Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Calculation of progress payments (GB/T 50500-2024 §9.1/§9.4): the cumulative-difference method, the 11-item composition of cumulative completed value, and payment/deduction rules

Current payable progress payment = cumulative completed value to date − cumulative paid price − current deductions (GB/T 50500-2024 Clauses 9.1.6, 9.4.9); absent an agreed ratio, payment should be no less than 80% of cumulative completed value (9.1.7); the cumulative value comprises 11 items — contract BOQ price, BOQ errors/omissions adjustments, provisional sums, adjustments of provisional prices after procurement, main contractor's attendance and coordination provisions, dayworks, changes in costs, regulation/policy changes, variations, additional works, claims; the statutory safety provisions advance may not be recovered from progress payments (9.1.7, 9.3.2), advances recovered per the agreement (9.2.6); disputed items certified and paid first on undisputed parts (9.4.11); payment applications must list construction workers' wages separately (9.4.9).

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 Ch. 9
  • GB/T 50319-2013 建设工程监理规范 第5.3.1条
  • 保障农民工工资支付条例(国务院令第724号)

Topic Positioning

A card on calculating progress payments (interim payments): following GB/T 50500-2024, the China national pricing standard for BOQ, Sections 9.1 and 9.4 — the cumulative-difference master formula, the composition of cumulative completed value, the payment floor, the deduction rules, and application essentials.

Core Conclusions

  • Master formula (9.1.6, 9.4.9): current payable = cumulative completed value to date − cumulative paid price − current deductions (including the current advance recovery).
  • Cumulative completed value per 9.4.9, 11 items: contract BOQ price; BOQ errors/omissions adjustments; provisional sums; adjustments of provisional prices after procurement; main contractor's attendance and coordination provisions adjustments; dayworks; changes in costs adjustments; regulation/policy-change adjustments; variations; additional works; claim amounts.
  • Payment ratio: absent agreement, no less than 80% of cumulative completed value (9.1.7).
  • Recovery and bases of measurement: advances recovered per the contract, or at once or in installments if silent (9.2.6); the statutory safety provisions advance may not be recovered from progress payments — recovered once at final account (9.1.7, 9.3.2); prior cumulative payments follow the cumulative payable in the last payment certificate, regardless of gaps with actual disbursement (9.1.8); for disputed BOQ items, certify and pay first on undisputed parts (9.4.11).
  • The application (9.4.9) covers six items — cumulative completed value, cumulative recovered advances, cumulative payable progress payment, prior cumulative payments, employer deductions, current payable — and must separately state the current construction workers' wages, reported per Appendix F Table F.3.1.
  • Supervision side (GB/T 50319-2013 Clause 5.3.1): recheck quantities -> the chief supervision engineer issues the payment certificate, auditing six items including the executed contract price, variation/claim adjustments, advance recovery, and retention money deduction; the retention money base excludes advance recovery and price-adjustment amounts.

Applicable Boundaries

Applies to BOQ-priced works (building/municipal, etc.); railway measurement and valuation for payment systems differ — do not mix. Contracts prevail; 80% is a guiding floor, not a mandatory cap. Not for final account (listing per Clause 10.3.2) or post-termination settlement. Multi-year major projects prepay advances yearly per the annual plan (9.2.3).

Further Reading

See GB/T 50500-2024 Clauses 9.1.6-9.1.8, 9.2.2-9.2.6, 9.3.2, 9.4.4, 9.4.9, 9.4.11, Clause 10.2.10 (interim settlement by construction stage payment applications) and Appendix F Table F.3.1; GB/T 50319-2013 Clause 5.3.1; linking the Regulations on wage payment to migrant workers, Articles 24, 26, 29, 35 (labour cost disbursement at most monthly, dedicated accounts, employer advance liability).

Keywords

Cited By