calculation caliber: progress payments are computed as the difference between cumulative completed and cumulative paid contract prices (cumulative difference method), separately listing construction workers' wages payable currently.
3. Form structure and filling: six rows with "application amount / verification amount / remarks" columns matching the six items (row 1 cumulative gross value; row 2 cumulative recovered prepayment; row 3 cumulative payable; row 4 prior cumulative paid; row 5 employer deductions; row 6 current payable). Following: contractor signature block, supervising engineer and Grade-1 registered cost engineer review blocks, employer review block. Table notes: four copies — employer, supervisor, cost consultant, contractor each keep one; the preparer and Grade-1 registered cost engineer shall sign and seal; contractor representative, supervising engineer, and employer representative shall sign or seal.
4. Prepayment deduction on the form: enter row 2 "cumulative recovered prepayment" with the cumulative figure (incl. current recovery); the current deduction = current cumulative minus prior cumulative, which also forms part of row 5 "employer deductions", i.e., row 6 = row 3 - row 4 - row 5. Recovery per 9.2.6: prepayments are recovered during performance per the contract; absent or unclear agreement, recovery may be lump-sum or in installments after cumulative gross value reaches a set proportion of the contract price; in installments, proportional recovery from each payment period's progress or process-settlement payments until the agreed amount is fully recovered; on early termination, unrecovered prepayments are fully recovered at termination settlement.
5. Two cautions (9.1.7): (1) prepayment recovery shall comply with 9.2.6; safety-production measure prepayments comply with 9.3.2; (2) "progress payments shall not recover safety-production measure prepayments" — such prepayments are not deductible from progress payments and are handled separately. Also, absent an agreed payment ratio, the ratio should not be below 80% of cumulative completed gross value.
Applicable Boundaries
- Applies to interim contract payments under GB/T 50500-2024 for unit-price and lump-sum contracts (lump-sum provisional-quantity adjustments appear in row 1, sub-item 2).
- The standard is recommended (GB/T); contract agreement prevails; absent agreement, the standard applies.
- The six rows match 9.4.9; sector- or project-specific forms (e.g., railway work-verification forms, supervisor review forms) follow their own rules — this is the general form.
- The contractor fills the form and must attach calculation bases; construction workers' wages must be listed separately and paid in full and on time.
Further Reading
- GB/T 50500-2024: 9.1.7 (payment ratio; safety-prepayment), 9.2.6 (recovery modes), 9.4.9 (application contents and caliber), Appendix F Table F.3.1 and notes.
- Extensions: Section 9.2 (prepayment process), 9.3.2 (safety-production measure prepayment), 9.4.11 (undisputed part paid first), 10.2.4 (process-settlement payment ratio); linkage with GB/T 50319-2013 5.3.1 supervisor review and issuance.
- Practice companion: the start-recovery formula T = P - M/N (common practice per Cai Jian [2004] No. 369) — see prepayment recovery mechanism cards.