The employer's time requirement for reviewing progress payments (GB/T 50500-2024 §9.1/§9.4): the reasonable-time fallback, the certificate-confirmation procedure, and common deadline conventions
GB/T 50500-2024 sets no fixed review days: Clause 9.4.11 requires the employer to check within a "reasonable time" after receiving the progress-payment application and issue the payment certificate, with disputed items paid first on undisputed parts; Clauses 9.1.10/9.1.11 form the procedural chain "draft certificate first to the contractor for confirmation + contract-agreed latest payment date". Specific deadlines rest on the contract — the model text GF-2017-0201 general-conditions convention: supervision 7 days + employer 7 days (late deemed acceptance); government and public-institution employers are further bound by the "Regulations on Payment to Small and Medium Enterprises" (State Council Order No. 802) 30/60-day payment limits.
Applicable Codes
- GB/T 50500-2024 第9.1.6~9.1.11条
- GB/T 50500-2024 第9.4.9~9.4.12条
- GF-2017-0201 通用条款第12.4.4条
- 保障中小企业款项支付条例(国务院令第802号)
Topic Positioning
Answers "within what time must the employer review progress payments": the normative structure of review deadlines under GB/T 50500-2024 — the standard itself sets no fixed days; deadlines rest on the contract, with "reasonable time" as the fallback.
Core Conclusions
- GB/T 50500-2024 Clause 9.4.11: the employer shall check within a "reasonable time" after receiving the progress-payment application, issue the progress payment certificate upon confirmation, and pay on time; for BOQ items disputed in measurement or pricing, certify and pay first on the undisputed parts.
- Supporting chain: Clause 9.1.10 — before issuing a payment certificate, the employer gives the draft certificate to the contractor for confirmation (written confirmation if no objection; a review report if objection, checked with the employer); Clause 9.1.11 — pay the certified progress payment by the contract-agreed latest payment date or earlier; late payment is claimable under Clause 9.4.12.
- Common deadline references: the model text GF-2017-0201 general conditions 12.4.4 convention — supervision reviews within 7 days, the employer approves within 7 days, failure to issue the payment certificate deemed acceptance of the contractor's application; government/public-institution employers are bound by the "Regulations on Payment to Small and Medium Enterprises" (State Council Order No. 802, effective 2025-06-01): payment within 30 days of delivery, at most 60 days if agreed, 60 days for large enterprises; late interest no lower than the 1-year LPR, or 0.05% per day absent agreement.
- Absent an agreed ratio, progress payments should be no less than 80% of cumulative completed value (Clause 9.1.7).
Applicable Boundaries
- "Reasonable time" is a fallback expression — concrete days must be fixed in the particular conditions (7-14 days for checking plus deemed-acceptance recommended); the model text and the regulations are external references that do not change the standard's own lack of fixed days.
- The 30/60-day rules apply only where the employer is a state organ, public institution, or large enterprise and the contractor an SME; government-invested projects may not refuse or delay payment on grounds of incomplete audit.
- Computation of payment amounts (cumulative difference, 11 items) and advance/measure-advance recovery rules are covered by other cards.
Further Reading
- GB/T 50500-2024 Clauses 9.1.6-9.1.11 (progress payment computation and payment procedure), Clauses 9.4.9-9.4.12 (application, review, and claims)
- "Model construction contract text" GF-2017-0201 general conditions Clause 12.4.4
- "Regulations on Payment to Small and Medium Enterprises" State Council Order No. 802 (2025 revision, superseding No. 728)
Keywords
- 进度款审核时限
- 合理时间
- 进度款支付证书
- deemed acceptance / deemed approval
- Regulation on Ensuring Payment to Small and Medium-sized Enterprises
- GF-2017-0201
- interim payment