Calculation of progress payments (GB/T 50500-2024 §9.1/§9.4): the cumulative-difference method, the 11-item composition of cumulative completed value, and payment/deduction rules
Current payable progress payment = cumulative completed value to date − cumulative paid price − current deductions (GB/T 50500-2024 Clauses 9.1.6, 9.4.9); absent an agreed ratio, payment should be no less than 80% of cumulative completed value (9.1.7); the cumulative value comprises 11 items — contract BOQ price, BOQ errors/omissions adjustments, provisional sums, adjustments of provisional prices after procurement, main contractor's attendance and coordination provisions, dayworks, changes in costs, regulation/policy changes, variations, additional works, claims; the statutory safety provisions advance may not be recovered from progress payments (9.1.7, 9.3.2), advances recovered per the agreement (9.2.6); disputed items certified and paid first on undisputed parts (9.4.11); payment applications must list construction workers' wages separately (9.4.9).
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 Ch. 9
- GB/T 50319-2013 建设工程监理规范 第5.3.1条
- 保障农民工工资支付条例(国务院令第724号)
Topic Positioning
A card on calculating progress payments (interim payments): following GB/T 50500-2024, the China national pricing standard for BOQ, Sections 9.1 and 9.4 — the cumulative-difference master formula, the composition of cumulative completed value, the payment floor, the deduction rules, and application essentials.
Core Conclusions
- Master formula (9.1.6, 9.4.9): current payable = cumulative completed value to date − cumulative paid price − current deductions (including the current advance recovery).
- Cumulative completed value per 9.4.9, 11 items: contract BOQ price; BOQ errors/omissions adjustments; provisional sums; adjustments of provisional prices after procurement; main contractor's attendance and coordination provisions adjustments; dayworks; changes in costs adjustments; regulation/policy-change adjustments; variations; additional works; claim amounts.
- Payment ratio: absent agreement, no less than 80% of cumulative completed value (9.1.7).
- Recovery and bases of measurement: advances recovered per the contract, or at once or in installments if silent (9.2.6); the statutory safety provisions advance may not be recovered from progress payments — recovered once at final account (9.1.7, 9.3.2); prior cumulative payments follow the cumulative payable in the last payment certificate, regardless of gaps with actual disbursement (9.1.8); for disputed BOQ items, certify and pay first on undisputed parts (9.4.11).
- The application (9.4.9) covers six items — cumulative completed value, cumulative recovered advances, cumulative payable progress payment, prior cumulative payments, employer deductions, current payable — and must separately state the current construction workers' wages, reported per Appendix F Table F.3.1.
- Supervision side (GB/T 50319-2013 Clause 5.3.1): recheck quantities -> the chief supervision engineer issues the payment certificate, auditing six items including the executed contract price, variation/claim adjustments, advance recovery, and retention money deduction; the retention money base excludes advance recovery and price-adjustment amounts.
Applicable Boundaries
Applies to BOQ-priced works (building/municipal, etc.); railway measurement and valuation for payment systems differ — do not mix. Contracts prevail; 80% is a guiding floor, not a mandatory cap. Not for final account (listing per Clause 10.3.2) or post-termination settlement. Multi-year major projects prepay advances yearly per the annual plan (9.2.3).
Further Reading
See GB/T 50500-2024 Clauses 9.1.6-9.1.8, 9.2.2-9.2.6, 9.3.2, 9.4.4, 9.4.9, 9.4.11, Clause 10.2.10 (interim settlement by construction stage payment applications) and Appendix F Table F.3.1; GB/T 50319-2013 Clause 5.3.1; linking the Regulations on wage payment to migrant workers, Articles 24, 26, 29, 35 (labour cost disbursement at most monthly, dedicated accounts, employer advance liability).
Keywords
- 工程进度款
- 进度款计算
- 累计差额法
- interim payment
- 累计完成工程总值
- 工程计量支付
- 进度款支付申请
- GB/T 50500-2024
- payment certificate
Related Cards
- →
Contractor cash-flow risk control when progress-payment review runs overdue: deemed approval of measurements, payment of undisputed portions, and four-layer defense (GB/T 50500-2024)
Review deadlines are not bottomless: absent contractual deadlines, GB/T 50500-2024 Article 7.1.5 establishes "overdue silence = measurement accepted," Article 9.4.11 "undisputed portions paid first," and Article 9.1.7 payment no less than 80% of cumulative completed work value; overdue non-payment supports claims under 9.4.12, and in extreme cases priority-of-payment under Civil Code Article 807 (exercisable within 18 months) and the Regulation on Payment to SMEs. Defense deploys across four layers: contract clauses - process management - legal remedies - self-rescue financing.
- →
Contractor's objection period and tiered remedies against final account review results (GB/T 50500-2024)
After receiving the settlement verification/review result, the contractor must raise itemized written objections within the agreed objection period (28 days absent agreement), failing which the result is deemed accepted (GB/T 50500-2024 Clauses 10.3.8, 10.3.10); if dissatisfied, escalate through the ladder: recheck → incomplete settlement first for undisputed parts → negotiation/professional conferencing → dispute review/mediation → administrative mediation (within one month) → arbitration/litigation, while continuing performance during the dispute.
- →
Quantifying advance-funding pressure when contract payment proportions are too low, and standard floors (GB/T 50500-2024: 80% progress payments, 10%-30% advance payment)
Every 10-point drop in the payment proportion adds roughly 10% of the contract amount in advance funding: peak advance = (1 - payment proportion) x contract amount; average advance ~= peak/2; annual financing cost ~= average advance x annual rate. GB/T 50500-2024: progress payments should not be below 80% of cumulative completed work value (9.1.7); in-process settlement not below 80% (10.2.4); advance payment not below 10% and not above 30% of contract price (9.2.2). Advance funding stacks migrant-wage, supply-chain, and tax-prepayment chain risks; the Regulation on Payment to SMEs (30/60-day terms and overdue interest) can be invoked for relief.
- →
Full workflow of agreeing and paying construction advance payments (GB/T 50500-2024 Section 9.2): nature, proportion, procedure, guarantee, and recovery
The construction advance payment (materials advance) is paid by the Employer before commencement for the Contractor's materials preparation - earmarked and interest-free. For labour-and-material contracts, the payment proportion should not be less than 10% of the signed contract price (net of provisional sums, dayworks and provisional sums for nominated specialist subcontract works) and should not exceed 30% of the signed contract price (for major multi-year projects, prepaid annually at the same proportion in accordance with the annual plan). The Contractor applies -> the Employer reviews and pays (an equal-value guarantee may be agreed); recovery is made as agreed in the contract, or, if not agreed, in one or more instalments; on termination of the contract, any unrecovered portion is recovered in full.
- →
Core differences between railway work-acceptance valuation and building progress payments: positioning, pricing basis, procedure, non-valuable list, and payment rules
Railway work-acceptance valuation is an investment-control tool (approved-estimate cap + supervisor review sign-off + investment completion reported level by level + five-item negative list of non-acceptable items + deduction of employer-supplied materials); building progress payment is a contract-price payment tool (the contract BOQ is the sole pricing basis; absent agreement, payment should not be below 80% of the cumulative completed value; undisputed portions paid first). Similar in function but entirely different in institutional foundation.
- →
Definition and cost composition of the all-in unit rate (GB/T 50500-2024 Clause 2.0.9, GB/T 50875-2013 Clause 2.2.58)
All-in unit rate = labour cost + material cost (including engineering equipment) + plant and small tools cost + overheads (company and site) + profit + risk cost within the agreed scope and range, required to complete one specified unit of measurement of a billed (BOQ) item; VAT is excluded (a price-exclusive tax). Basis: GB/T 50500-2024 Clause 2.0.9 and GB/T 50875-2013 Clause 2.2.58; building works BOQ-based pricing uses the "incomplete-cost" caliber excluding statutory levies and fees and taxes, while highways and other industries may use the fully loaded caliber including statutory levies and fees and taxes — confirm the applicable industry standard before citing.
Cited By
- ←
Whether quantities confirmed at the progress-payment stage can be re-measured and reduced at the final account: the line between provisional payment and lock-in (lock-in by signed measurement results, stage settlements absorbed into the final account, rough measurement as no basis for settlement)
No single answer; the determinant is the nature and level of the confirming document, not whether payment has been made: the three confirmations that are provisional in nature - issue of an interim payment certificate, provisional payment, and rough measurement (by physical progress or proportion) - may be re-measured and reduced at the final account (GB/T 50500-2024 Articles 9.1.14 and 9.4.14); once both parties sign the measurement results without limiting them 'for progress payment use only' (Article 7.1.8), or the interim settlement by construction stage documents have been signed (Article 10.2.3, 'the final account must not re-measure or re-price them'), the quantities are locked and may not be reduced, the sole exception being preliminaries and main contractor's attendance and coordination provisions, which must be recalculated under Articles 10.2.7 and 10.3.3; once the final account documents are signed and sealed by both parties, no repeated checking is allowed in any case (Article 10.3.12; Article 19 of MOHURD Decree No. 16).
- ←
Interim payment and final settlement of preliminaries: statutory safety provisions prepayment and recovery points (9.3.2 - at least 50% within 28 days of commencement), progress-payment methods (9.4.4 - agreed breakdown or element-works ratios), the three-stage preliminaries breakdown table (6.2.13, Appendix E Table E.3.3), interim versus final settlement (10.2.7, 10.3.3) and the three-class treatment in settlement review
Statutory safety provisions prepay at not less than 50% of the total within 28 days of commencement, the rest decomposed per the early-arrangement principle and paid with progress payments; computing progress payments never recovers the prepayment - it is recovered once at the final account (9.3.2). Preliminaries progress payments follow the parties' agreed breakdown; absent agreement, by the ratio of cumulative completed work-item list value to the work-item list total, the breakdown resting on Appendix E Table E.3.3 (initial set-up / mid-term running / late dismantling, 6.2.13, 9.4.4). Preliminaries listed in interim settlements serve only interim payment (10.2.7); the final account recomputes all preliminaries of the completed works per clause set 7.3 and chapter 8, including safety-provision adjustments - interim figures are no basis (10.3.3).
- ←
Reconciling the three output-value bases of construction output, measured output and settlement output: item-by-item basis distinction, four classes of difference attribution, the disallowance-and-resubmission tests, and the tie-out with stage settlement documents
Construction output value (physical-progress statistics basis), measured output value (contract basis of qualified quantities certified by the supervising engineer or employer) and settlement output value (contract entitlement basis) are three non-overlapping measurement boundaries; the aim of reconciliation is not to make the three figures equal, but - anchored on the measured output value - to place every difference item by item into the accounts of (1) not yet submitted, (2) measurement period not yet reached, (3) quality not yet confirmed, (4) variations not yet priced held in suspense (plus basis differences and permanent removals), until the residual is zero. Disallowance or resubmission must simultaneously pass the measurement-conditions tests (within the BOQ, an approved variation or dayworks scope; quality qualified with acceptance complete; per the contract calculation rules; within the measurement period; the variation priced or on a provisional price; the Notice of Claim issued within 28 days). Payment of interim settlement by construction stage shall be no less than 80% of the current stage settlement total (GB/T 50500-2024 clause 10.2.4), and stage settlement documents signed and confirmed merge into the final account without re-measurement or re-pricing (clause 10.2.3).
- ←
Whether completed but unaccepted sub-divisional work items can be measured and claimed for progress payment: the quality-pass threshold to measurement and the negative rules barring valuation, exceptions for causes not attributable to the contractor and the measurement of rework quantities, the timing distinction between pre-concealment measurement and the final account, and the deduction rules when quality failures are found after measurement
Passing quality acceptance is a substantive threshold to measurement, not a formality: the object of measurement must be 'qualifying work the contractor has completed per the contract requirements and that is to be measured' (GB/T 50500-2024 cl. 7.1.1), and work not accepted under the quality acceptance standards, or failing acceptance, is withheld from measurement and valuation for payment by the project supervision office (TB 10402-2019 cl. 6.0.6 item 2) -- so it can be neither claimed for measurement nor enter progress payment; after rectification, rework and a passed re-inspection, measurement resumes for the same location. The only exception sits on the responsibility side: rework caused by a variation or by employer responsibility is measured per the rework items and quantities fixed in the rework confirmation sheet and the costs are compensated (cl. 7.6.1, 7.6.4); rework quantities caused by the contractor are not measured and the costs are borne by the contractor. Measurement results not checked in time may be deemed approved, but must not serve as evidence that the works have been delivered as accepted (cl. 7.1.5); where a quality failure is found after measurement, the employer may deduct repair and rework costs in the final account (cl. 10.3.13) and, within the defects liability period, deduct repair costs from the retention money (cl. 10.5.3).
- ←
Node division modes, payment percentage floors and post-confirmation re-review rules for interim settlement by construction stage: GB/T 50500-2024 Clauses 10.1.3/10.2.3/10.2.4/10.3.15/10.5.1, Cai Jian [2022] No. 183 and local implementation documents
Nodes, procedures and methods are governed by the contract (GB/T 50500-2024 Clause 10.1.3), and the forms may be monthly/quarterly/annual/physical-progress nodes (Clause 2.0.35); policy and local documents refine this into three modes: fixed cycle, physical-progress nodes, and sub-section/segment/specialism. The payment percentage of interim settlement shall not be lower than 80% of the total interim settlement amount for the current period (Clause 10.2.4). The payable final account amount = final account total price - retention money withheld - cumulative amounts actually paid beforehand (Clause 10.3.15); the cumulative retention money, or the bond amount where a bond substitutes for it, must not exceed 3% of the total settlement price of the works (Clause 10.5.1), so where 3% is retained a single payment reaches 97% of the settlement total price and the cumulative payment reaches 100% on expiry of the defects liability period. Interim settlement documents signed and confirmed by both parties form part of the final account documents, and the final account shall not re-measure or re-price them (Clause 10.2.3); Cai Jian [2022] No. 183 words this as 'in principle not reviewed again after completion', and the documents of Xinjiang, Zhejiang and other places read 'not reviewed again' or 'in principle not reviewed again'.
- ←
The "double 80%" rule for progress-payment and in-process settlement payment ratios: GB/T 50500-2024 Clauses 9.1.7 and 10.2.4 vs GB 50500-2013 Clause 10.3.7 (60%-90%)
GB/T 50500-2024 raises the payment floor from 2013's 60% to 80% and removes the 90% cap, forming "double 80%": progress payments (9.1.7) - where the contract is silent, preferably not below 80% of the cumulative completed work value; in-process settlement payments (10.2.4, new in 2024) - not below 80% of the current in-process settlement amount. The two 80s differ in force: the progress-payment one is a fallback when the contract is silent ("preferably not below"); the in-process one is a floor that contractual agreement cannot breach ("shall not be below").
- ←
The advance-payment recovery mechanism: two recovery modes, the start-recovery-point formula, and related rules (GB/T 50500-2024 §9.2/9.1.7/9.3.2)
Advances are recovered per the contract; if unclear, either mode: one-time recovery (fully deducted once cumulative completed value reaches the agreed share of the contract price) or installment recovery (deducted proportionally from each progress payment or interim settlement by construction stage until the agreed amount). On contract termination, unrecovered portions are fully recovered in the termination settlement. The practice start-recovery-point formula T = P - M/N (from the Cai Jian [2004] No. 369 practice). Related: absent agreement, progress payments no less than 80% of cumulative completed value; the statutory safety provisions advance is not recovered from progress payments but once at the final account; the guarantee decreases as recovery proceeds and is returned when fully recovered.
- ←
Composition differences between interim settlement by construction stage and the final account: stage settlement on three elements plus a five-item payment application, the final account on 13 listed items (GB/T 50500-2024 clauses 10.2 / 10.3)
Interim settlement by stage prices at settlement nodes: its composition = the relevant contract sums within the total price for the period or node + the contract adjustments agreed by the parties, less contractor-cause liquidated damages (clause 10.2.1); the payment application follows the five items of clause 10.2.10 on 'cumulative completed price - cumulative paid - current deductions'. The final account is compiled per clause 10.3.2 as 13 items in order (contract BOQ total - BOQ errors, provisional sums, provisional prices, main contractor's attendance, dayworks, price fluctuation, law and policy changes, variations, additional works, claims, damages, others). Stage settlement files signed by both parties form part of the final account and are not re-measured or re-priced (clause 10.2.3) - only preliminaries and the main contractor's attendance provisions are recomputed per clause 10.3.3.
- ←
Stepwise procedure, stage time-limits and measurement-dispute routes for progress payment measurement and payment (GB/T 50500-2024 Sections 7.1, 9.1 / 9.4, Chapter 11; comparison with GB 50500-2013)
Progress payment measurement and payment turns on measurement period = payment period, in four steps: 1 the contractor submits measurement outputs and the payment application per measurement period and payment verification date (GB/T 50500-2024 Articles 7.1.5, 9.4.9); 2 the employer checks in writing and the contractor confirms in writing or submits review comments; failure to provide check / re-check results in time deems the contractor's outputs (or comments) accepted (7.1.5, 7.1.6), sign-off per 7.1.7; 3 the payment certificate goes to the contractor for confirmation first (9.1.10); the employer issues the certificate after checking within a reasonable time, pays the undisputed part first where some items are disputed (9.4.11), and pays before the contractual latest payment date (9.1.11); 4 failing agreement after checking, review and re-check, Article 7.1.7 routes to Chapter 11 - negotiation, dispute review or mediation, then arbitration or litigation (11.1.1, 11.1.2). The 2024 edition mostly says agreed time; the concrete day-counts (7-day verification, 24-hour notice, 7-day objection and re-check, 14-day certificate) appear only in the repealed GB 50500-2013 Articles 8.2.3 / 8.2.4 / 8.2.5 / 8.3.5 and 10.3.9, for comparison only.
- ←
Advance payment rules for the statutory safety provisions (mandatory health, safety and environmental (HSE) provisions) compared: GB 50500-2013 Clause 10.2.2's 60% vs GB/T 50500-2024 Clause 9.3.2's 50%, no recovery from progress payments, one-time recovery at final account
The advance percentage for the mandatory health, safety and environmental (HSE) provisions (renamed "statutory safety provisions" in the 2024 standard) has dropped from 60% to 50%: GB 50500-2013 (repealed) Clause 10.2.2 required an advance of not less than 60% of the current year's planned total within 28 days of commencement; GB/T 50500-2024 (current) Clause 9.3.2 changes this to not less than 50% of the total and adds the explicit recovery rule that "the advance for the statutory safety provisions shall not be recovered when computing progress payments due and shall be recovered in one lump sum at final account". The advance window (within 28 days of commencement) is unchanged.
- ←
Prepayment and payment rules for statutory safety provisions (GB/T 50500-2024 Clauses 9.3.2, 9.3.3): not less than 50% prepaid within 28 days of commencement, paid alongside progress payments, recovered in one lump sum at final account
Under Clause 9.3.2 of GB/T 50500-2024, the China national pricing standard for BOQ, the employer shall, within 28 days after commencement, prepay to the contractor not less than 50% of the total statutory safety provisions; the remainder shall be broken down on the "arrange in advance" principle and paid alongside progress payments; for multi-year major works the prepaid total may be broken down by reference to the annual programme of works. When computing progress payments due, the prepaid safety provisions shall not be recovered; they are recovered in one lump sum at final account. Clause 9.3.3: where the employer fails to pay by the agreed time, the contractor may give notice; if payment is still not made within the agreed period after such notice, the contractor is entitled to suspend the works and the employer bears liability for breach of contract; where a safety accident occurs because the employer failed to pay the statutory safety provisions on time, the employer bears the corresponding responsibility.
- ←
Should the construction-installation cost in a design estimate carry provisional sums? — the stage division of provisional sums (BOQ/contract level) vs reserve funds (estimate level)
No. The construction-installation cost (works cost) in a design estimate must not carry provisional sums. Provisional sums are a contract-price account of BOQ pricing (construction tendering and implementation) (defined in GB/T 50500-2024, 2.0.13; scope limited by 1.0.2; employer-controlled, unused portions revert, 8.3.1); the estimate's uncertain/unforeseeable costs are carried by the reserve funds (basic + price-difference) in the total estimate, whose composition — works costs + other construction costs + reserves + construction-period loan interest + VAT (T/ZBD 100.3-2022, 4.1.1 and Annex A) — has no "provisional sum" account.
- ←
The contractor's four-level remedy ladder when the owner delays payment (demand -> suspension and claims -> administrative complaint -> termination/priority of payment)
Four escalating levels — "gentle demand -> pressure by suspension -> administrative complaint -> legal remedies": (1) written demand (GB/T 50500-2024 §10.2.12/§10.3.17) + undisputed portion first (§9.4.11) + overdue interest (Decree No. 728, Article 15: agreed rate no less than the 1-year LPR, 0.05% per day absent agreement); (2) statutory suspension rights (prepayment §9.2.4, safety measure fees §9.3.3) + 28-day dual-node claims (§9.4.12); (3) complaint to the SME authority (Decree No. 728, Article 17, with credit blacklisting); (4) termination + priority of payment for the project price (Civil Code Articles 563/807, 18-month exclusion period).
- ←
Determining the progress-payment ratio and the payment sign-off procedure (GB/T 50500-2024 §9.1/§9.4 + GB/T 50319-2013 §5.3.1)
The ratio is set by three layers — "contract agreement first -> national-standard floor -> local mandates": absent agreement, no less than 80% of cumulative completed value (9.1.7); current payable = cumulative completed price - cumulative paid - current deductions (9.1.6, 9.4.9); the work-safety measure advance is not recovered from progress payments (9.3.2); the procedure runs contractor applies -> specialty supervision rechecks -> chief supervision engineer endorses -> employer approves -> chief supervision engineer issues the certificate (GB/T 50319-2013 §5.3.1); the retention base excludes advances and price-adjustment amounts.
- ←
Full process of construction payment: advance payment, safety-measures fee, progress payment, interim settlement by construction stage, final account, retention money and final settlement (GB/T 50500-2024 Chapters 9-10)
Payment along the timeline in six segments: advance payment (for works with contractor-procured materials, neither below 10% nor above 30% of the contract price after deducting provisional sums etc., prepaid before commencement, recovered as agreed) → statutory safety provisions (at least 50% prepaid within 28 days after commencement; not deducted from progress payments, recovered once at the final account) → progress payments (amount due = cumulative completed − cumulative paid − deductions; not less than 80% of the cumulative completed value where the contract is silent) → interim settlement by construction stage (new in 2024: signed stage settlements enter the final account without re-pricing; stage payments not below 80%) → final account (thirteen heads; failure to check or to certify in time is deemed acceptance) → retention money (3% cap) and final closure (defects liability period generally 1 year, 2 at most). The chain runs on contract-agreed time limits with a 28-day backstop; judicial enforcement of "accepted at the submitted price" requires an express contractual provision.
- ←
Appendix F Table F.3.1 progress-payment application (approval) form of GB/T 50500-2024: structure, six reporting items, and prepayment deduction entries
Table F.3.1 is a six-row form (each row with application/verification amount columns) matching the six items of 9.4.9: (1) cumulative completed gross value (11 sub-items), (2) cumulative recovered prepayments (incl. current), (3) cumulative payable progress payment, (4) prior cumulative paid progress payments, (5) amounts the employer should deduct, (6) current payable progress payment. Prepayment deduction goes in row 2 "cumulative recovered prepayment" (cumulative figure); current deduction = current cumulative minus prior cumulative, also part of row 5; progress payments shall not recover safety-production measure prepayments (9.1.7). Four copies; preparer and Grade-1 registered cost engineer sign and seal; contractor representative, supervising engineer, and employer representative sign or seal.
- ←
Measurement linkage between GB/T 50500-2024 and the nine measurement standards GB/T 50854-50862-2024: responsibilities, cycles, and the division of procedures (procedures to the pricing standard, quantity take-off to the measurement standards)
GB/T 50500-2024 and the nine measurement standards (GB/T 50854-50862-2024) interlock by mutual delegation on measurement: 50500 7.1.1 states quantities "shall be calculated per the national and industry measurement standards and supplementary rules agreed by the parties" (take-off to the measurement standards); 50854 3.0.2 reciprocally requires measurement during implementation to also comply with GB/T 50500 (procedures to the pricing standard). Measurement responsibilities (contractor written submission -> employer written verification -> mutual deemed acceptance, 7.1.5/7.1.6; per-cycle summary sign-off 9.4.13), measurement cycles (cycle aligned with payment cycle, monthly fallback when unclear, 9.4.1; milestone measurement 7.1.2; price-adjustment segmented measurement 7.1.3) are all governed by 50500 Chapter 7 and Section 9.4; the nine standards cover only item classification, units, and appendix calculation rules (50854 4.2.6: per Appendices A-Q).
- ←
GB/T 50500-2024: both progress payments and process-settlement payments floored at 80% — the wording contrast between 9.1.7 "should not be lower" and 10.2.4 "shall not be lower"
Under GB/T 50500-2024, the payment-ratio floors for progress payments and construction-process settlement payments are both 80%, with different force: Clause 9.1.7 on progress payments — "where the contract does not state a payment ratio for the works value, the ratio should not be lower than 80% of the cumulative completed works value" — "should" is recommendatory: agreement prevails, the 80% floor applies only absent agreement; Clause 10.2.4 on process-settlement payments — "the payment ratio shall be agreed in the contract and shall not be lower than 80% of the current process-settlement total" — "shall not" is a prohibitive hard floor: even an agreed ratio below 80% fails the standard. The bases differ: progress payments on "cumulative completed works value", process-settlement payments on "current process-settlement total".
- ←
The relation between measurement and payment: quantities fixed before payment (the causal chain of GB/T 50500-2024 Chapters 7 and 9)
Measurement is the precondition and quantitative basis of payment, and payment is the monetary realization of the measurement result: progress payment = confirmed measured quantities x all-in unit rates; measurement results, once checked and confirmed by both parties, serve as the basis for computing the price but not as a basis for acceptance of conforming delivery; the measurement period should coincide with the payment period; for disputed BOQ items, payment certificates are issued and payment made first on the undisputed portion.
- ←
The employer's time requirement for reviewing progress payments (GB/T 50500-2024 §9.1/§9.4): the reasonable-time fallback, the certificate-confirmation procedure, and common deadline conventions
GB/T 50500-2024 sets no fixed review days: Clause 9.4.11 requires the employer to check within a "reasonable time" after receiving the progress-payment application and issue the payment certificate, with disputed items paid first on undisputed parts; Clauses 9.1.10/9.1.11 form the procedural chain "draft certificate first to the contractor for confirmation + contract-agreed latest payment date". Specific deadlines rest on the contract — the model text GF-2017-0201 general-conditions convention: supervision 7 days + employer 7 days (late deemed acceptance); government and public-institution employers are further bound by the "Regulations on Payment to Small and Medium Enterprises" (State Council Order No. 802) 30/60-day payment limits.
- ←
GB/T 50500-2024, China's BOQ pricing standard: positioning, 2024-vs-2013 changes, chapter map and card-group navigation
GB/T 50500-2024, the China national pricing standard for BOQ-based pricing (MOHURD Announcement No. 212 of 2024, approved 26 November 2024), came into force on 1 September 2025 and repealed GB 50500-2013. Its status shifted from a partly mandatory code to a recommended national standard (GB to GB/T), aiming to regularise pricing rules and let the market form construction costs. It governs pricing activity in tendering, contracting and execution for construction works; EPC and other general-contracting models apply it by reference, and the requirement that state-funded projects use BOQ pricing is carried by a MOHURD ministerial order. Nine headline revisions (per the foreword): risk scope and allocation rules by contract form; a new bid clarification mechanism; revised pricing of preliminaries; the 'contract price agreement' chapter replaced by contract selection and requirements; revised measurement and adjustment rules; site visas abolished and additional-works pricing introduced; interim settlement by construction stage added; dispute resolution revised; the cost-expert-assessment chapter deleted. The structure was rebuilt from 16 chapters into 12 chapters plus annexes: 'tender control price' renamed tender price ceiling; completion settlement and contract-termination settlement merged into 'works settlement and payment' (absorbing stage settlement); dispute resolution and expert assessment merged; pricing tables moved to annexes (with a new Annex G, schedule of price-adjustable key materials).